In the question Task B has a duration of 10 days, while solving the video has a duration of 8 days for Task B. This lead to a miscalculation of NODS effecting the tasks reliant on Task B, on when to start production (other than Task D). This results different slack to the effected NODS/Tasks. Task B and E also have 0 slack, along the videos critical path. Your videos have been helpful though!
@AndrewScarffe18 күн бұрын
You're absolutely right- my mistake! I'll re-record a video with this corrected. A simple oversight there - thank you for flagging!