Learning Project Management Critical Path in 30 min with Ricardo Vargas

  Рет қаралды 14,008

Ricardo Vargas

Ricardo Vargas

Күн бұрын

In this video, Ricardo explains in detail how to calculate the critical path. It explains with examples how to calculate the forward pass and the backward pass, as well as the free and total floats.
Learning Critical Path in 30 min with Ricardo Vargas
This video is part of the content Ricardo is working to explain some project management principles!
LEARN MORE ABOUT MY ONLINE SCHOOL AT
learn.ricardo-vargas.com
IF YOU LIKE THIS VIDEO, SUBSCRIBE MY CHANNEL AT rvarg.as/youtube
TABLE OF CONTENT
0:00 - Introduction
0:49 - The Concept Critical Path
2:14 - The four components of Critica Path
5:54 - The forward pass
14:14 - The backward pass
23:21 - Free and Total float
34:01 - Final Considerations
Learning Critical Path in 30 min with Ricardo Vargas
Project Management
ricardo vargas pmp
pmp certification
ricardo Viana Vargas
project management certification pmp
pmp exam
project schedul
decision support system
decision making
critical path
forward pass
backward pass
time management
project management
total float
free float
early start
early finish
late start
late finish

Пікірлер: 25
@rvvargas
@rvvargas Жыл бұрын
Thanks for your interest in this video. You can download the exercise file at get.ricardo-vargas.com/criticalpath. 🚀 Do not miss the chance to visit our online school with several free courses for your project management learning. Access the school at learn.ricardo-vargas.com
@ramaneswararaorongala7263
@ramaneswararaorongala7263 Жыл бұрын
Excellently explained in a lucid way👏 Kudos to you🙏 Template link is guiding to your website, after submitting the details, there is a message that template is sent my email. But, never, i saw an email from your side. Please look into this bug.
@EbuniMisses
@EbuniMisses Жыл бұрын
One thing about Mr. Vargas is that he is going to make sure you understand what you are doing and why you are doing it in vey practical terms. He makes it easy to apply the information to a variety of areas.
@ikennachidiebere4620
@ikennachidiebere4620 7 күн бұрын
Thanks a lot Mr Vargas. You have a way of breaking down complexities into simple understandable terms.
@rvvargas
@rvvargas 6 күн бұрын
Thank you. Have a wonderful week! 🙏
@danielledeangelis6281
@danielledeangelis6281 8 ай бұрын
This is the video that finally made me understand Critical Path without formulas!
@kaykayyou9088
@kaykayyou9088 4 ай бұрын
This is the single most helpful resource I've found on this topic. Better than the PMBOK, better than all the supplemental resources my program shared. Thank you!!
@AC-ro6ib
@AC-ro6ib Жыл бұрын
Im taking the PMP exam on 1/28/23. Your videos are extremely helpful.
@the-john-smith
@the-john-smith Жыл бұрын
and, how it went?
@COBJ8
@COBJ8 Жыл бұрын
Thank you for taking on this intimidating topic. The content you put out is always useful.
@GABSIAN1838
@GABSIAN1838 Жыл бұрын
The determination of CP can provide the Project Manager and the project team a lot of information such as the establishment of the early and the late start, the development of human resources (when and who I need), the calculation of total float..
@jaenudinrifaiify
@jaenudinrifaiify 10 ай бұрын
Thanks Mr. RV
@georgewithey1689
@georgewithey1689 Жыл бұрын
This is a really great tutorial! Great job!!
@ricardorodrigues5151
@ricardorodrigues5151 Жыл бұрын
Simple however, valious. Thanks for share!
@cafecandido3219
@cafecandido3219 8 ай бұрын
Well explained, thanks Ricardo Vargas
@rileygla23
@rileygla23 9 ай бұрын
Lovely hope to pass my online study😊
@michaeldoherty7434
@michaeldoherty7434 Жыл бұрын
Thanks Ricardo. Your finish dates are one day later than the traditional way to do it. So if you start on day 0 and the task is 1 day then it finishes on day 0. However your method makes the maths a bit simpler and gets the same result. Hence I’d suggest people use the way that you calculate the floats.
@rvvargas
@rvvargas Жыл бұрын
Thanks Michael. Some people like to start with 0. For me it is far simpler starting with Day One (1) so the math becomes very direct. Cheers. Ricardo.
@user-rj8dv7hs1d
@user-rj8dv7hs1d Жыл бұрын
Dear Ricardo , Suppose we are calculating the range of an estimate for an individual activity on the critical path , further to obtain an estimate for that duration using a weighted Beta averaging ; thus upon calculating the range using Beta EAD ± SD , would this range be the widest among all other project activities , if so would it have the greatest risk?
@rvvargas
@rvvargas Жыл бұрын
Great question. This is the average path. It is not the path with the greatest duration. The path with the gratest lengh is the one with all pessimistic dates on the distribution. Regarding risks, the behavior is quite the opposite. The most optimistic date is the one that brings most of the threats because it considers the path that everything goes well. I hope this could answer your question.
@user-rj8dv7hs1d
@user-rj8dv7hs1d Жыл бұрын
@@rvvargas Yes , Thank you and it is much appreciated.
@HexalHexal
@HexalHexal Жыл бұрын
This is not the correct calculation. If you start an activity on day 1 and it has a duration of 4 days. Then it is full day 1, full day 2, full day 3, and full day 4 ... not 5. The formula is ES+D-1=EF
@rvvargas
@rvvargas Жыл бұрын
Hi Stefan. This is one approach and it is right too. I did that because I do not want people to think it is on the start or end of a day. But of course that if you start at the beginning of day 1 and it takes 4 days it will end at the end of day 4. But when you move this 4 to the next activity you will have to add one because the task will then start in the morning of day 5. At the end it does the same effect. You can use EF=ES+D and ESnext activity = EF previous activity or you can use EF=ES+D-1 and ESnext activity = EF previous activity +1. Ricardo
@HexalHexal
@HexalHexal Жыл бұрын
@@rvvargas thank you for the explanation, Ricardo. Have a wonderful day.
@FreshNFunky24
@FreshNFunky24 5 ай бұрын
Thanks a lot for calling this out. I was going through examples and saw this and couldn't get the math to work.
Basics of Kanban Boards for Project Management with Ricardo Vargas
20:53
Китайка и Пчелка 4 серия😂😆
00:19
KITAYKA
Рет қаралды 3,6 МЛН
UFC 302 : Махачев VS Порье
02:54
Setanta Sports UFC
Рет қаралды 1,4 МЛН
100❤️
00:20
Nonomen ノノメン
Рет қаралды 69 МЛН
Smart Sigma Kid #funny #sigma #comedy
00:19
CRAZY GREAPA
Рет қаралды 7 МЛН
PMI Process Group and the PMBOK Guide Explained by Ricardo Vargas
14:57
5 Tips From Ricardo Vargas To Master A Work Breakdown Structure
14:44
Ricardo Vargas
Рет қаралды 2,6 М.
Crisis Management in Six Steps with Ricardo Vargas
28:38
Ricardo Vargas
Рет қаралды 8 М.
Agile or Fragile  Top 7 Scrum Mistakes with Ricardo Vargas
17:11
Ricardo Vargas
Рет қаралды 7 М.
PMBOK® Guide 6th Ed Processes Explained with Ricardo Vargas!
53:23
Ricardo Vargas
Рет қаралды 1,8 МЛН
How to Create a Project Plan | Every Project Manager MUST KNOW
19:22
Basics of Design Structured Matrix DSM with Ricardo Vargas
27:27
Ricardo Vargas
Рет қаралды 5 М.
Ricardo Vargas Explains the Theorem of Bayes and Project Estimates
14:25
Китайка и Пчелка 4 серия😂😆
00:19
KITAYKA
Рет қаралды 3,6 МЛН