do we add the project manager, project coordinator, superintendent and other management personal in site management activity?
@galvanizedgnome2 жыл бұрын
No
@RLB522 жыл бұрын
Very helpful
@UjangSonjaya4 жыл бұрын
Should we develop level of effort in the project? Is in the first activity of project? Is in the last / project close out of project?
@LEARNPROJECTMANAGEMENT5 жыл бұрын
Why the LOE got both relations as Predecessor? why we can assign its relation as Pred and Succ with SS and FF respectively. Appreciate your Response
@bustinjimberlake66444 жыл бұрын
Wondered the same thing. Seen it both ways on various videos.
@roganfield89554 жыл бұрын
It could either be in predecessor or successor since it is a FF relationship ..and both are correct..
@holinesswithinandwithout2 жыл бұрын
LOE is a summary activity and can be used to obtain the duration between activities without having a critical path represented, so using SS-FF between activities tells u the duration between what ever activities u need.
@rorygrant4824 Жыл бұрын
Should do it with predecessor and successor otherwise you will have open ends and fail schedule health check
@sanachaieb93015 жыл бұрын
how vannot -make-task-name-visable-gantt-chart Primavera P15.2