Hello, On Q21 I got it incorrect because I assumed the costs of supervisors was already included in the labour costs - to me that wasn't made clear in the question. This happens often when I am revising for my exam, what can I do? Thanks in advance.
@SteveWillisACCA11 ай бұрын
Please read carefully, it says "In addition to the above costs, the management accountant estimates that for each increment of 50,000 units produced, one supervisor will need to be employed. A supervisor’s annual salary is $35,000."
@user-ut2ux8qs3d11 ай бұрын
Oh right 😅 thanks @@SteveWillisACCA
@krish96636 ай бұрын
When I did high-low method on Q22, I tested the VC against Year 2 and Year 3 data and ended up with a different fixed cost to 225,000.. is that correct?
@SteveWillisACCA6 ай бұрын
Yes, high-low is just an approximation and ignores all the data except the high and the low one.
@yazmincashmore9232 Жыл бұрын
Where did you get the Fixed Cost from? 225,000?
@SteveWillisACCA Жыл бұрын
Please check in the question again--they give you the fixed costs in the original budget.
@yazmincashmore9232 Жыл бұрын
@@SteveWillisACCA Thanks missed that!, one more question how did you get the 210,000 units?
@MaxX-ou2fw Жыл бұрын
@@yazmincashmore9232 80% of capacity
@yazmincashmore9232 Жыл бұрын
@@MaxX-ou2fw thanks
@pramilamahat11464 ай бұрын
whats difference between flexed and flexible budget
@SteveWillisACCA3 ай бұрын
Flexible budget: future--we know fixed and variable costs, can budget for any activity level. Flexed--Past. Set the flexible budget to the actual activity. "We flexed the budget to last months activity"