HELLO PO SA LAHAT.. WELCOME BACK TO MY CHANNEL RANDY YERRO OFW SIMPLE HOUSE VLOG..
This House 🏠🏠🏠 Video Own by Maam Romelyn Diza
Si Maam ay isang DH. sa Singapore,10 years narin siyang Abroad,33 years old Single.from Ilocos Norte Philippines
CONGRATS MAAM ROMELYN DIZA GOD BLESS YOU ALWAYS🙏🙏🙏
BUILDING A HOUSE 774,737 PHP
$15,494 USD
PLAN WITH BUILDING PERMIT = 15,000
STRUCTURAL = 326,972
STEEL TRUSSES = 54,535
ROOFING = 55,200
SPANDREL = 23,125
PORCH & CANOPY WINDOW = 21,905
PLASTERING AND ECT.... 7,880
Septic Tank & Toilet Pipe = 14,091
Flooring = 33,544
Electricity = 59,545
Plastering = 93,930
Glass Windows & Doors = 61,090
Other Expenses Door Jamb = 7,920
Start Building A House November 28 2019
House Size 7 x 10.5 meter
73.5sqmeter 3rooms 2Toilet&B,Terrace,Living,Dining,Kitchen
Qty Item Price/Unit Total
100bags -Holcim Cement -235 = 23,500
5load -Sand/Balas -1,800 = 9,000
2,000pcs - #5 Hollow Block - 13 = 26,000
150pcs - Roundbar 10mm - 117 = 17,550
24pcs - Roundbar 12mm - 169 = 4,056
110pcs - Roundbar 16mm - 299 = 32,890
48pcs - Coco Lumber 2x2x12 - 212 =10,176
20kilos -Tie Wire = 1,400
10kilos - #4 C W Nails = 900
10kilos - #3 C W Nails = 700
5kilos - #2 C W Nails = 350
First Order = 126,322
Qty Item Price/Unit
1bag Holcim Cement 235 pesos
Qty Item Price/Unit
1pc 16mm Roundbar 299 pesos
1pc 12mm Roundbar 169 pesos
1pc 10mm Roundbar 117 pesos
Qty Item Price/Unit
1pc Wood 212 pesos
Qty Item Price/Unit
1pc Ordinary Plywood 680 pesos
STEEL TRUSSES MATERIALS
Qty Items Unit/Price Total
15pcs - Channel 4" - 1,480 - 22,200
28pcs - C-Purlins 2x3 (1.5) - 500 - 14,000
8pcs - C-Purlins 2x8 (1.5) - 830 - 6,640
4pcs - AngleBar 3/16×1 1/2 - 340 - 1,360
1Gal - Epoxy Red - 750 - 750
1Gal - Epoxy Red - 640 - 640
1Gal - Epoxy Red - 780 - 780
2Litter - Epoxy Red - 190 - 280
1Gal - Thinner - 250 - 250
1Gal - Tninner - 180 - 180
4Litter - Thinner - 45 - 180
2pcs - P-Brush 2×1/2 - 50 - 100
4pcs - P-Brush 2 - 35 - 140
4pcs - Darie 4" CD - 35 - 140
2pcs - Toka CD - 200 - 400
2pcs - Sand Flex 18+ - 60 - 120
1pc - Freight - 500 - 500
TOTAL COST = 48,760
Steel Trusses Materials =48,760
Steel Trusses Labor Cost =4,900
Painting for Trusses Labor Cost = 870
TOTAL COST = 54,535
Materials for Porch and Canopy Window
Qty - Item - Unit/Price - Total
15pcs - Roundbar 10mm - 128 - 1,920
5bags - Holcim Cement - 270 - 1,350
10bags - Holcim Cement - 260 - 2,600
320pcs - Hollow Block - 14 - 4,480
3bags - Apo Cement - 235 - 305
Fare of Materials - 90 - 90
MATERIALS TOTAL COST = 11,055
Labor Cost for Making Porch = 4,850
Labor Cost Canopy Window - 5,000
Labor Cost for Loading Sand = 1,000
TOTAL COST = 21,905
ROOFING MATERIALS MATTE GRAY
Qty - Item - Unit/Price - Total
110.4LM - TERRARIB 0.45 - 616.94 - 68,110.18
7pcs - Box Gutter 0.45 - 865.55 - 6,058.85
15pcs - End Flashing 0.45 - 865.25 - 12,983.25
700pcs - Tekscrew 12x65 - 1.25 - 875
600pcs - Blind Rivets - 0.40 - 240
3pcs - Silicone Sealant - 130 - 390
1pc - Touch Up Paint - 300 - 300
GROSS AMOUNT = 88,957.28
NET AMOUNT = 41,621
LABOR.
DELIVERY CHRAGE = 10,000
TOTAL CONTRACT AMOUNT = 51,621
CLOSED C = 50,000
Roofing Materials Cost = 50,000
Labor Cost = 5,200
TOTAL COST = 55,200
SPANDREL MATERIALS
Qty - Items - Unit/Price - Total
373.5LM -Spandrel 0.40 - 85.5 - 31,952.93
24pcs - Fascia MLDG 0.40 - 136 - 3,264
25pcs - End MLDG 0.40 - 136 - 3,400
3pcs - Bfly MLDG 0.40 - 136 - 408
1,000pcs - Blind Revits - 0.40 - 400
1kilo - Concrete Nail - 150 - 150
1Can - Touch-Up Paint - 300 - 300
GROSS AMOUNT = 39,874.93
NET AMOUNT = 17,197.95
TOTAL CONTRACT AMOUNT = 17,197.95
CLOSED C = 17,000
MATERIALS SPANDREL = 17,000
LABOR COST = 6,125
TOTAL COST = 23,125
Pag Hukay para sa Septic Tank...Labor Cost 1,750 Pesos
Septic Tank
Materials = 8,220
Labor = 3,375
Car Rent = 2,500
TOTAL = 14,095 PHP
Flooring....
Materials = 24,274
Labor = 8,625
Snacks = 645
TOTAL = 33,544 PHP
Electricity...
Materials = 44,816
Labor = 13,420
Snacks = 959
Materials Fare = 350
Total = 59,545
3pcs - Hamba Door - 2,000 - 6,000
1kl - Nail - 70 - 70
TOTAL = 6,070
Plastering
Materials = 39,810
Labor = 51,525
Snacks = 2,218
Materials Fare = 377
Total = 93,930 PHP
Windows and Doors
Labor Materials = 60,000
Snacks = 455
Primer Materials = 635
Total = 61,090 PHP
TOTAL COST 774,737 PHP
$15,494 USD
This House is Located in
Vintar Ilocos Norte Philippines
Dont Forget to Like and Subcribes😊
Thank You for Watching and Have a Good Day💗
#katasngofw #ofwhousesinthephilippines #buildingahousestepbystep
💝💝💝🏠🏠🏠💝💝
🏡 FACEBOOK PAGES
/ randyreovocayerro
🏡 Facebook Acount Randy Reovoca Yerro
/ dhoy.ranz.9
💝💝💝🏠🏠🏠🏡🏡🏡💖💖💖
🏡PAPULAR VIDEOS
1. • Katas ng OFW, OFW SIMP...
2. • OFW SIMPLE HOUSE BAHAY...
3. • Katas ng OFW, OFW SIMP...
4. • SIMPLE HOUSE CONGRATS ...
5. • OFW SIMPLE HOUSE,CONGR...