The implementation of its urban regeneration project is in full progress in Elliniko, with Lamda Development announcing that it has significantly accelerated the pace of implementation of its strategic plan for infrastructure projects.
Mr. Athanasiou pointed out that the infrastructure works of the first phase of Hellinikon will start immediately from the contractor who has been announced after a tender, while in October the first excavations for the construction of the Marina Residential Tower project will begin. A Tower that will be the highest green skyscraper in the Mediterranean and aspires to become a new landmark at the European level.
Regarding the project of undergrounding Poseidonos Avenue, excavation has already progressed to 50% of the total volume. The aim is to maximize the reuse of excavated products in other areas of the project, such as the Park.
It is a 1.5 km long road, of which over 1 km (1,150 m) is the underground section with 3 traffic lanes in each direction.
The new road section will make a decisive contribution to traffic congestion, while the current L. Poseidonos will be replaced by a light traffic road.
Regarding the EAKN (National Youth Sports Center), in less than 3 months, around 100 athletes were moved to furnished apartments in nearby areas in terms of their training areas.