I scored 60% on this pre-assessment. I hope I can do better on the real PMP exam. Excellent questions. Good luck to everyone preparing for their exam!
@ankitseksaria14 сағат бұрын
Excellent video, Q & A, feeling more confident
@DevilPandaGamingYT14 сағат бұрын
QT 127: James is a technical Project Manager who recently completed an important milestone on his project. The Customer was very happy with the product and even started thinking about giving the maintenance contract to James. But, before accepting the new contract, James wants to close the project. Which of the following activities is not part of the project closure? A: Conducting the final lessons learned meeting and documenting in the lessons learned register. | B: Finalizing open claims from the Vendors. • C: Getting deliverables acceptance from the Customer and formal sign off. • D:Release of organization resources. B: Finalizing open claims from the Vendors. Explanation: Finalizing open claims from vendors relates to the procurement process and dealing with outstanding contractual obligations, but it's typically handled before the formal project closure. Project closure focuses on activities like reviewing and documenting lessons learned, obtaining formal acceptance and sign-off from the customer, and releasing project resources. Finalizing open vendor claims may be more appropriate as part of the contract management or procurement closure process, which may precede or run parallel to project closure but isn't directly a closure activity.
@tharanin728219 сағат бұрын
Scenario 1 : Dormancy Risk is Realized ,but we need some time perform some simulation. So the time is elapsed. Days - 3 days. Scenario 2 : Connectvity Issue is connected to lots of other modules which may impact other modules as well. Scenario 3: Proximity In next 30 days the risk is going to impact the project deliverables. Scenario 4: Urgency Risk response plan is ready and that should be implemented in 20 days.
@mintelixir244121 сағат бұрын
I wish each question had a reference in PMBOK 7 to be able to read more about the topic.
@Soyabeans1000Күн бұрын
Excellent video!
@dipankarmondal1468Күн бұрын
4/5
@fpvtec30Күн бұрын
You helped me become more confident in my journey to become a PMP pro. I appreciate you and I thank you sincerely.
@EstherAbdallah-fb9keКүн бұрын
Hi Varun, thanks for taking time to create this simulation/mock exams. However, it's quiet easier and different from the PMI Study Hall Practice. I don't feel confident writing my exam tomorrow
@EduHubSpotКүн бұрын
Do share the good news with us. I am sure this video will help you tomorrow. Varun
@UmairKhan-hc2ql2 күн бұрын
Q2 Scenario 1: Judging Scenario 2: Perceiving
@EduHubSpotКүн бұрын
Awesome Job !! Gautham
@UmairKhan-hc2ql2 күн бұрын
Q1 Scenario 1: Introvert Scenario 2: Extrovert
@EduHubSpotКүн бұрын
Very Impressive !! Gautham
@sanjeevkonnur33722 күн бұрын
Hi Gautham Thanks a lot for the clear explanation. I went nostalgic as it took me 18 years back, as I studied these motivation theory topics during Engineering ( Organizational Behavior)😊 Question 1 - Shevi is following theory X As the work is repitative, and shevy is closely monitoring the team Vihaan is following Theory Y As the the work us related to R&D, Team members are self motivated as the product will bring revolution. And Vihaan is self organizing the team. Question 2 Shanthi is trying to satisfy "Esteem" need, as she is looking for a promotion.
@EduHubSpotКүн бұрын
That is exactly how you should think. Gautham
@Shahabayesha2 күн бұрын
Thank you Gautam. Scored 3/5
@ndingwanjuliette72842 күн бұрын
How can I get into the Education whatapp group ?
@EduHubSpotКүн бұрын
Kindly share your name & number so we will add you in the group. Team EHS
@rafiatobehi63162 күн бұрын
Thank you so much Eduhubspot for all that you do. Although your practise questions were tough, they were key in preparing my me for the exam. I’m happy to say I passed AT in all domains. Please if you all are reading this, get his mock exam questions on his website. They were truly a gamechanger for me!
@Ravibadade2 күн бұрын
Hello Sir, I have over all 6 years of experience in Travel Management, Office Administration I want to make move to Project Management Shall i go for PMP certification or CAPM If you can suggest me please
@EduHubSpotКүн бұрын
Yes you can absolutely do that. Kindly send me an email directly and I will ask someone from our mentoring team to call you and explain the process in detail: [email protected] Or you can fill the contact us form on the website and someone will reach out to you within 24 hrs www.eduhubspot.com/about-us/contact-us Varun
@cosmaschuks76232 күн бұрын
Could you speak clarify on question 136 as your spoken words seems to differ from the chosen marked answer by your team. Which should I take as the correct answer please. Finish to start ( Which is my preference) or Finish to finish
@EduHubSpotКүн бұрын
Thanks for pointing out the graphical error. Correct Answer B Varun
@shanmugasundaram99263 күн бұрын
S-1 is Dormancy - Risk was realized already, S-2 is Connectivity - This Risk is connected to other modules, S-3 is Proximity - Identified the Risk, S-4 is Risk Response plan is identified for the Risk.
@EduHubSpotКүн бұрын
Very Impressive !! Gautham
@nandhiniselvakumar66913 күн бұрын
Hi, I have cleared my PMP exam with 2 ATs, and this video is the only source of my last min preparation. Very insightful questions which gave me right mindset to resolve the actual PMP questions. Thank you so much for all the efforts in creating such an amazing video.
@EduHubSpotКүн бұрын
Many Congratulations!! I am super happy after reading this comment as our video has helped you in your PMP journey. Varun
@SarahJohnson-c7k3 күн бұрын
Buzz Aldrin! 2nd man to walk on the moon!
@EduHubSpotКүн бұрын
Thanks for sharing !! Varun
@akbalfirose3 күн бұрын
Gautham Iam with you
@EduHubSpotКүн бұрын
Thank you so much !! Gautham
@zobekguerrero13663 күн бұрын
Havent watched the video yet, but I already Thumbs up the video 🙂
@EduHubSpotКүн бұрын
Thanks in advance for the comment and do watch the video. Varun
@zobekguerrero1366Күн бұрын
Finished watching. I picked D. I thought the team would need to find out the root cause of why the architectural design doesn't work. B, makes sense after the explanation. Ty
@simonoganga95353 күн бұрын
Wow!! The questions were so tough and tricky, they put me out of my comfort zone, I have to repeat it to understand the logic and processes. Thanks Varun and Team.
@EduHubSpotКүн бұрын
I am glad you loved the video. Varun
@maryamyusufbayero4 күн бұрын
B
@maryamyusufbayero4 күн бұрын
B
@maryamyusufbayero4 күн бұрын
A
@maryamyusufbayero4 күн бұрын
D
@maryamyusufbayero4 күн бұрын
B
@zobekguerrero13664 күн бұрын
I like when he says "you know" mid sentence such as 1:01:30 😂
@EduHubSpot4 күн бұрын
@@zobekguerrero1366 Hahah. In the end, you know what matters? That concept should go straight to head. Hahah Varun
@anupillai11974 күн бұрын
Great explanation Gautham.. Q1 - Scenario 1 - Shevi is following authority type and the the work is repetitive and providing rewards hence Theory X - Scenario 2 - Vihaan is following theory Y, because the project is innovative type and entire team is self motivated. Q2 - Shanti is looking for a promotion which falls under Esteem category
@EduHubSpotКүн бұрын
Loving your thought process. Gautham
@atlg_ff19834 күн бұрын
Q1: Scenario 1 - Theory X as this is a monotonous work pattern; Scenario 2 - Theory Y as this is an dynamic work pattern; Q2: Esteem Needs for Promotion
@EduHubSpotКүн бұрын
That is exactly how you should think. Gautham
@dipankarmondal14684 күн бұрын
5 0ut of 5
@LeticiaBuchanan-w7r5 күн бұрын
HW#1 (112/180) 62.22%
@EduHubSpotКүн бұрын
Very impressive !! Thanks for your participation !! Varun
@piyushniraula63435 күн бұрын
In Q115, How come we are submitting a change request for a agile project?
@piyushniraula63435 күн бұрын
In question when the new stakeholder is not attending any meetings, how can we select the option of conducting a meeting to understand right, shouldn't the answer be B?
@piyushniraula63435 күн бұрын
Hi Varun, in question 67, shouldn't the answer be A. Update the issue log with Paul's feedback, since all the stakeholders are already discussing the impact together?
@amungunngando4056 күн бұрын
For question 8, isn't the release planning meeting mentioned in ans (D) the same as the sprint planning meeting mentioned in ans (A). And with that in mind, isn't A a better option to D?
@Adam-Eaton6 күн бұрын
15/15
@EduHubSpotКүн бұрын
Very Impressive !! Gautham
@kaushiksaha5216 күн бұрын
I Scored 20%
@EduHubSpotКүн бұрын
Keep up the good work !! Thanks for your participation !! Varun
@chaitu054347 күн бұрын
Kudos Gautham. This is an ultimate reference video on Agile overall process flow. I love the way you connected the dots . It helps lot for PMP prep aswellas on the realtime implementation of agile
@EduHubSpot6 күн бұрын
I am glad that you loved the video. Gautham
@rameshaafridi30507 күн бұрын
hi , Came here to say that Allahumduillah i have cleared PMP with 2AT/T and i am so so grateful for all the support that i have gained from your videos. I have tagged you in my linkedin status too - would appreciate a comment on that too :) thanks alot for your support!! yayyy Allah all mighty has helped me alot :)
@EduHubSpot6 күн бұрын
Hearty Congratulations !! This is really great news and i am glad that our videos has helped you in your PMP journey. Gautham
@rameshaafridi30507 күн бұрын
hi Varun and team , Came here to say that Allahumduillah i have cleared PMP with 2AT/T and i am so so grateful for all the support that i have gained from your videos. I have tagged you in my linkedin status too - would appreciate a comment on that too :) thanks alot for your support!! yayyy Allah all mighty has helped me alot :)
@EduHubSpot6 күн бұрын
Many Congratulations!! I am super happy after reading this comment as our video has helped you in your PMP journey. Varun
@sindhuragada42367 күн бұрын
Scenario 1: John is postponing the work until last minute which student syndrome. Scenario 2: John started the work but he is filling up the time left for completion of given task with other stuff which is parkinsonlaw
@EduHubSpot6 күн бұрын
Very impressive!! Gautham
@sindhuragada42367 күн бұрын
Question1 Scenario 1 : Since its a repetitive work, and everyday meetings indicate closely micro managing so the Answer is Theory X style Q 1 Scenario 2: The project involves working with cutting edge technology which itself is motivating for the team so this is Theory Y Q2: Shanti is trying to satisfy her Esteem. Promotion is the keyword for. esteem needs
@EduHubSpot6 күн бұрын
Loving your thought process. Gautham
@sindhuragada42367 күн бұрын
Number of defects found. - This is Collecting facts - so it is WP Data Finish dates of activities - This is a collection of dates which is WP Data. Deliverable status. - This is collecting Status of showing the actual work, so it is WP information. Number of change request completed. - This is showing actual change request, progress so it is information that can be used in reports. Implementation status of change request. Status reports representing implementation status of change request. - As it is a report of information, this falls under WP report. Electronic dashboard representing deliverable status. - As it is electronic representation of project status and information, this is WP Report.
@EduHubSpot6 күн бұрын
That is exactly how you should think. Gautham
@prachigarg59289 күн бұрын
I have just started preparing 2 days and dont have much knowledge abt predictive process but still i got 9/15 which is 60%. I will retry after 1 month ,taking the lectures, notes, hopefully will be able to get 100%.
@EduHubSpot6 күн бұрын
Awesome job !! Gautham
@urslabrownmkeh15389 күн бұрын
I am writing on 9/26/24. I learned a lot from this video. The configuration management plan, and how to identify when it's a management plan question. Thank you!
@prachigarg59289 күн бұрын
Today is 24 sep , not 26 dear. Best of luck.
@EduHubSpot6 күн бұрын
Thanks for loving the video. Gautham
@urslabrownmkeh15389 күн бұрын
12/15, thank you.
@EduHubSpot6 күн бұрын
Very impressive !! Gautham
@Yajnesh_K-b3t9 күн бұрын
As part of HW 01 - scored 56.66% (102/180).
@EduHubSpot6 күн бұрын
Good job !! Thanks for your participation !! Varun
@ibrahimabed19769 күн бұрын
I passed my PMP Exam yesterday from the first attempt , thank you for all your effort i have learned from you a lot, your explanations and questions where extremely helpful and the content you are providing are amazing, I really appreciate it and thank you once again!!!
@EduHubSpot9 күн бұрын
Many Congratulations!! I am super happy after reading this comment as our video has helped you in your PMP journey. Varun