Earned Schedule- An improvement to EVM Scheduling Metrics

  Рет қаралды 14,936

Project Control Academy

Project Control Academy

6 жыл бұрын

Earned Value Management (EVM) is a powerful tool for evaluating the schedule and cost performance of projects and predicting future results. However, existing earned value schedule performance metrics (SPI & SV) does not do a good job with schedule performance evaluation and prediction. Use of Earned Schedule enhances the earned value management ’s ability to accurately represent and forecast schedule information. Watch this video training to learn how.
Get the full video training, summary, transcript, podcast link, mp3 download, shareable quotes, and other posts related to this episode and topic at www.projectcontrolacademy.com...
--------------------
FREE RESOURCES
--------------------
Listen to The Project Control Mastery Podcast on iTunes: itunes.apple.com/us/podcast/p...
Learn How to Succeed in Project Controls and Grow Your Career: projectcontroltraining.com/tr...
Get free training series on Earned Value Management at www.projectcontroltraining.com...
Get access to 6-weeks of free training on PMP certification at projectcontroltraining.com/pmp...
--------------------
CONNECT WITH SHOHREH & PROJECT CONTROL ACADEMY:
--------------------
www.projectcontrolacademy.com/
/ projectcontrolacademy
/ shohrehghorbanifan
/ projectcontrolacademy
/ shohrehghorbani
--------------------
ABOUT THE INSTRUCTOR, SHOHREH GHORBANI
--------------------
Shohreh Ghorbani is an internationally recognized program developer and instructor in the field of Project Controls. As the founder and director of Project Control Academy, the leading provider of comprehensive and practical trainings in project controls and earned value management, Shohreh has served thousands of professionals to take their project controls skills to the next level. With her impressive track record in teaching and years of hands-on experience on a broad range of project control technical areas in various industries, clients have acknowledged Shohreh as a subject matter expert and passionate trainer who transfers the knowledge of project controls in a simple and understandable manner. Shohreh is a licensed project management professional (PMP) recognized by Project Management Institute (PMI) and a professional member of American Association of Cost Engineers (AACE). She holds a Master of Science in Industrial Engineering.
Meet her at www.projectcontrolacademy.com/
--------------------
ABOUT THE PROJECT CONTROL MASTERY
--------------------
The Project Control Mastery is a weekly training on #ProjectControls, where you learn how to master your skills and knowledge in Project Controls and grow your career to the next level of success.
-------------------
SUBSCRIBE!!
--------------------
Subscribe to KZbin: / projectcontrolacademy
Subscribe to iTunes podcast: itunes.apple.com/us/podcast/p...
Join the newsletter & receive new training videos in your mailbox: projectcontroltraining.com/tr...

Пікірлер: 44
@mrrownel
@mrrownel 6 жыл бұрын
I commend you on the clarity which you spoke and the simply and effective way in which you explained. Excellent video! Thank you and well done!
@Projectcontrolacademy
@Projectcontrolacademy 6 жыл бұрын
Many thanks, Pernel for your positive feedback. Much appreciated.
@haroonmohammed4265
@haroonmohammed4265 4 жыл бұрын
Planned Value curve in the graph for the later part of explanation is suppose to reach 1M at the planned duration, month 6 and the EV extending to the actual duration, month 9. apart from that, very informative. Thankyou.
@pallavisalunkhe9049
@pallavisalunkhe9049 3 жыл бұрын
Detailed explanation. Appreciated. Thank you
@Projectcontrolacademy
@Projectcontrolacademy 3 жыл бұрын
Our pleasure, Pallavi.
@chonadocumento1664
@chonadocumento1664 6 жыл бұрын
Tons of thanks! Very impressive presentation of each topic. God bless!
@Projectcontrolacademy
@Projectcontrolacademy 6 жыл бұрын
Many thanks for your positive feedback Chona. Much appreciated.
@MikayilRAHIMOV
@MikayilRAHIMOV 6 жыл бұрын
Hi Shohreh, Appreciated your effort.Perfect!.Well explained.
@Projectcontrolacademy
@Projectcontrolacademy 6 жыл бұрын
Thanks Mikayil for your support. Much appreciated.
@hammon8108
@hammon8108 6 жыл бұрын
Very detailed explanation, you made sure you speak slowly and with emphasis to important words. Good luck, looking forward to see more video.
@Projectcontrolacademy
@Projectcontrolacademy 6 жыл бұрын
Thanks Li Namnam.
@kgpramanick636
@kgpramanick636 6 жыл бұрын
in later part, the planned curve ( green line) is also extended to meet the actual curve ( red ), in fact the green line should remain as it is.
@Projectcontrolacademy
@Projectcontrolacademy 6 жыл бұрын
Thanks for your attention Kg. Good observation. You are absolutely right. The PV curve should have been stopped at month 6. The calculations are right though.
@chin3884
@chin3884 5 жыл бұрын
I also got confused then.
@udathaxyz
@udathaxyz 6 жыл бұрын
Excellent explanation. Very interesting and understandable. Very well rendered.
@Projectcontrolacademy
@Projectcontrolacademy 6 жыл бұрын
Thanks, Udatha. Glad to hear that it was easy to understand.
@hardiyanto254
@hardiyanto254 6 жыл бұрын
Earned Schedule more make sense than Earned Value. Good explanation. Thank you
@Projectcontrolacademy
@Projectcontrolacademy 6 жыл бұрын
That's right Hardiyanto. Thank you.
@akhild69
@akhild69 11 ай бұрын
We can look at introducing BAC (t) , ETC (t) & EAC(t) metrics to forecast completion times similar to Cost forecast by factoring schedule performance with time metrics
@benzonjhermogeno
@benzonjhermogeno 3 ай бұрын
Thanks madam, it's really helpful
@Projectcontrolacademy
@Projectcontrolacademy 3 ай бұрын
Awesome. Glad to hear it was helpful.
@jonhitchcock5070
@jonhitchcock5070 6 жыл бұрын
Good presentation. At the end of project illustration does not show the planned value curve correctly because the planned schedule value should end at six months rather than following the Earned Schedule out to nine months. The planned line should not be moving as the schedule variance begins to accumulate. If there is a way to get the information into a shorter amount of time, more concise, it would be even better.
@Projectcontrolacademy
@Projectcontrolacademy 6 жыл бұрын
Thanks for the correction Jon. You are absolutely right. The PV curve should have stopped at month 6. The calculations are right though.
@SohamBanerjee123
@SohamBanerjee123 4 жыл бұрын
SPI is a ratio , no question of units(say $) . Only issue is at the end it will come down to 1.
@rexbk
@rexbk 6 жыл бұрын
Nice proooject. Thanks.
@Projectcontrolacademy
@Projectcontrolacademy 6 жыл бұрын
Thanks Raja.
@waltherchambi2718
@waltherchambi2718 2 жыл бұрын
Thanks for the explanation, how is the calculation of earned value of indirect cost as well owner cost, CM cost, …
@roganfield8955
@roganfield8955 3 жыл бұрын
Thank you very much Ms.Shohreh!.. it is very helpful and informative..i actually encountered this dilemma in my previous work (dilemma when the spi is 1 but was already beyond the completion date).. thank you very much!.. i hope i came across this video during that time.. :) however, i just noticed the graph from your last example that the PV at the end of June does not reflect a 100% completion. Should not it be more proper to have it have its peak by End of june and flattens toward the end of september?
@ahmedalmassri2037
@ahmedalmassri2037 3 жыл бұрын
great really
@Projectcontrolacademy
@Projectcontrolacademy 3 жыл бұрын
Thank you, Ahmed.
@chin3884
@chin3884 5 жыл бұрын
Thank you. Very good explanation. Can you explain "earned duration"?
@Projectcontrolacademy
@Projectcontrolacademy 5 жыл бұрын
Thanks for your comment. In regards to your question, there is no term as "earned duration". The 3 key elements of Earned Schedule technique are "Earned Schedule (ES), "Actual Time (AT)", and "Planned Duration (PD)". These elements were described in the video.
@adinaswabi1213
@adinaswabi1213 4 жыл бұрын
Much Appreciated your efforts in Project Management specially in Project control Management. Let me ask you, can we claim any PDUs for PMP certificate renewal against these training's?
@Projectcontrolacademy
@Projectcontrolacademy 4 жыл бұрын
Zafar, thank you for your message. We do offer official PMI PDUs as we are a registered education provider of PMI. However, we cannot offer PMI PDUs for our KZbin videos, as we don't have a means of assessing whether the viewer has watched the entire video or not. However, you can claim 1.5 PDUs by attending our free monthly webcasts. You can also get 10-35 PDUs upon the completion of our comprehensive training programs. You can check our website for more details. www.projectcontrolacademy.com/project-controls-training/
@chin3884
@chin3884 5 жыл бұрын
What is the difference between earned schedule and earned duration?
@Projectcontrolacademy
@Projectcontrolacademy 5 жыл бұрын
Thanks for your comment. In regards to your question, there is no term as "earned duration". The 3 key elements of Earned Schedule technique are "Earned Schedule (ES), "Actual Time (AT)", and "Planned Duration (PD)". These elements were described in the video.
@ezsutra
@ezsutra 2 жыл бұрын
How can you determine Earned Schedule in a spreadsheet?
@Projectcontrolacademy
@Projectcontrolacademy Жыл бұрын
Yes, actually it works better in Excel and via calculations. Check earnedschedule.com/Calculator.shtml for calculators developed by the ES creator, Walter Lipke.
@ayushmansdiary2694
@ayushmansdiary2694 6 жыл бұрын
Hi, Can you pls explain me what is the difference between value of work done and earned value or budgeted cost of work performed. I'm really confused with these two terms
@Projectcontrolacademy
@Projectcontrolacademy 6 жыл бұрын
Ranjan, you are referring to the old EVM terminologies. Budgeted Cost for Work Performed (BCWP) also called Earned Value (EV), is the budgeted cost of work that has actually been performed. For getting more clarity on EVM, I suggest you check these EVM free training video series: projectcontroltraining.com/evmfreetraining/
@ayushmansdiary2694
@ayushmansdiary2694 6 жыл бұрын
Project Control Academy thank you
@Projectcontrolacademy
@Projectcontrolacademy 6 жыл бұрын
Our pleasure Ranjan.
@muhammadtahir7527
@muhammadtahir7527 3 ай бұрын
I am sure the concept of earned schedule is floated by someone who has never been a scheduler on a project. The completion date is always calculated by scheduling tool (p6) which is dead precise. SPI was never intended to get the completion or end date of project. It's used as a monetary bench mark against which the work done (EV) is measured. I wonder why it's being inculded by PMI
@Projectcontrolacademy
@Projectcontrolacademy 3 ай бұрын
We recommend you read the Earned Schedule book by Walter Lipke and all the case study applications of the accuracy and application of Earned Schedule in projects to get a better idea. Alternatively you can check the Earned Schedule website at www.earnedschedule.com/
How to Forecast the Cost at Completion of a Project
15:40
Project Control Academy
Рет қаралды 32 М.
How to Assess the Accuracy of Your Cost Forecasts?
20:06
Project Control Academy
Рет қаралды 4,4 М.
The day of the sea 🌊 🤣❤️ #demariki
00:22
Demariki
Рет қаралды 86 МЛН
Haha😂 Power💪 #trending #funny #viral #shorts
00:18
Reaction Station TV
Рет қаралды 14 МЛН
Can You Draw A PERFECTLY Dotted Line?
00:55
Stokes Twins
Рет қаралды 64 МЛН
Василиса наняла личного массажиста 😂 #shorts
00:22
Денис Кукояка
Рет қаралды 9 МЛН
Why the EVM Scheduling Indicators are Not Reliable
19:51
Project Control Academy
Рет қаралды 8 М.
An introduction to an effective earned value management system (EVMS) part 1
54:29
Association for Project Management
Рет қаралды 3,3 М.
How to Calculate Earned Schedule
15:49
Project Control Academy
Рет қаралды 15 М.
Essential Project Controls Tools to Master
18:10
Project Control Academy
Рет қаралды 27 М.
Performance-Based Cost Forecasting (EAC/ ETC)
20:33
Project Control Academy
Рет қаралды 20 М.
The Components of a Project Controls Plan (PCP)
33:53
Project Control Academy
Рет қаралды 18 М.
5 Important Lessons Most Project Controllers Learn Too Late in Their Career
14:22
Project Control Academy
Рет қаралды 14 М.
How to Calculate Earned Schedule
8:12
Plan Academy Inc.
Рет қаралды 6 М.
The Philosophy Behind  S-Curves
14:38
Project Control Academy
Рет қаралды 60 М.
The day of the sea 🌊 🤣❤️ #demariki
00:22
Demariki
Рет қаралды 86 МЛН