How to Use Critical Paths in Microsoft Project

  Рет қаралды 90,410

Simon Sez IT

Simon Sez IT

3 жыл бұрын

✅To read the accompanying article on Critical Path in Microsoft Project, go here: ➡️www.simonsezit.com/article/wo...
Not all tasks are created equal in Microsoft Project. There will always be some tasks that are more critical to the overall project than others, and we refer to these tasks as the critical path.
The critical path is a chain of linked tasks that directly affect the project’s finish date. These tasks are so important that if any of the tasks on the critical path are late, the whole project is delayed. Tasks not on the critical path have a certain amount of slack, whereas tasks on the critical path, do not. Slack refers to the amount of time a task can be delayed without affecting the overall end date of the project.
Project calculates the longest path through the plan based on dates. The path will typically contain a chain of linked tasks. These tasks are the critical path. For example, if Project calculates a path that is 20 days long (path a) and another path of linked tasks is only 15 days long (path b), the tasks in path b can be up to 5 days late without changing the critical path.
The tasks within the critical path control the calculated start or finish dates of the project and are often linked by task dependencies. The project is considered complete when the last task in the critical path is finished.
The critical path is continuously calculated by Microsoft Project and can change as tasks are modified or updated. It is worth noting that this calculation is purely an estimate. Despite this, the critical path gives project managers a good idea of where to focus attention.
🌍 Get unlimited training with Simon Sez IT’s 150+ courses ⏩ www.simonsezit.com/courses/
🚀 Level up your skills with a free 30-day trial to our complete training library of 8,500+ videos ⏩ www.simonsezit.com/ssit-first...
💻 Watch more free popular training tutorials from Simon Sez IT:
🔥Check out our FREE 300+ hour training course playlist here ➡️
• Simon Sez IT Long Trai...
✅ Check out our free video playlist for Project 2021 for beginners 👉 • Microsoft Project 2021...
✅ Project 2019 Beginners to Advance here 👉 • Microsoft Project 2019...
✅ Excel 2021/365 Training Tutorials for Beginners 👉 • Excel 2021/365 Trainin...
✅ Microsoft Office 2021 and Office 365 Training here 👉 • Microsoft Office 2021 ...
💬Stay in touch!
SimonSezIT.com: www.SimonSezIT.com/
LinkedIn: / simon-sez-it
FaceBook: / simonsezit
🔔 Subscribe to our channel:
kzbin.info...
If you enjoyed the video, please give a thumbs up 👍🏽 ;-)

Пікірлер: 18
@raycarlone2005
@raycarlone2005 3 жыл бұрын
Calculate multiple critical paths is what i have been searching for a ever. thanks so much.
@mvabiv
@mvabiv Жыл бұрын
Excellent, helpful video. TY!
@hamzaawalze4626
@hamzaawalze4626 3 жыл бұрын
Following ur vedios from kenya
@SimonSezIT
@SimonSezIT 3 жыл бұрын
Thanks for watching Hamza!
@amritheshe2757
@amritheshe2757 Жыл бұрын
Calculate Multiple Critical Paths.. Thank you
@adrianeland87
@adrianeland87 Жыл бұрын
Great clear explanation . Thanks
@SimonSezIT
@SimonSezIT Жыл бұрын
Glad it was helpful! We have other free videos for project management here 👉 kzbin.info/aero/PLzj7TwUeMQ3iqvdrIfS1DciFNWxLsBhkt
@rvrahul18
@rvrahul18 4 ай бұрын
Thank you so much..
@thamaradamayanthi1977
@thamaradamayanthi1977 3 жыл бұрын
Thank you
@SimonSezIT
@SimonSezIT 3 жыл бұрын
Happy you liked it Thamara!
@cpwyou
@cpwyou Ай бұрын
How can you tell which are the multiple critical paths
@ivynya29
@ivynya29 2 жыл бұрын
When will the multiple critical paths be useful?
@user-to9rg1ef3q
@user-to9rg1ef3q 8 ай бұрын
For critical paths calculation, does the software only consider the task duration, should it also consider the resources availability?
@manosdrako
@manosdrako 2 ай бұрын
based on the Critical Path Methodology, only task durations and dependencies are taken into account. Not sure if Project can account for resource availability and/or overallocation
@MVK_GS
@MVK_GS 9 ай бұрын
Not all MS Project versions do this. Stupidly, the web-based versions do not have a critical path toggle.
@colcot50
@colcot50 2 жыл бұрын
Summary tasks shouldn’t be predecessors or successors
@samuelfranciscogarcia1440
@samuelfranciscogarcia1440 3 жыл бұрын
Can you share your file please 🕳🏡
@wafa7734
@wafa7734 11 ай бұрын
6:00
Master Microsoft Project in 20 MINUTES! (FREE COURSE)
18:39
Alvin the PM - Become a Certified Project Manager
Рет қаралды 339 М.
Does size matter? BEACH EDITION
00:32
Mini Katana
Рет қаралды 17 МЛН
ОСКАР ИСПОРТИЛ ДЖОНИ ЖИЗНЬ 😢 @lenta_com
01:01
HAPPY BIRTHDAY @mozabrick 🎉 #cat #funny
00:36
SOFIADELMONSTRO
Рет қаралды 11 МЛН
Critical Path in MS Project 2016
9:43
KnowledgeCity
Рет қаралды 33 М.
What is the Critical Path Method (CPM)?
5:27
Online PM Courses - Mike Clayton
Рет қаралды 259 М.
Using Advanced Reporting in Microsoft Project 2019
13:26
Simon Sez IT
Рет қаралды 61 М.
# 1 MS Project 2019 ● Basics in 20 Minutes ● Easy
29:37
Vision 6D
Рет қаралды 1,1 МЛН
Project Advanced Tutorial
49:15
Learnit Training
Рет қаралды 166 М.
How to Use Microsoft Teams for Project Management
13:43
Bulb Digital
Рет қаралды 420 М.
# 15 MS Project 2016 ● Critical  Path ● Howto
13:59
Vision 6D
Рет қаралды 96 М.
Samsung Galaxy 🔥 #shorts  #trending #youtubeshorts  #shortvideo ujjawal4u
0:10
Ujjawal4u. 120k Views . 4 hours ago
Рет қаралды 5 МЛН
КРУТОЙ ТЕЛЕФОН
0:16
KINO KAIF
Рет қаралды 5 МЛН
Мой инст: denkiselef. Как забрать телефон через экран.
0:54
Красиво, но телефон жаль
0:32
Бесполезные Новости
Рет қаралды 776 М.
Как распознать поддельный iPhone
0:44
PEREKUPILO
Рет қаралды 1,5 МЛН