How did you create the WD layout? Provide steps please and thank you sir
@CpmsolutionsCa5 жыл бұрын
The Working Days is a User Defined Field that was created under the Enterprise>UDF menu. A Global Change function (under Tools>Global Change) was created that made "(Working Days = Original Duration) / 8". This is assuming all the calendars are using an 8 hour day, as shown in the example. If you have a WBS node that is using a different number of hours per day, then your Global Change statements will need to be bit more complex to take into account the different hours per day.
@australiateluguvlogs1435 жыл бұрын
@@CpmsolutionsCa Awesome mate. Thanks for the help.
@Sh-tx8gy4 жыл бұрын
@@CpmsolutionsCa i did everything but grand total is not showing in the working days coloumn in wbs level, only the activity duration showing
@neveenmohammed51197 жыл бұрын
It's very useful And help me to solve a problem in my program thanks a lot