Reserve Analysis - Contingency Reserve and Management Reserve

  Рет қаралды 9,619

PMC Lounge

PMC Lounge

Күн бұрын

Пікірлер: 17
@pmclounge
@pmclounge 2 жыл бұрын
Check out more Schedule Management videos here goo.gl/sKpxmP Also, Cost Management videos: goo.gl/4ZRw4N and Estimation Technique videos: goo.gl/gijvbg
@YOUEC15
@YOUEC15 3 жыл бұрын
Contingency reserve...is definitely not only includes buffer time, it for sure includes funds also
@amikorwa
@amikorwa 2 жыл бұрын
Sir when is actually project reserve analysis done i.e. during plan risk management or planning risk responses or monitor and control risk or qualitative risk analysis?
@pmclounge
@pmclounge 2 жыл бұрын
Hi Amit, note that Reserve Analysis is actually a planning tool that can be used in planning processes like 'Estimate Activity Duration' as an example. Don't forget to subscribe for more 😊👍
@Eng.Ibrahim_Khalid
@Eng.Ibrahim_Khalid 20 күн бұрын
Can I write some conditional funding in the charter instead of Reserve Analysis? For example, as you mentioned if we hit big rocks that would cost 50k$, but if we didn't that money would be an extra profit for the Project Manager. Which will be questionable to the Project sponsor and unwelcome. So can we just write conditional funding in the charter that says (If we hit big rocks 50$K will be funded otherwise, the project manager won't be responsible).
@pmclounge
@pmclounge 13 күн бұрын
While it might seem tempting to add conditional funding directly into the charter, it’s generally not recommended. Reserve Analysis exists specifically for those 'big rocks' or unexpected risks, and needs to be planned for. Writing conditional funding into the charter could raise concerns with the project sponsor. Instead, it's better to handle such risks through well-defined reserves. Thanks for bringing up a good discussion point though! 👍
@sumitmitra7336
@sumitmitra7336 2 жыл бұрын
If for a planned risk response ( A vendor defaulting on supplying project related equipment's), a contingency reserve is kept & as the project progresses , that risk doesn't happen , then what should the PM do next 1. Update the risk register & release the contingency reserve associated with that risk 2 . Retain the contingency reserve as a buffer for overall project risks 3. Inform the project sponsors & stakeholders that the procurement equipment's have been successfully purchased 4. Update the lessons learnt register stating that contingency reserve was not necessary
@N3770SS
@N3770SS 3 жыл бұрын
This video was a lifesaver for a presentation I needed to do. Thank you.
@pmclounge
@pmclounge 3 жыл бұрын
You're welcome. Don't forget to subscribe 👍🙂
@robertmusilli5198
@robertmusilli5198 3 жыл бұрын
great
@pmclounge
@pmclounge 3 жыл бұрын
Thank you Robert 😊👍
@ameenpcc
@ameenpcc 4 жыл бұрын
Suppose a PM had a contingency reserve for his project as well as the management had a management reserve for the same project. Now the project has been completed successfully (cheers!) and no risk was materialized. Therefore no reserve was utilized. Now how to use or release these reserves? Who is authorized to release, who are the recipients, what is the process? Appreciate your detailed explanation.
@pmclounge
@pmclounge 4 жыл бұрын
The project manager has the authority to release the contingency reserve back to management. In real life, if there really is a project that went out without any hiccups, the project manager might as well ask the management to spend a part of contingency reserve on a lunch outing 😉👍
@Kathaisolli_storyteller
@Kathaisolli_storyteller 4 жыл бұрын
Excellent Explanation
@pmclounge
@pmclounge 4 жыл бұрын
Glad you liked it 👍😊
@dulsafuminoro2688
@dulsafuminoro2688 5 жыл бұрын
I love this channel!
@pmclounge
@pmclounge 5 жыл бұрын
We love you 3000 😉😊
Top Down and Bottom Up Estimating Techniques
5:56
PMC Lounge
Рет қаралды 19 М.
Пришёл к другу на ночёвку 😂
01:00
Cadrol&Fatich
Рет қаралды 11 МЛН
How To Get Married:   #short
00:22
Jin and Hattie
Рет қаралды 22 МЛН
Will A Guitar Boat Hold My Weight?
00:20
MrBeast
Рет қаралды 254 МЛН
Develop Schedule Process
10:13
PMC Lounge
Рет қаралды 4,2 М.
What is Contingency Reserve in a Cost Estimate?
11:28
Project Control Academy
Рет қаралды 11 М.
Parametric Estimation | Tools and Techniques
10:20
PMC Lounge
Рет қаралды 15 М.
What to Put in Your Risk Register (Risk Log)
11:08
Online PM Courses - Mike Clayton
Рет қаралды 64 М.
Risk Identification: How to Identify Project Risks
13:20
Online PM Courses - Mike Clayton
Рет қаралды 15 М.
Leads and Lags with examples
11:21
PMC Lounge
Рет қаралды 9 М.
Analogous Estimation | Tools and Techniques
10:57
PMC Lounge
Рет қаралды 10 М.
Earned Value Management Technique - Formulas and Explanations
12:04
Пришёл к другу на ночёвку 😂
01:00
Cadrol&Fatich
Рет қаралды 11 МЛН