You forgot to mention that when you run the Generate WO or the PMWOGENCronTask, it will use the Generate Ahead By + Lead. For example I have a lead=10 and generate ahead by = 5, therefore it will look 15 days before the estimated start date. I recommend not setting the Generate Ahead By because the padding can easily be varied using the Lead field.
@SudharsanR-x4r Жыл бұрын
Hey Team, This is a great video, kudos for such a detailed preview on the module. I would love to know something more on PPM and Job Plam (JP). If a JP of a version is associated to the PPM and it has been generating work orders, and then if the JP is updated to a newer version (making it ACTIVE). Will the PPM automatically associate itself with the JP of the latest ACTIVE version?
@MaximoSecrets7 ай бұрын
Yes, once the Job plan revision is made Active, it is the one applied with a PM. A Job Plan at PNDREV (Pending Revision) can not be applied to a work order.