brother, i have actual start and finish date in my baseline, when i assign the baseline its not showing me actual start date in BL project start date...pls advise
@SoftEdemy2 жыл бұрын
Dear ahmed, contact me at wa.link/36dp7i
@reginaldibenne68755 ай бұрын
Great video..What of in a situation a delay occur in an activity with Total Float of 4 days while the delay lasted for like 10 days, when do I need to report delay evne in this case?
@SoftEdemy5 ай бұрын
@reginaldibenne6875 if total float is 4 days. And the calendar assigned is 7 days calendar than the delay impact for 10 days will be only 6 days on the schedule . Better to find out other zero float activity which is also relevant and have 10 days delay .otherwise no other option as you cannot create new critical path for baseline programme.