MIVAN Shuttering Procedure I 7 days Slab Cycle I aluminium formwork

  Рет қаралды 2,664

Civil Construct

Civil Construct

Күн бұрын

MIVAN Shuttering Procedure I 7 days Slab Cycle I aluminium formwork
About This Video Content,
In this video Er. Narendra Patle explained about, we talk about 7 days slab cycle with mivan shuttering, will discuss procedure with the activities to follow on site each day to achieve 7 days cycle
This video covers all these topics
▶️Day 1
Grid line work
Thesi work (fixing of wooden planks )
Complete vertical column, shear wall and nonstructural wall reinforcement work
▶️Day 2 and 3
Erection of wall panels, deck panels with all chajjas elevation work
▶️Day 4
Complete Beam and slab reinforcement work with covering
▶️Day 5
Complete all Electrical Conduting work and MEP sleeves and cutouts if needed
▶️Day 6
Complete Gridline checking and supporting work of slab
▶️Day 7
Complete checking work of RCC, architect, quality and MEP work as per approved drawing and with respecting departments
Final do Concrete Casting work of slab
and many more...
===================================================================
Download all Courses free ( BBS Excel Sheet / Drawing / Useful pdf )
(Note: Videos and documents will get update daily, so stay tuned for more information )
docs.google.co...
Download file in pdf
docs.google.co...
Please Subscribe: / civilconstruct
===================================================================
Visit our Channel for Civil Engineering Knowledge:
/ dndconstruction
Visit our Channel for lifestyle & Fitness
/ @dineshlifestyle
Follow us on INSTAGRAM: www.instagram....
Join us on Telegram: t.me/civil_con...
Follow us on FACEBOOK: / 102249415176766
===================================================================
#mivanshuttering #7daysslabcycle #dndconstruction
mivan technology construction
Slab cycle in construction
complete procedure to follow to complete slab in 7 days by mivan technology
===================================================================
Disclaimer - This video is for educational purpose only. Copyright
Disclaimer Under Section 107 of the Copyright Act 1976, allowance is
made for "fair use" for purposes such as criticism, comment, news
reporting, teaching, scholarship, and research. Fair use is a use
permitted by copyright statute that might otherwise be infringing.
Non-profit, educational or personal use tips the balance in favor of
fair use .

Пікірлер
MIVAN Shuttering Process: From Start to Finish #mivan @DNDConstruction
51:41
Incredible: Teacher builds airplane to teach kids behavior! #shorts
00:32
Fabiosa Stories
Рет қаралды 11 МЛН
Help Me Celebrate! 😍🙏
00:35
Alan Chikin Chow
Рет қаралды 60 МЛН
MIVAN Shuttering Interview Questions l Top 20
16:04
Civil Construct
Рет қаралды 11 М.
MIVAN Shuttering Procedure I 7 days Slab Cycle I aluminium formwork
13:02
Conventional Shuttering Procedure l 8 Days Slab Cycle I Ply Shuttering
11:57
How To Calculate Concrete Quantity l MIVAN Shuttering l In Excel
14:52
Civil Construct
Рет қаралды 1,7 М.
GETO Aluminium Formwork Animation
6:08
Connie Wisdom
Рет қаралды 57 М.
MIVAN Shuttering Interview Questions l Top 15
7:22
Civil Construct
Рет қаралды 40 М.
Mivan shuttering Accessories and tools.
11:09
DC SITE ENGINEER
Рет қаралды 10 М.