Unions controlled by organized crime helped stretch out construction time to 15 years and add to the $4 billion cost overruns of Long Island’s Shoreham nuclear power plant.
Two of the plant’s former workers said mob-influenced unions had absolute control of work at the power plant in Suffolk County. The plant, built over 15 years at a price of $4.2 billion - nearly $4 billion over its originally estimated cost.