Civil PE Exam - Construction - Benefit to Cost Ratio of a Bridge

  Рет қаралды 25,736

Civil Engineering Academy

Civil Engineering Academy

Күн бұрын

Пікірлер: 13
@ccbanka
@ccbanka 10 жыл бұрын
For (P/F,15,7%) I got 0.3624 (appears the 0.5083 value used in the video is for 10 years, not 15). Also, for (P/F,7%,25) I got 0.1842 (not 0.6227). The B/C ratio I calculated is 1.15. Thank you very much for these videos. They have been outstanding and a great help.
@CivilEngAcademy
@CivilEngAcademy 10 жыл бұрын
ccbanka Thank you for catching this! I don't know what I was looking up..I think it was late night! I have corrected the video with some comments so I hope it helps others that check it out.
@serpico3312
@serpico3312 10 жыл бұрын
Civil Engineering Academy I get 1.14 which is not much different than ccbanka. We all make mistakes; aside from that, the videos are great! Keep making the videos.
@tiancaidexiongxiong
@tiancaidexiongxiong 7 жыл бұрын
Here is what I got: (7*9.1079+10*7.0236*0.3624+15*0.1842)/80=1.15
@alimoh1984
@alimoh1984 7 жыл бұрын
Thanks for adding the corrections on the video as caption. thanks for your time
@cocoon757
@cocoon757 8 жыл бұрын
why annual cost of repairing the bridge does not count as cost (Denominator)?
@AbidAli-bv2gl
@AbidAli-bv2gl 10 жыл бұрын
Sir, you are doing great, Keep going on.You will be the best teacher for PE exam
@cdf4013
@cdf4013 8 жыл бұрын
Can I put the increase of salvage value as my benefit and use initial cost (80k) as my total cost for calculating B/C? By the way, thanks for your great video.
@supermanny73
@supermanny73 10 жыл бұрын
Where can I find the corrected video? Thanks.
@supermanny73
@supermanny73 10 жыл бұрын
Sorry, I just saw the notes and corrections. When I first saw this video, it was on my cell phone and the notes were not appearing. Excellent video...keep up the great work!!
@adamalday01
@adamalday01 8 жыл бұрын
The book recommends superposition for stepped cash flows. When I try this method I don't come up with the correct present value.Any idea why?
@CivilEngAcademy
@CivilEngAcademy 8 жыл бұрын
Your calculation should be close to the solved solution. Maybe you used incorrect value from the table. I tried to use superposition and got close answer in the video. Using superposition: Present value of Benefit = 10*(P|A,25,7%) - 3*(P|A,15,7%) = 10*11.6536 - 3*9.1079 = 89.2123 Your solution: Present value of Benefit = 7*(P|A,15,7%) + 10*(P|A,10,7%)*(P|F,15,7%) = 7*9.1079 + 10*7.0236*0.3624 63.755 + 25.45 89.205
@adamalday01
@adamalday01 8 жыл бұрын
Thank you for the response
Construction-Cable Statics Problem
7:43
Civil Engineering Academy
Рет қаралды 42 М.
Construction-Estimating Labor Costs for Work
5:43
Civil Engineering Academy
Рет қаралды 114 М.
OCCUPIED #shortssprintbrasil
0:37
Natan por Aí
Рет қаралды 131 МЛН
Geotechnical - Soil Phase Diagram for Dry Density
6:13
Civil Engineering Academy
Рет қаралды 36 М.
Construction   How Many Trucks are Needed to Fill a Compacted Trench
6:50
Civil Engineering Academy
Рет қаралды 17 М.
Construction-Find the Float Time at an Activity
8:06
Civil Engineering Academy
Рет қаралды 23 М.
Civil PE Exam - Construction - How to Solve for Total Cutback Width
6:41
Civil Engineering Academy
Рет қаралды 3,4 М.
Geotechnical-Factor of Safety Against Sliding on Retaining Wall
7:16
Civil Engineering Academy
Рет қаралды 105 М.
Civil FE/PE Problem - Quantity Take Off - Find the Total Material Costs for a Ditch
11:47
PE Civil Exam Updates 2024 (PPI2Pass Review)
6:28
Test Prep Insight
Рет қаралды 9 М.
Civil FE/PE Problem - Project Schedules -  How to find the Critical Path
10:23
Civil Engineering Academy
Рет қаралды 6 М.