Project Management: Finding the Critical Path, duration and Project Duration | Critical Path Method

  Рет қаралды 953,994

Civil Engineering Exam

Civil Engineering Exam

Күн бұрын

Пікірлер: 120
@radhikapareek2701
@radhikapareek2701 2 жыл бұрын
Thank you so much sir ☺️ for such a easy explanation 😊.
@CivilEngineeringExam
@CivilEngineeringExam 2 жыл бұрын
Most welcome 😊
@RanjanKumar-vs5ex
@RanjanKumar-vs5ex Жыл бұрын
Tomorrow is my project management exam and I'm watching this video for first time 😃
@beckymwale1512
@beckymwale1512 Жыл бұрын
😅
@addisukorra7322
@addisukorra7322 Жыл бұрын
Activity No. Activity description Duration (days) Depends on 1 Site clearance 2 2 Excavation in foundations 6 1 3 Foundations including plinth beam 10 2 4 Column casting up to roof level 10 3 5 Slab and beam of roof 21 4 6 Earth filling and flooring 10 5FS 1 10d 7 Brickwork 10 5FS 1 7d 8 Doors/windows 3 7FF 9 Plastering 10 7SS 1 7d 10 Painting 7 9SS 1 7d 11 Plumbing 7 7FF 1 3d 12 Electrical works 7 11SS 13 Handover 1 10, 11, 12
@a.zgamer3376
@a.zgamer3376 10 ай бұрын
??😅
@akshaykayapak8209
@akshaykayapak8209 Жыл бұрын
nicely easily explained sir..thank you so much
@SharableMail
@SharableMail 5 ай бұрын
very clear easy to understand thank you
@serbanstere
@serbanstere 2 жыл бұрын
One question. Are there any restrictions regarding the intersections between arcs ? Are them allowed in this method ?
@universeisherestudytime8701
@universeisherestudytime8701 8 ай бұрын
No intersections shouldn't be practiced ... Yes when u make it for the first time u can intersect but then you can make a neatly drawn network
@MAHENDRALANJHI-pe8zo
@MAHENDRALANJHI-pe8zo Жыл бұрын
Thank you sir it is beneficial.
@NairoshiKimisoi
@NairoshiKimisoi 5 ай бұрын
❤❤❤❤❤wow thanks 👍 sir, you teach well ❤❤
@Sunil_bavoor13
@Sunil_bavoor13 2 жыл бұрын
thank you sir for explaining this tomarow I have exam PROJECT MANAGEMENT SKIIL (PMS)
@hemanthgowda.
@hemanthgowda. 2 жыл бұрын
Same
@hemanthgowda.
@hemanthgowda. 2 жыл бұрын
Send some important questions
@parameshnaidu5946
@parameshnaidu5946 11 ай бұрын
Easy manner to understand everyone tq so much bro 😊
@g.vofficial7624
@g.vofficial7624 2 жыл бұрын
Thankyou so much sir good explanation 🙏
@addisukorra7322
@addisukorra7322 Жыл бұрын
Two project activities ‘A’ and ‘B’ (B being dependent on A) have a finish-finish relationship with 8 days ‘lag’. The estimated duration for the activities are 10 days and 15 days, respectively. If activity ‘A’ is scheduled to start on the 12th day from the beginning of project, on which day can you schedule to start activity ‘B’?
@bashirchauhan954
@bashirchauhan954 Жыл бұрын
20th
@Chachustp
@Chachustp Жыл бұрын
15th ?
@nvennela5602
@nvennela5602 11 ай бұрын
16th?
@madhukarnaidunaidu4852
@madhukarnaidunaidu4852 Жыл бұрын
Thank you for the video, useful
@cybershrajal
@cybershrajal 5 ай бұрын
We are computer science student watching this
@Sisterdiya
@Sisterdiya 4 ай бұрын
Thank You Respected Sir for teaching me so well during my examination days. You have been a blessing for all these days. Thank You Dear and Respected Sir. Thank You. God bless you and your family always. ❤️🙏✝️
@adabalanagavenkatavinay1485
@adabalanagavenkatavinay1485 Жыл бұрын
Super explanation sir thanku so much
@saurabhpandey3535
@saurabhpandey3535 2 жыл бұрын
Nice video 👌. Well explained.
@CivilEngineeringExam
@CivilEngineeringExam Жыл бұрын
Thanks a lot 😊
@johnkallonyokie
@johnkallonyokie 7 ай бұрын
Very clear and understandable thanks
@shiva_rocky
@shiva_rocky 2 жыл бұрын
Sir good explanation thank u 😊
@amaliaazufa5232
@amaliaazufa5232 2 жыл бұрын
thanks for the explanations
@nikhithab4631
@nikhithab4631 Жыл бұрын
Easy way and good information sir
@vinayakbadiger2063
@vinayakbadiger2063 Жыл бұрын
Well explained
@prajyotdeshpande6602
@prajyotdeshpande6602 Ай бұрын
How can longest path determine minimum amount of time required by project
@029_menaha4
@029_menaha4 Жыл бұрын
Thank you for this video sir
@learnwithb2138
@learnwithb2138 Жыл бұрын
Thank you sir 🙏
@Elevateeveryday-w8t
@Elevateeveryday-w8t Жыл бұрын
So nice ❤
@alindayu
@alindayu Жыл бұрын
Very similar to operation management: production routing planning.
@harshitmishra9852
@harshitmishra9852 2 күн бұрын
Thanks u sir
@DhirendraBhujel-b5b
@DhirendraBhujel-b5b Ай бұрын
Thsnks so much sir
@exploremindtech882
@exploremindtech882 2 жыл бұрын
Nice bhai
@dularakavindu1743
@dularakavindu1743 6 ай бұрын
Thank you so much ❤
@ucantbeat2256
@ucantbeat2256 2 жыл бұрын
Verry nice
@66_priyeshgurjar97
@66_priyeshgurjar97 11 ай бұрын
Sir How long will it take to Complete the Project and Critical Path Duration Is same???
@CivilEngineeringExam
@CivilEngineeringExam 11 ай бұрын
yes
@vanditapatil5442
@vanditapatil5442 Жыл бұрын
How to put numbers in the circles. I wanted explanation for how to number the events correctly
@CrimeMasterGogo900
@CrimeMasterGogo900 Жыл бұрын
Sir Path BEIJ Is possible or not and if not than why sir plz reply
@abhimanyudoesanything
@abhimanyudoesanything Жыл бұрын
see the arrows its opposite
@shafiqahmed3391
@shafiqahmed3391 2 жыл бұрын
Hi. Do you do assignments? Related to construction management?
@johnyumbezuze1958
@johnyumbezuze1958 Жыл бұрын
Yes
@shaikhfaiz3450
@shaikhfaiz3450 Жыл бұрын
Critical path will be same for everyone or its depends upon different people draw different kind of network draw ? Plz ans me sir or any one plz ?
@CivilEngineeringExam
@CivilEngineeringExam Жыл бұрын
same for all
@AlbatrossInstmine
@AlbatrossInstmine Жыл бұрын
Sir why can't we take B - F - I - H . It will be the the critical path as 4 + 5 + 12 + 22 = 43 , Hence critical path will be 43.
@faithkarimi147
@faithkarimi147 Жыл бұрын
Yeah the same question am asking
@_lessthanzero_
@_lessthanzero_ Жыл бұрын
Check the video again
@rajanbhattarai4229
@rajanbhattarai4229 Жыл бұрын
The time duration of i is 2 not 12
@TechNepal8945
@TechNepal8945 Жыл бұрын
i think this question /answer both are wrong bro there is no activity connected in loop .
@techgarg4250
@techgarg4250 Жыл бұрын
Bhai waha 2 hai not 12 please it again
@magedrefat1658
@magedrefat1658 Жыл бұрын
Very clear
@danielmbozi3204
@danielmbozi3204 10 ай бұрын
But the line you used classify it so short become hard for me to validate the critical path
@samuelzvirevo4481
@samuelzvirevo4481 5 ай бұрын
am confused on activity H,,,,,to put E andJ
@maingadave4841
@maingadave4841 Жыл бұрын
A nice one but am struggling to learn the english
@abunoman1838
@abunoman1838 10 ай бұрын
thanks
@vengalabhaskar
@vengalabhaskar 2 жыл бұрын
is it possible to explain with site activities in a construction site ?
@CivilEngineeringExam
@CivilEngineeringExam 2 жыл бұрын
sure
@md-pind.wala3323
@md-pind.wala3323 2 жыл бұрын
Good
@clema3official
@clema3official 23 күн бұрын
❤❤❤
@danielmbozi3204
@danielmbozi3204 10 ай бұрын
It is so critical
@saravanan02
@saravanan02 10 ай бұрын
Sir CE3302 Important mattum podunga sir pls
@bbrakesha4659
@bbrakesha4659 Жыл бұрын
Thinks sir
@sudhanshurohela
@sudhanshurohela 2 жыл бұрын
Shortest duration ko select kyu nahi kiya
@muhammadtalha6319
@muhammadtalha6319 2 жыл бұрын
Mene bhi shortest hi parha hai waise.
@shrinishrinivas9605
@shrinishrinivas9605 Жыл бұрын
Tq sir
@danielkim6672
@danielkim6672 Жыл бұрын
Thank u curry mucnh
@Prashant121_
@Prashant121_ Жыл бұрын
*20 April 2023 I didn't understand. My exam is in next week*
@AbhishekTiwari-kv4gq
@AbhishekTiwari-kv4gq Жыл бұрын
Sir what is slack time?
@CivilEngineeringExam
@CivilEngineeringExam Жыл бұрын
difference between the time allocated to the task and the time it actually takes. flexible time for completion of the project
@AbhishekTiwari-kv4gq
@AbhishekTiwari-kv4gq Жыл бұрын
@@CivilEngineeringExam Thanks sir
@n30n2d3
@n30n2d3 3 ай бұрын
A for 🍎 B for 🏀 C for 🐈 D for 🐕 E for 🐘 F for 🐠
@FredzEditz00
@FredzEditz00 3 ай бұрын
Sir its J not I E and J forms H But you said E and I
@sonamtenzin1255
@sonamtenzin1255 5 ай бұрын
your answer is wrong for your information
@KHUSHIMEHRA-c8v
@KHUSHIMEHRA-c8v 9 күн бұрын
Really?
@DhirendraBhujel-b5b
@DhirendraBhujel-b5b Ай бұрын
What is dummy activity
@CivilEngineeringExam
@CivilEngineeringExam Ай бұрын
imaginary activity for close the network
@neharathod3158
@neharathod3158 Жыл бұрын
plz explain proprly. i cant understand
@bibo5649
@bibo5649 Жыл бұрын
Sir activity D you are confusing us
@tonnymakokha
@tonnymakokha Жыл бұрын
I think the last path is supposed to be B-F-J-H and not B-F-I-H, this is because H is not precedent by I but H is preceded by J, please correct that sir.
@tonnymakokha
@tonnymakokha Жыл бұрын
hence the critical path should be 43 and not 34
@140_kenguvabhavesh
@140_kenguvabhavesh Жыл бұрын
yes,thank you@@tonnymakokha
@annonymousperson8508
@annonymousperson8508 Жыл бұрын
Bro BFJ is complete path then why to add H? I guess it's perfect
@kipngenobrian3473
@kipngenobrian3473 10 ай бұрын
You are right
@admanassas1853
@admanassas1853 6 ай бұрын
This is a PERT chart.....
@santhosh9121
@santhosh9121 7 ай бұрын
😉😉😉
@Silverwasp72
@Silverwasp72 5 ай бұрын
B - E - I - J ?
@SanceShaji
@SanceShaji 5 ай бұрын
Not possible since the arrow is NOT from E -> I instead it is from I->E
@Suki4r
@Suki4r 7 ай бұрын
This is the most confusing thing for me
@sangrambarla8587
@sangrambarla8587 6 ай бұрын
Fr
@aryamanutkarsh
@aryamanutkarsh Жыл бұрын
Tch tch soo confused
@omkarkshirsagar3337
@omkarkshirsagar3337 Жыл бұрын
Hechhh (H) 😂👍
@Snorlax_Play
@Snorlax_Play 7 ай бұрын
Hindi mai bolo sir
@robertfulau4194
@robertfulau4194 2 жыл бұрын
.
@ivetymutabazi3514
@ivetymutabazi3514 6 ай бұрын
It's A not Yee 😬😫
@itsarkadey
@itsarkadey 5 ай бұрын
Shut up
@shahneelkhan1442
@shahneelkhan1442 Жыл бұрын
This is wrong
@Rakibul_52
@Rakibul_52 7 ай бұрын
Are you From Bangladesh (Diu)
@anishbista645
@anishbista645 2 жыл бұрын
time waste mumerical.
@rushnainpadiyar6384
@rushnainpadiyar6384 Жыл бұрын
acha
@xyz.1234hdgjtvbhh
@xyz.1234hdgjtvbhh Жыл бұрын
Its H not hech
@umarrashid82
@umarrashid82 2 жыл бұрын
What happened to the slack calculations or float calculations? Arent they necessary to check the criticality and hence find the critical path ?
@CivilEngineeringExam
@CivilEngineeringExam 2 жыл бұрын
i'll continue in next video
@mandalapumanikanta3370
@mandalapumanikanta3370 Жыл бұрын
​@@CivilEngineeringExam brother can you please tell me tution this subject per one hour daily or every three per a week please brother I very trouble to understand this subject
@mandalapumanikanta3370
@mandalapumanikanta3370 Жыл бұрын
Please 🙏🏻 brother
@safetyadvisorspecialist7272
@safetyadvisorspecialist7272 9 ай бұрын
thank you sir.
Noodles Eating Challenge, So Magical! So Much Fun#Funnyfamily #Partygames #Funny
00:33
Don't underestimate anyone
00:47
奇軒Tricking
Рет қаралды 27 МЛН
Thank you Santa
00:13
Nadir Show
Рет қаралды 50 МЛН
Project Management: Finding the Critical Path(s) and Project Duration
4:31
Excel@Analytics - Dr. Canbolat
Рет қаралды 851 М.
Project Scheduling - PERT/CPM | Finding Critical Path
6:57
Joshua Emmanuel
Рет қаралды 1,5 МЛН
How to draw a CPM network diagram
4:15
Engineer4Free
Рет қаралды 921 М.
Noodles Eating Challenge, So Magical! So Much Fun#Funnyfamily #Partygames #Funny
00:33