Significant progress was made on the South Circuit, with subbase placement nearly complete and the edge drain system fully installed, setting the stage for paving. Infrastructure work includes the completion of utility conduits, stormwater basin stabilization, and connections to grid power. Garage condos are also moving forward, with Building 7 nearing full enclosure and materials for buildings 1 and 2 set to arrive next month.