Crews are constructing the piers for the new BNSF Railway bridge over the Missouri River at Bismarck and Mandan. After a brief pause during winter, work began with pile driving for Pier 9 on the west side and will begin soon for Pier 8 near the west riverbank.
Barges have been assembled to serve as a base for equipment used during in-water construction, including long-reach excavators, cranes, bucket lifts, welders, and pile hammers.
With barges in place, preparation is underway for work at Pier 7, one of the two piers in the main river channel. Throughout the project, the river will always have an open channel for recreational users.