This problem walk-though video will demonstrate how to crash a project after determining drawing the network diagram and determining the critical paths.
NOTE:
From 7:09 to 10:23 there is a typo in some of the columns relating to Path 3:
The Blue Wave 1 column should read -1=19
The Green Wave 2 column should read -2=17
The Orange Wave column should read -1=16
These were actually corrected at 10:24 going forward.
Those typos do not change the final crash results and costs.