Thanks for the useful and valuable tips! My question: capacity planning in person days, stories in points - where is the bridge between both of them? From managment side always PD are interesting, but how to satisfy management needing PD information?
@GaboCh2000 Жыл бұрын
Good question. Use the same unit for Capacity and SP. For example, 8 days capacity, 1SP for each day. Size the tickets accordingly. If 1 SP it should take one day to complete and so on.
@variousfaces3127 Жыл бұрын
To be honest that hardly works in reality, since the estimation is done by the devs, they are really confronted with a challenge to estimate complexity and then return to person days again, that confuses people and is simply not accepted... 🙈