DFCCIL Is committed for targeted commissioning of the section and till date 500 km stretch are being used by running trains and by March 2020 it will increase to 992 km. timelines of commissioning of the different sections are following:
In this financial year 2020-21 40% i.e. 1100 route Km. will be operationalised.
1. Khurja-Bhaupur - 359 KM.
2. Palanpur-Rewari - 641 Km.
3. Ganjkhawja-Chiralapathu - 100 Km.
Remaining all 1700 route Km. i.e. 60% will be completed by June 2022 .