Dear Jeferson. Many thanks for all your valuable process courses. I would like to highlight that in example 5.2, You specified in the Excel spreadsheet the process pressure as 258 in kpa (absolute) while 258 kpag (gauge) is given in the sketch. Please check and revert.
@jefersoncostaengineer Жыл бұрын
Hi, in the spreadsheet was missing the "g" in the pressure information (line 20). This information is gauge pressure as informed in the sketch. Thanks for the alert. I will fix the units of measurement in the spreadsheet. In any case, the calculation in the video is correct. Good catch :)
@custodiosantos8384 Жыл бұрын
Thank you for sharing your knowledge.
@jefersoncostaengineer Жыл бұрын
My pleasure 😇
@rahilreda690411 ай бұрын
Dear Sir , thank you a lot for this explanation , i have just one question : in the munit 20:03 , you have talked about the calculation of NPSHa by Hysys software : you have said that the P1 : is the inlet pressure at the pump suction and as we know this value normaly shall including ( absolute pressure at the vessels - pressure loss +- static pressure of the static head ) how we can get the same value as the excel sheet calculation by adding the dynamic pressure ( V2/2G ) , when we can consider this dynamic pressure , and why you have not consider this value in exceel sheet ? NPSH-A = (((Pvessel-Pv)/ρ)x10.2)+Hz-Hf+(V²/2g) , thank you very much
@jefersoncostaengineer11 ай бұрын
Hi, dynamic pressure is based on pump nozzle. In the preliminary calculation pump was not selected, and pump nozzle is not available. Moreover, ignoring dynamic head will drive us to safe margin. For all these reasons, we usually perform NPSHa calculation without dynamic pressure.
@warnme2001 Жыл бұрын
TQ for sharing your knowledge. Is there a different NPSH calculation for reciprocating pump? 🤔
@jefersoncostaengineer Жыл бұрын
Hi for reciprograting pump, the chemical process engineer must subtract an additional term related to the reciprocating pump acceleration head. NPSHA = pg + pz - pvp - pf - pac
@adedirefisayo682 Жыл бұрын
Thank You Mr Costa
@jefersoncostaengineer Жыл бұрын
Thanks a lot for the feedback 😁
@nicholashassan20258 ай бұрын
Thank you for this excellent information. What if we are to take distilled water at 1 Bar absolute on the suction side of a pump at 100 degrees centigrade, what is the calculation?
@jefersoncostaengineer8 ай бұрын
The procedure is the same. As the fluid is at saturated conditions, you will work on the elevation of your vessel/column or eventually you can consider cooling the stream before pump suction.
@abdulazizal-shamli155 Жыл бұрын
Thank you a lot mr. Jeferson , but from where I can get the excel sheet ?
@jefersoncostaengineer Жыл бұрын
Hi, excel sheet will be available once on Telegram channel INProcess once like target is achieved 😇
@abdulazizal-shamli155 Жыл бұрын
@@jefersoncostaengineer please we waiting once it is available
@jefersoncostaengineer11 ай бұрын
Thanks a lot for your support :)
@engineertakeyaldeenal-haj67615 ай бұрын
@@abdulazizal-shamli155did you get it ?
@reem780226 ай бұрын
Hello sir, I'm trying to get the data from PV of controllers and export it to Excel so that it transfers the data automatic in the dynamic state. How can I do that?
@jafarramadan98585 ай бұрын
How can i find your Excel sheet calculation please?
@jefersoncostaengineer5 ай бұрын
Usually I let materials available at my telegram channel. here is the link t.me/chemicalprocessengineer. Otherwise, they are available only for my Inprocess Booster students 😇