Sir JC, is your formula the same as getting the weighted percentage per scope of work with the formula "total cost of the certain scope divided by the total cost of the project?" Thanks in advance for your response!
@salt1093
@salt1093 Ай бұрын
Hi JC - I have one error in the Baseline Duration Total column at a task which was added after the baseline was set. I am currently on baseline 5. The project currently has 2208 activity lines. Some have been deleted (removed from scope) and this specific one task added - which is showing the error. Baseline Days Completed shows a number (411). The 'Planned Completion Value' column also shows an error - I assume this is due to the error in the 'Baseline Duration Total' column. Can you please help me resolve this, is there a way?
@ozlembugan1784
@ozlembugan1784 2 ай бұрын
Hi again :) I wanna ask that; Can we show these columns (% planned and % complete) in a S-chart to compare them?
@JCleRouxx
@JCleRouxx Ай бұрын
Yes you can but it takes a bit of work. You would need to shift your timenow date through the months of the project and then export those monthly planned % values to Excel.
@ozlembugan1784
@ozlembugan1784 Ай бұрын
@@JCleRouxx Are you gonna share a video about this topic?
@olalekanadeyemi249
@olalekanadeyemi249 2 ай бұрын
I'm wondering how to get the cumulative planned % complete. Thanks
@fr9nki46
@fr9nki46 2 ай бұрын
Hi JC, great video! Will definitely adjust my calculation. But have you ever taken your calculation and added a weighting factor? I need to weight the schedule based on cost as some tasks duration doent justify the overall weighting against the project. PLEASE I require your help
@arny82
@arny82 2 ай бұрын
This is just brilliant thank you. I am getting a few errors on summary tasks, any idea why? I have followed your guide step by step. I noticed the summary tasks that display errors are the one which I have added some blank fields underneath them...your help is much appreciated
@EV-hj6fc
@EV-hj6fc 2 ай бұрын
How do you update notes or daily communication, changes and tasks?
@ozlembugan1784
@ozlembugan1784 2 ай бұрын
Hi JC. Thanks for the tutorial. I tried to apply this on my project and I encountered an error. MS project doesn't allow me to write the part 0,0.01, which is in formula below. It says "The formula contains a syntax error or contains a reference to an unrecognized field or function name." What else can I use? IIf([Duration]=0,0.01,ProjDateDiff([Baseline Estimated Start],[Baseline Estimated Finish])/60/8)
@JCleRouxx
@JCleRouxx 2 ай бұрын
Maybe your windows setting requires a point instead of the comma? Maybe try that and see if it works?
@JCleRouxx
@JCleRouxx 2 ай бұрын
Also check, your formula is missing the last bracket... IIf([Duration]=0,0.01,ProjDateDiff([Baseline Estimated Start],[Baseline Estimated Finish]))
@ozlembugan1784
@ozlembugan1784 2 ай бұрын
@@JCleRouxx I wrote it this way "IIf([Duration]=0;0,01;ProjDateDiff([Baseline Estimated Start],[Baseline Estimated Finish])/60/8)". The formula accepted. Thank you for your help.
@IreshaWickramasingh1
@IreshaWickramasingh1 3 ай бұрын
Hi JC, Thank you so much for sharing this and it is very helpful. I'm taking the planned percentage by updating the baseline program to the status date and then pasting it as text into the updated project file. I've tried to apply your advice, but the manually calculated planned value I derived by updating the baseline program to the status date differs from the calculated value you taught me. For example, my manually calculated percentage is 39%, but when I use the calculation method you provided, it becomes 42%. Do you have any guesses about what might be going wrong?
@JCleRouxx
@JCleRouxx 2 ай бұрын
Difficult one, there could be various reasons. Perhaps in the way you update the baseline programme. Do you use % complete or remaining duration in your update?
@IreshaWickramasingh1
@IreshaWickramasingh1 2 ай бұрын
@@JCleRouxx I used % complete
@FarazKhan-bn8rn
@FarazKhan-bn8rn 3 ай бұрын
I am still wondering why you need such complex formulas when you can just add a cost to an activity and use the earned value field to get the plan and actual % 😅😅😅😅😅😅😅😅😅😅😅
@JCleRouxx
@JCleRouxx 3 ай бұрын
True! 😅 However, the formula can be saved and applied to all projects and therefore you have a quick way of comparing planned vs actual without having to cost load your schedule each time.
@katybunja8566
@katybunja8566 Ай бұрын
how to get actual and plan percentage based on cost?
@anshulkushwaha4350
@anshulkushwaha4350 3 ай бұрын
can we also use it to create a planned percentage based on late dates?
@JCleRouxx
@JCleRouxx 3 ай бұрын
I think you will be able to, I'll have a look.
@milner267
@milner267 4 ай бұрын
Thanks JC. for clarity, I saw you sped through the part where you'd have to baseline the newly added tasks. would that baseline activity have to be done every single time a new task is added?
@JCleRouxx
@JCleRouxx 3 ай бұрын
Yes, you need the baseline as part of the formula to indicate the planned value. So if you add tasks, you have to baseline again before you obtain the planned % value.
@milner267
@milner267 3 ай бұрын
@@JCleRouxx thanks a lot JC. Any concerns regarding the fact that the client bday have an approved baseline, out wood want to track also, the items which were not part of an initial baseline? I can see that raising stakeholders' eyebrows, re-Baselining every time, especially as MSP records the date BL'd
@sameerapremarathna3956
@sameerapremarathna3956 4 ай бұрын
Please upload more videos
@shivsaurabh5922
@shivsaurabh5922 4 ай бұрын
Your starting assumption is wrong. % complete in msp means ( % planned complete) and we have to customise formula for % actual complete
@JCleRouxx
@JCleRouxx 4 ай бұрын
Not sure what you base this on. % complete is only populated once you start adding actual values to the schedule.
@shivsaurabh5922
@shivsaurabh5922 4 ай бұрын
@@JCleRouxx correct, my mistake
@roldanduarteholguin7102
@roldanduarteholguin7102 6 ай бұрын
We want to share with Companies, Universities and Governments 57 years of successful professional experience in several countries, in Oil and Gas, Petrochemical, Steel, Hydroelectric, Engineering and Construction Projects. Since 1981 we have been developing the Digital Twin, which is the most complete technological tool to optimize all types of Compa-nies, Cities and Countries. kzbin.info/www/bejne/m5LHkoSfgcR0gZI kzbin.info/www/bejne/nInPoWeHgcmKh9U
@roldanduarteholguin7102
@roldanduarteholguin7102 6 ай бұрын
Export the Azure, Chat GPT, Revit, Plant 3D, Civil 3D, Inventor, ENGI file of the Building or Refinery to Excel, prepare Budget 1 and export it to COBRA. Prepare Budget 2 and export it to Microsoft Project. Solve the problems of Overallocated Resources, Planning Problems, prepare the Budget 3 with which the construction of the Building or the Refinery is going to be quoted.
@Johanswnpl
@Johanswnpl 7 ай бұрын
Faaaaaanks !!
@JCleRouxx
@JCleRouxx 4 ай бұрын
You're weeeeelcome! 😊😊
@AJ-nm9gb
@AJ-nm9gb 7 ай бұрын
but isnt cost same? , in real world cost per litre of fuel keeps changing right?
@abdellahfaouzi1412
@abdellahfaouzi1412 8 ай бұрын
Thank you so much you saved my life !!!! I subscribed to your channel . For those who found the problem of the appearance of zero (0) for all values, you must check that you saved baseline of your project.
@JCleRouxx
@JCleRouxx 4 ай бұрын
That's great news! Thanks for the additional tip.
@gopalmahajan4140
@gopalmahajan4140 8 ай бұрын
That activity will be critical than, how to avoid that activity in the critical activity chart?
@ig7061
@ig7061 8 ай бұрын
Hello, thanks for the video. I have one issue that I cannot fix. For example, I have a project manager who is involved in the whole project from start to finish, but it is very difficult to assign to him all the tasks that I have in the project because they overlap, and it is too hard to control from an overallocations point of view. Is there any trick to assign the project manager (PM) to the entire project without causing overallocations?
@gopalmahajan4140
@gopalmahajan4140 8 ай бұрын
PM can be allocated to the activities explained. The common resources can be used there. This shall not hamper
@mohasoamakara5085
@mohasoamakara5085 9 ай бұрын
This is awesome. May I ask how can I contact you? I would like to volunteer in one of your projects!
@timothylim-x8x
@timothylim-x8x 9 ай бұрын
Hi, can i get some help. Actually i just need to show my target % vs actual % I've been searching 100 videos, and none have done so. is microsoft project unable to do such simple task? im abit frustrated
@milner267
@milner267 10 ай бұрын
Thanks so much for sharing. a question for you: is there a way to show this as either an "S-curve" within the report tab, or within task usage?
@milner267
@milner267 7 ай бұрын
Hi JC, still interested in this topic. is it possible to see within task usage? because while it is possible to see at at a status data, what was planned, key stakeholders would want to know what that curve would look like. any help would be appreciated
@jonnyland7
@jonnyland7 11 ай бұрын
Great! it solved my problem in a big project!
@JCleRouxx
@JCleRouxx 4 ай бұрын
Awesome!
@weamibrahem4736
@weamibrahem4736 11 ай бұрын
Very interested.. Can we get the formula that you used
@JCleRouxx
@JCleRouxx 4 ай бұрын
You can find the formula here - bit.ly/3KxKyI2
@benpienaar2310
@benpienaar2310 Жыл бұрын
Thank you Kobus! Almost all of my headings and tasks calculates the % planned perfectly except a few Headings that shows ERRORS. Any advice?
@GilbertoMartinez-f2u
@GilbertoMartinez-f2u Жыл бұрын
Did you set the baseline?
@benpienaar2310
@benpienaar2310 Жыл бұрын
@@GilbertoMartinez-f2u That helped! Thank you!
@nimarafienejad6466
@nimarafienejad6466 9 ай бұрын
I faced the same issue and after few hours noted that those Task lines added to schedule after setting the Baseline. maybe this is your issue as well?
@ig7061
@ig7061 Жыл бұрын
Thanks !!!
@aseyeaflakpui3859
@aseyeaflakpui3859 Жыл бұрын
Hi JC, Thank you for this video. I am facing a challenge here. I followed all the steps but I am getting 100% for all activities including the ones yet to start. What could be the problem?
@aseyeaflakpui3859
@aseyeaflakpui3859 Жыл бұрын
I think I've found what the problem is. I hadn't set my status date. Thank you
@dantevanniekerk
@dantevanniekerk Жыл бұрын
Kobus... How do I get hold of you to make use of your services?
@dunyojustice4050
@dunyojustice4050 Жыл бұрын
Please how can have access to the software I'm interested
@honeystarism
@honeystarism Жыл бұрын
Hi, thank you for this tutorial. I tried following the steps, but some of the tasks are #ERROR. Is this caused by the duration, as some of my tasks are in weeks and months. Can you help? Thank you.
@nimarafienejad6466
@nimarafienejad6466 9 ай бұрын
I faced the same issue and after few hours noted that those Task lines added to schedule after setting the Baseline. maybe this is your issue as well?
@funfunny9319
@funfunny9319 Жыл бұрын
Thanks JC for sharing this. Am I correct if I say every time you insert delays, you set a new base line? If yes, how we can record lets say 20 different delays on a project? I am asking this because we can set up to 11 baselines on microsoft project.
@TheEugenezandberg
@TheEugenezandberg Жыл бұрын
Awesome vid ! Only problem is that I keep getting a syntax error when using your formula .. I even tried to "retype" the highlighted error but to no avail :( Any advice ?
@JCleRouxx
@JCleRouxx Жыл бұрын
Hi Eugene, difficult to tell without looking at the input. It may just be a misplaced space or bracket causing the issue?
@TheEugenezandberg
@TheEugenezandberg Жыл бұрын
@@JCleRouxx I was very careful to follow the exact sintex and spacing but still doesn't work
@ShadiEdalatian
@ShadiEdalatian Жыл бұрын
Thank you. the video was great.
@JCleRouxx
@JCleRouxx 4 ай бұрын
Thanks man! So happy you found it valuable.
@nazirramguthee6568
@nazirramguthee6568 Жыл бұрын
Hey JC, what is the document you presented in the last section called?
@adrianmondolo
@adrianmondolo Жыл бұрын
Hi! I have a question. Is there any way to change the actual status date? in order to open the project and have the time to create a report with the status of one week ago for example.
@JCleRouxx
@JCleRouxx Жыл бұрын
You will have to set the status date on the Project tab each time.
@shaileshmodhia7600
@shaileshmodhia7600 Жыл бұрын
Sir nice explained. However formulas used in customised columns could not be seen. Will u provide the formulas
@JCleRouxx
@JCleRouxx Жыл бұрын
You can find the formulas here - lerouxconsulting.com/ms-project-for-construction-articles-and-resources/creating-a-planned-percentage-complete-field-in-microsoft-project
@adrianmondolo
@adrianmondolo Жыл бұрын
you are the love of my life!! you explained this really easy and slow. I couldn't ask for more. Thank you sooooo much! 🥰
@JCleRouxx
@JCleRouxx Жыл бұрын
🤣 Great to hear. You'll have to get past my wife first though!
@SteveMcQueen-m1k
@SteveMcQueen-m1k Жыл бұрын
The deeper you get into the subtasks, the less accurate it becomes. Level 1 +- 1%, level 2 from %1 to 2%, level 3 up to 3%. i use the formula set at your link page. did i set something wrong?
@JCleRouxx
@JCleRouxx Жыл бұрын
Interesting. The formula gives me solid accuracy even in lower levels. Just double check if you've set the summary settings correctly?
@gayatrilshinde1560
@gayatrilshinde1560 Жыл бұрын
is we have column name baseline estimated start and finish date or we have to use baselinestart and finish date
@JCleRouxx
@JCleRouxx Жыл бұрын
Use the Baseline Estimated Start and Baseline Estimated Finish in the formula. These are standard fields in MSP already.
@pwardseitz
@pwardseitz Жыл бұрын
Very interesting use of this tool. The big question is how does actual cost data get entered? If it can pull from the accounting software, this is an exciting way forward for us. If it involves manual entry, not so much.
@JCleRouxx
@JCleRouxx Жыл бұрын
Good point. I'm sure you would be able to draw it in from Excel, so if you can get your actuals out into excel and bundle them under the BOQ items, it should be possible.
@morganshongwe6501
@morganshongwe6501 Жыл бұрын
Wow Thanks JC this really worked, ive been strugling
@JCleRouxx
@JCleRouxx Жыл бұрын
Aah Morgan, great news. I've also had my fair share of struggling with this %-complete column.
@JuanPerez-hb5kb
@JuanPerez-hb5kb Жыл бұрын
Hi JC, I am JC as well. I really liked the tutorial on the correct way to show Planned %. I do have a question, does MS Project have Labor Units? I have not seen this
@JCleRouxx
@JCleRouxx Жыл бұрын
Hi JC! . MS Project can only show labor units in "manhours". You can certainly export the data and then convert it if you like.
@milkymikez100
@milkymikez100 Жыл бұрын
Great thanks
@Ben-q1x5o
@Ben-q1x5o Жыл бұрын
Beautiful
@JCleRouxx
@JCleRouxx Жыл бұрын
Thanks Ben!
@abhishekdwivedi1692
@abhishekdwivedi1692 Жыл бұрын
Very nice presentation. 👍👍
@Shahadaleqiel
@Shahadaleqiel Жыл бұрын
Hi, I face an issue we are behind schedule and the summary task shows we are ahead, that incorrect. so I follow the same as you did but I got an error in the summary task. how can I fix that? thanks in advance!
@JCleRouxx
@JCleRouxx Жыл бұрын
Hi Shahad. There can be many reasons for this. It could be that some of the tasks below the summary task is not included in Baseline, or that a Baseline does not exist for certain tasks. Also check that the status date is correctly set, check for any manual schedule tasks.
@Shahadaleqiel
@Shahadaleqiel Жыл бұрын
@@JCleRouxx can you please help me with that I tried to fix the issues for 2 months if you can give me your email so we can discuss these issues it will be much appreciated! this task Is much important to me
@Shahadaleqiel
@Shahadaleqiel Жыл бұрын
Hi, when I followed up on the steps, I got 1 for all activities in the Updated % planned? so the planned percentages change to 100% based on the Updated % planned column those are issues I face now .. can you help with that?
@susuchen4638
@susuchen4638 Жыл бұрын
Hello JC; I watched your video about the pROJECT, i want ask you how you make the sheet with dependencies and delayed shecedule,
@JCleRouxx
@JCleRouxx Жыл бұрын
Hi Susu. You can simply add those fields in your view to have the same sheet. To do the update requires a more complex process which is a bit cumbersome to explain here. Have a look at our other videos or consider the course where this is explained in detailed, step-by-step.