Megamix Sdn. Bhd. was awarded the order to supply ready mixed concrete to the Sentral Suite Project under the contract of Aneka Jaringan Sdn. Bhd.
This was a big quantity order of about 6,200m³ to be done in a single continuous pour that was estimated to run from 16/11/17 to 18/11/17. This operation involved meticulous logistic and resources planning with strict compliance to quality control requirement.
The order was completed with a final quantity of 6,068m³ in 40 hours, from 16/11/17 to 18/11/17.