How to estimate amount of cement and sand needed for your block work

  Рет қаралды 28,283

9 - 5 DATA

9 - 5 DATA

Күн бұрын

Пікірлер: 30
@Bluesky_construct2567
@Bluesky_construct2567 2 жыл бұрын
You remain the one person to bring justice to this estimation on this KZbin so far. By the way, kindly avail us how you arrive at 0.275 You swift response will be highly appreciated. Thanks a lot
@kelvinikiriko773
@kelvinikiriko773 2 ай бұрын
please has he reply you on the question you asked? base on the 0.275
@franklinobiukwu3483
@franklinobiukwu3483 4 жыл бұрын
I find this video educating. You're doing great!
@9-5data
@9-5data 4 жыл бұрын
Thank you
@georgerether79
@georgerether79 6 ай бұрын
Nice work mister
@obadex
@obadex 3 жыл бұрын
Great work keep it up
@abbafary1445
@abbafary1445 Жыл бұрын
The vid is educative sir kudos. My Question here is, how did uou arrived at getting 0.275 vertical mortar? Thank you best regards
@folexkendrick
@folexkendrick 2 жыл бұрын
Please does this account for the plastering too?
@dapoabolarinobj8105
@dapoabolarinobj8105 4 жыл бұрын
Bravo, Engr!
@9-5data
@9-5data 4 жыл бұрын
Thank you sir.
@kelvinikiriko773
@kelvinikiriko773 2 ай бұрын
hi good morning, do you understand how the 0.275 on the vertical mortar comes about?
@kelvinikiriko773
@kelvinikiriko773 2 ай бұрын
@@9-5data hello boss please throw more light on the 0.275 vertical mortar you got thanks
@georgerether79
@georgerether79 6 ай бұрын
How did the Height of the horizontal mortar change into 275mm or 0.275
@tushabejoseph7377
@tushabejoseph7377 2 жыл бұрын
How did you obtain 0.0637 in the calculation of bed mortar/horiz mortar??? . explain am lost from dt very point
@tushabejoseph7377
@tushabejoseph7377 2 жыл бұрын
And by calculation how did you get the 10 blocks ? Minus assuming
@garpeeroberts5580
@garpeeroberts5580 3 жыл бұрын
Hi, how did you obtained the 0.275 in the vertical mortar area calculations?
@theslickking-majura5799
@theslickking-majura5799 2 жыл бұрын
my question exactly
@ovuosita
@ovuosita 4 ай бұрын
Sir, how did you arrive with 0.275 ?
@AguEmmanuel-kn8qt
@AguEmmanuel-kn8qt 9 ай бұрын
Pls how did u get the 0.275
@temidayoafolabi7344
@temidayoafolabi7344 7 ай бұрын
for the vertical, the height of the block is 225mm. Now add the 25mm mortar at the top and also the one at the bottom of the block. You will have 25mm + 225mm + 25mm = 275mm, You can check the diagram at 2:44 . Check the red boxes.
@divinennate3226
@divinennate3226 Жыл бұрын
Pls how did you arrive at 1.3 and 1.1 as percentage of 30 and 10 respectively
@temidayoafolabi7344
@temidayoafolabi7344 7 ай бұрын
This is how, assume the wet volume is 1 cubic meter, we are told that the dry volume is 30% more that the wet volume. What this means is that you will add 30% of wet volume to the 1 cubic meter value of the wet volume. see, Wet vol. = 1m3 Dry vol. = (30% of 1) + 1 =(30/100 * 1) + 1 =(0.3 * 1) + 1 = 0.3 + 1 = 1.3. therefore, for every 1 m3 of wet volume, we have 1.3 m3 of dry volume. 1.3 in other words is a constant.
@theslickking-majura5799
@theslickking-majura5799 2 жыл бұрын
Sir kindly explain how you arrived at 0.275
@acheampongkoranteng4847
@acheampongkoranteng4847 3 жыл бұрын
Can this be applied to solid blocks?
@9-5data
@9-5data 3 жыл бұрын
Check the channel to see video on solid blocks
@olatundelateefat5177
@olatundelateefat5177 4 жыл бұрын
🙌🙌🙌🙌
@emmanuelodoba4623
@emmanuelodoba4623 4 жыл бұрын
Barca go still go trophyless
@9-5data
@9-5data 4 жыл бұрын
Hmmmmm. Thanks for your concern
@alsemi-back-up579
@alsemi-back-up579 Жыл бұрын
TOO COMPLICATED!!!!!!!!!!!!! HOW MANY BAGS OF MASONARY FOR HOW MANY BLOCKS!!!!!!! IT IS NOT ROCKET SCIENCE MAN!!!!!!!!!!!!!!
How To Calculate Cement And Sand Mortar For Construction Projects
10:46
Cost Engineering Professional
Рет қаралды 15 М.
How to calculate how many blocks or bricks needed for a wall
8:36
Build and repair and restore
Рет қаралды 103 М.
Правильный подход к детям
00:18
Beatrise
Рет қаралды 11 МЛН
BAYGUYSTAN | 1 СЕРИЯ | bayGUYS
36:55
bayGUYS
Рет қаралды 1,9 МЛН
The Real Use of Carbon Capture
54:33
Decouple Media
Рет қаралды 1,7 М.
how to calculate quantity of cement, sand and crushed stone in floor/ slab
6:14
HOW TO MEASURE FOR SUPER STRUCTURE [BLOCK WORK]
23:04
Quantity Surveying Workshop
Рет қаралды 4,2 М.
Estimating sand, cement, water for mortar to lay block
12:48
Tim Palmer - Logs to lumber
Рет қаралды 6 М.
How to estimate the amount of block for a foundation
11:05
Mason The Mason
Рет қаралды 24 М.
Правильный подход к детям
00:18
Beatrise
Рет қаралды 11 МЛН