Thanks Phil. I'm a PMP but I still come back to refresh myself. You are a gifted teacher.
@pmpexam7 жыл бұрын
Thanks Cecil. Hope you are enjoying your newfound PMP freedoms :-) Haha!
@MGBarkell7 жыл бұрын
Excellent lesson I will take with me to the exam room and beyond. Thank you!
@pmpexam7 жыл бұрын
Thanks Mike!
@khulekanianderson834 Жыл бұрын
This is an excellent presentation, sir. You demystified the technique of EVM and articulated it for anyone to understand it
@malikfaizanmahmood2134 жыл бұрын
Thanks sir for sharing. Really helped me for my bachelor's thesis
@askwaleed15 жыл бұрын
Simple, straight & efficient....... Thanksssss
@billdowpmo_pmcoach5 жыл бұрын
Excellent Video. Thanks for sharing.
@ginjupallyvamshi77185 жыл бұрын
Splendid video
@pmpexam2 жыл бұрын
Thank you!
@dearosman17 жыл бұрын
thank you Mr Philip I had learned this lesson it's clear more reliable. please keep on going this lessons
@pmpexam7 жыл бұрын
Thank you Osman!
@ruwanhewavitharana79806 жыл бұрын
Very good explanation. Thank you very much.
@abdulhamidabozaid36698 жыл бұрын
so simple and clear .. thank you .
@pmpexam8 жыл бұрын
+Abdulhamid Abozaid Thank you!
@ppsayl12355 жыл бұрын
So earned value doesn't become an EV variable until the work that is planned becomes measurable by means of tangible work/time completion (0%-100%) against that planned work, correct?
@allaboutpixhawkandrpi36916 жыл бұрын
Awesome Lesson Bro ! learned alot!
@pmpexam5 жыл бұрын
Thank you Moe!
@Denise-sq4wy7 жыл бұрын
Hi Phill, I have to implement a simple cost tracking and performance tool for projects. We do have a project plan with activities, but costs are simply tracked against an approved budget and key cost categories. (eg: Plant and equipment = approved budget of US$300K , Hardware = approved budget of US$ 20K etc) Can i still use EVM based on assigned cost categories?
@pmpexam7 жыл бұрын
User question: Hi Phill, I have to implement a simple cost tracking and performance tool for projects. We do have a project plan with activities, but costs are simply tracked against an approved budget and key cost categories. (eg: Plant and equipment = approved budget of US$300K , Hardware = approved budget of US$ 20K etc) Can i still use EVM based on assigned cost categories?
@pmpexam7 жыл бұрын
Yes Deni. It depends. You can use Earned Value on this project if you have an approved budget (Baseline) broken out into the time periods that the costs are expected to hit. If you do not have the expected costs (approved budget) broken out by time period, you will be unable to efficiently use SPI but you could still use a weak version of CPI depending on your data. Do you have the approved budget broken out by time period for each activity or cluster of activities (work packages)?
@queenkize9 жыл бұрын
Per your video, if I worked and spent only $3,500 from the $5,000 planned value, how come I ended up spending more on the actual cost if I only produced less than I planned for?
@pmpexam8 жыл бұрын
+queenkize - it was explained at 4:11 Cost overruns due to resource risks and weather delays. On a real project this could be several possible reasons. So in this scenario the PM got less than planned done and the project is late because the originally planned "core team" is unavailable and there are weather challenges.
@FD-lo8xr9 жыл бұрын
thank you i needed this :)
@pmpexam8 жыл бұрын
+fAMOSS DAMOSS Thanks!
@VanessaKlinger8 жыл бұрын
So the project is behind schedule by 90% and we are over budget 86% respectively? Thanks
@pmpexam8 жыл бұрын
Vanessa - it is the reverse, the project is 10% behind schedule and 14% over budget. You could say you are only making 86 cents for every dollar spent. You are not getting the full value for your money. You can also say you are only 90% efficient schedule-wise and 86% efficient cost-wise. Also, you are spending 10 days working on the project but only achieving 9 days worth of work.
@courtneyellis17048 жыл бұрын
How did you graph this?
@pmpexam8 жыл бұрын
@Courtney by entering the values in Excel. Excel has the graph function.
@fernandoenriquez85738 жыл бұрын
how did you graph
@pmpexam8 жыл бұрын
@Fernando by entering the values in Excel.
@fernandoenriquez85738 жыл бұрын
Thank you sir for your feedback but perhaps the better question is how to construct a set up using "plug & play"; an instrument that is predetermined in excel, or so it seems.
@pmpexam7 жыл бұрын
If I understand your question it is by putting in the formulas and letting excel do the calculations and manipulations?
@santuchatterjee8232 жыл бұрын
Hi Phil...Can you please make a video on the forecasting technique
@pmpexam2 жыл бұрын
Hi Santu! Check these videos out: kzbin.info/www/bejne/fpTRdYl8p71jiNE and kzbin.info/www/bejne/qqWwfXunl9qVbqM Does that help? Cheers!
@pmpalihena6 жыл бұрын
Where is the BAC (Budget at Completion)? Don't you need this value for the calculations too?
@preciousosegi96807 жыл бұрын
Thanks a lot Mike. Great job!
@angelaphillips28716 жыл бұрын
Phil, Does the type of contract effect the Earned Value Management process? For example, will a Cost plus fixed fee contract be managed the same as a T&M contract ?
@hrejoice82566 жыл бұрын
Thank you for your training and explanation.. Very practical teaching...
@spellru237 жыл бұрын
The light bulb went on - thank you
@pmpexam7 жыл бұрын
Awesome! Glad to hear that Ruby! Thanks :)
@aryaardhana64527 жыл бұрын
How come the progress values in March could be lower than the previous months? Does it make sense? Does the progress value should be increased on the next following months?
@pmpexam7 жыл бұрын
Good question Arya. This is looking at the months in isolation (stand-alone) as opposed to cummlatively (adding them up as the months go on). For example EV for Jan = 8 , EV for Feb = 6, EV for March = 3 (stand-alone) OR CUMULATIVE TOTAL EV at end of Jan = 8 TOTAL EV at end of Feb = 14 TOTAL EV at end of March = 17 (cumulative). Does that help?
@Welcome2TheInternet7 жыл бұрын
good video. thanks
@pmpexam7 жыл бұрын
Thank you Sir!
@queenkize9 жыл бұрын
Hi, I am actually taking the PMP course, is it okay if I could have your email address?
@pmpexam8 жыл бұрын
+queenkize All the best in your test. Have you taken it? support@praizion.com