Hi Brian, at 7:50 you say "you can plot these points" to create a 70% confidence frontier curve. I tried to do this with solver but a gradient optimization fails when using countif in the chance of calculation for the 70% curve. I think I'll try a datatable and plug in effort percentages to derive the duration values for the xy plot for the frontier curve. Not sure if that will work or not.
@brianputt9842 жыл бұрын
Hi Brian did you solve the issue or you still need help. Send me an email at Brian@theputts.com
@narvariya6 жыл бұрын
Hello Brian, Excellent explanation, How do you consider the impact of increased schedule translated in to increased cost through LD and project extension cost?
@brianputt9844 жыл бұрын
Nilesh -- Your question regarding the trade-off of schedule and cost goes to management. Are there political implications or other cost consideration for either accelerating the schedule or reducing the cost. This gets to a very difficult subject of Value Measures, but one that management needs to work through. I have advocated for companies to have a probabilistic capital budget, but in today's society this is very difficult to implement in any company of size.