Fast Works Going on Polavaram Project ll EYE 2 FOCUS

  Рет қаралды 508,256

Suman

Suman

3 жыл бұрын

శరవేగంగా సాగుతున్న పోలవరం ప్రాజెక్టు పనులు
Polavaram status as compared to the five year period from June 2015 to June 2019 (Then) and the 19 months thereafter (Now)
*1)Spill way*:Total spillway blocks 53. Length 1118.4 metres. Foundation level -18.5 to + 10 mtrs. Spill way crest level + 25.72 mtrs. The previous government has completed +34 mtrs level spill way concreting up to June 2019 whereas
Now; the length of spillway being 55 mtrs of which nearly +54 mtrs works are completed as of now.
2) Radial gates Spillway crust level is + 25.72 meters. The total number of gates is 48. The width of the gate is 16 meters and the height is 20 meters. By closing these 48 gates, the reservoir can store 194.60 billion cubic feet of water up to the full level +45.72 meters. To fasten these gates, the spillway pillars must be completed up to a height of +54.00 m. But the spillway pillars were not completed to a height of 54 m (at a height of +34 m) and the iron foil was temporarily fastened like a gate. It was advertised as radial gates installation completed then.
Now; 9 radial gates have already been installed for a total of 48 radial gates. Work on the remaining gates is expected to be completed by April, 2020
3) Spillway Bridge Concrete girders
Each spillway bridge is supported on 4 vertical girders. A total of 48 slabs have 192 vertical girders. The length of each girder is about 21 meters. Out of a total of 192 girders, only 22 girders have been completed in 5 years then.
Now; a total of 170 girders were completed during these 18 months.
4) Spillway Bridge Slabs The Spillway Bridge Slab can be used to lift and lower gates from one side of the spillway to the other and for continuous inspection and monitoring of the gates by officers and staff. Slabs should be constructed on the top of 48 columns. Each slab is approximately 21.5 mtrs long and 9.75 mtrs wide. The thickness is 0.45 mtrs.
Not a single slab of work on these 48 slabs has been started in the last five years then.
Now; construction of 40 slabs completed for a total of 48 slabs. Work is in full swing to complete all the slabs by February 15, 2021.
5) Trianon girders
To install, operate and maintain the 48 gates on the spillway, 49 trianon girders are to be installed on the slope below the 49 pillars water flow. The arm girders of the radial gates are connected to these to operate the gates. The total weight of the gate, which weighs 300 tons, is based on these trianon girders. Trianon girders must be completed to install the dam gates but they are not complete. To tighten the hydraulic cylinders the fulcrums should be fitted at a height of +45.00 m. But it’s not tightened. The level of the pillars should be at least 54.00 meters. None of this has been completed in the past five years, so the work of the Trianon girders has not started then.
Now; 40 girders were completed for a total of 49 trianon girders. All other trianon girders will be completed by the end of January, 2021.
6) Excavation works for foundations of Power House The Polavaram Power Station is designed to generate a total of 960 MW of electricity with 12 units each with a capacity of 80 MW. It is needed to excavate from +135 m to +12 m for the powerhouse. Excavation work from +135 m to +110 m was completed before 2014.
The previous government excavated only 18 meters from +110 meters to +92 meters i.e. excavation work is still to be done at a height of 80 m i.e. from +92 m to +12 m. The Average height of 30 m is completed partially and still 90 meters is to be done.
Now; excavation started at +92 meters and average of 6000 cubic meters per day work is being done. The front of 1 to 6 units is almost complete for a total of 12 units. All excavation work will be completed by March
7) Rehabilitation and Resettlement (R&R) The construction of the Polavaram project has inundated 371 settlements of 222 villages in the East and West Godavari districts. Of these, a total of 1,05,601 displaced families are to be rehabilitated . In the last five years only 1846 houses have been completed in 15 rehabilitation centers. There is also a severe shortage of infrastructure in these rehabilitation centers then.
Now; Construction of 11,500 houses in 47 R&R colonies is almost complete in the last 19 months. The government is taking steps to rehabilitate 17,860 displaced families by May, 2021.
*8) Spill Channel*:Due to the unplanned construction of the Coffer dam, the entire spill channel was filled with flood water and mud due to the floods of 2019. The conditions were such that water and mud had to be removed to do the rest of the work. The spill channel is 2,920 meters long and 1,000 meters wide. This requires the completion of earthworks and the construction of 10 m long and 10 m wide concrete blocks with a thickness of 1 m. Not only works were started, but the major designs were not even approved. The soil on the left and right embankment slopes of the spill channel is

Пікірлер: 162
@sivaroobanvijayakanthan2392
@sivaroobanvijayakanthan2392 3 жыл бұрын
Superb keep going India 🇮🇳
@kmohanbabu8845
@kmohanbabu8845 3 жыл бұрын
జై జవన్ జై కిసాన్ ఇండియా లో జై రైతు అన్న లార జై జగన్ గుండెల్లో ఉన్నరు రైతులు 🙏🙏🙏🙏🙏🙏🙏🙏👍👍👍🌾🌾🌾🌾🌾🌾🇮🇳🇮🇳🇮🇳
@balajinatarajan6189
@balajinatarajan6189 3 жыл бұрын
வாழ்க வளமுடன் நலமுடன் வாழ்த்துக்கள் ஜெகன்மோகன் ரெட்டி ஐய்யா அவர்களே நான் வணங்கும் ஈசன் தங்களுக்கு நீன்ட ஆயுளையும் நோயற்ற வாழ்வினையும் அளிக்கட்டும் ஓம் நமசிவாய நன்றி வணக்கம் 👌 🤝 👏 👍 🙏 💐
@npakiswpa
@npakiswpa 3 жыл бұрын
Great speed
@Ravi-nb2gg
@Ravi-nb2gg 3 жыл бұрын
SUPEREB WORK EXECUTING MEIL, GREAT.
@asamhemanthkumar
@asamhemanthkumar 3 жыл бұрын
Good progress... If govt supports properly this kind of progress is visible.
@srinivasulun7317
@srinivasulun7317 3 жыл бұрын
Jagan super
@venkatasiddaiah3836
@venkatasiddaiah3836 3 жыл бұрын
Veri.veri.good
@thasleemmohd4268
@thasleemmohd4268 3 жыл бұрын
Superb
@VELS436
@VELS436 3 жыл бұрын
Jai hind 🇮🇳❤️good water conservation mega project
@swka2172
@swka2172 3 жыл бұрын
Jai jagun
@SaifAli-ke8mb
@SaifAli-ke8mb 3 жыл бұрын
Very good
@corgraveland4874
@corgraveland4874 3 жыл бұрын
Very nice!
@sowmyakudupudi4639
@sowmyakudupudi4639 3 жыл бұрын
Great cm sir 🙏🙏🙏
@DramaVibes253
@DramaVibes253 3 жыл бұрын
amazing
@krlsarma1933
@krlsarma1933 3 жыл бұрын
Modi great it's a boon to ap people from Modi
@praveensatya9776
@praveensatya9776 3 жыл бұрын
😂
@sanjucreation09
@sanjucreation09 3 жыл бұрын
🤣🤣🤣🤣🤣🤣🤣🤣🤣
@Krish-rm9sr
@Krish-rm9sr 3 жыл бұрын
Funny
@motupdorjee1116
@motupdorjee1116 3 жыл бұрын
I love my india 🇮🇳😍👍
@ramakrishna-zk4gx
@ramakrishna-zk4gx 3 жыл бұрын
Super cbn
@ansetsreenivas
@ansetsreenivas 3 жыл бұрын
జగనా మాజాకాన చెప్పాడంటే...చేస్తాడంటే..ఒకే ఒక మొనగాడు జగన్మోహనుడు...జై వైస్సార్.
@sureshbabuvyas6224
@sureshbabuvyas6224 3 жыл бұрын
హ హ హ హ హ హ హ హ 😂
@sureshbhatt4439
@sureshbhatt4439 3 жыл бұрын
Feel proud.
@local2global
@local2global 3 жыл бұрын
Excellent work by meil
@chandrasekhar-sb7uq
@chandrasekhar-sb7uq 3 жыл бұрын
Good going keep it up
@siddapuramchaithukumar1766
@siddapuramchaithukumar1766 3 жыл бұрын
Radial gate system 😍😍
@theengineer8425
@theengineer8425 3 жыл бұрын
good
@antrixiiven1837
@antrixiiven1837 3 жыл бұрын
I love my 🇮🇳🙏..
@ravikumar-xu7xm
@ravikumar-xu7xm 3 жыл бұрын
Jayam neku Jagananna Jayam neku Jagananna
@sumanrajana5960
@sumanrajana5960 3 жыл бұрын
Nice work sir ,, next video eppudu
@indianguru8773
@indianguru8773 3 жыл бұрын
Should complete it fast before the next rainy season.. 1000's of TMC feet water was wasted this time around and let into the sea...Stop complaining about neighboring states and do what is expected of water which is available to you...
@rajugln3938
@rajugln3938 3 жыл бұрын
good job.. Plz show Cbn gate also
@swka2172
@swka2172 3 жыл бұрын
Graphics
@arifbasha1988
@arifbasha1988 3 жыл бұрын
Oka gate matrame erect chesaru... Pooja cheyyali ga
@venkatarr
@venkatarr 3 жыл бұрын
mogga kudisi poyindi adi😝😝
@kamalmohd8806
@kamalmohd8806 3 жыл бұрын
Thank you Modiji.
@sreenusreenu4647
@sreenusreenu4647 3 жыл бұрын
Jai Jagan Anna
@mikedenz5246
@mikedenz5246 3 жыл бұрын
Oh yeah they are really working fast?
@msreddyreddy1433
@msreddyreddy1433 3 жыл бұрын
Polavaram oka roopu vachhesindi
@nareshb5357
@nareshb5357 3 жыл бұрын
ECRM Dam complete iythene water storage authai
@kalyancivil1372
@kalyancivil1372 3 жыл бұрын
@@nareshb5357 coffer dam complete ayna floods canals ki pampochu
@nareshb5357
@nareshb5357 3 жыл бұрын
@@kalyancivil1372 copper dam complete avabate (cbn) kadha silpway lo water flow vachindhi rain season
@nareshb5357
@nareshb5357 3 жыл бұрын
Manaku kavalisindhi storage apde rayalsema ki benifit
@vanchienpham1664
@vanchienpham1664 3 жыл бұрын
👍👍👍👍👍👍👍
@machireddykesavareddy2727
@machireddykesavareddy2727 3 жыл бұрын
Great sir c m
@sathibabucheekatla4896
@sathibabucheekatla4896 3 жыл бұрын
Good information bro
@spsarmagunturi5343
@spsarmagunturi5343 3 жыл бұрын
KLraju garu polavaram needs chala video s vunnayi. Avi chudandi. Meeku kavalasinanni details vuntayi
@KLRaju-xc7gv
@KLRaju-xc7gv 3 жыл бұрын
Very good information for engineering students but lack of information on m.s.l. why?
@eye2focus
@eye2focus 3 жыл бұрын
*Polavaram status as compared to the five year period from June 2015 to June 2019 (Then) and the 19 months thereafter (Now)* *1)Spill way*:Total spillway blocks 53. Length 1118.4 metres. Foundation level -18.5 to + 10 mtrs. Spill way crest level + 25.72 mtrs. The previous government has completed +34 mtrs level spill way concreting up to June 2019 whereas Now; the length of spillway being 55 mtrs of which nearly +54 mtrs works are completed as of now. *2) Radial gates* Spillway crust level is + 25.72 meters. The total number of gates is 48. The width of the gate is 16 meters and the height is 20 meters. By closing these 48 gates, the reservoir can store 194.60 billion cubic feet of water up to the full level +45.72 meters. To fasten these gates, the spillway pillars must be completed up to a height of +54.00 m. But the spillway pillars were not completed to a height of 54 m (at a height of +34 m) and the iron foil was temporarily fastened like a gate. It was advertised as radial gates installation completed then. Now; 9 radial gates have already been installed for a total of 48 radial gates. Work on the remaining gates is expected to be completed by April, 2020 *3) Spillway Bridge Concrete girders* Each spillway bridge is supported on 4 vertical girders. A total of 48 slabs have 192 vertical girders. The length of each girder is about 21 meters. Out of a total of 192 girders, only 22 girders have been completed in 5 years then. Now; a total of 170 girders were completed during these 18 months. *4) Spillway Bridge Slabs* The Spillway Bridge Slab can be used to lift and lower gates from one side of the spillway to the other and for continuous inspection and monitoring of the gates by officers and staff. Slabs should be constructed on the top of 48 columns. Each slab is approximately 21.5 mtrs long and 9.75 mtrs wide. The thickness is 0.45 mtrs. Not a single slab of work on these 48 slabs has been started in the last five years then. Now; construction of 40 slabs completed for a total of 48 slabs. Work is in full swing to complete all the slabs by February 15, 2021. *5) Trianon girders* To install, operate and maintain the 48 gates on the spillway, 49 trianon girders are to be installed on the slope below the 49 pillars water flow. The arm girders of the radial gates are connected to these to operate the gates. The total weight of the gate, which weighs 300 tons, is based on these trianon girders. Trianon girders must be completed to install the dam gates but they are not complete. To tighten the hydraulic cylinders the fulcrums should be fitted at a height of +45.00 m. But it’s not tightened. The level of the pillars should be at least 54.00 meters. None of this has been completed in the past five years, so the work of the Trianon girders has not started then. Now; 40 girders were completed for a total of 49 trianon girders. All other trianon girders will be completed by the end of January, 2021. *6) Excavation works for foundations of Power House* The Polavaram Power Station is designed to generate a total of 960 MW of electricity with 12 units each with a capacity of 80 MW. It is needed to excavate from +135 m to +12 m for the powerhouse. Excavation work from +135 m to +110 m was completed before 2014. The previous government excavated only 18 meters from +110 meters to +92 meters i.e. excavation work is still to be done at a height of 80 m i.e. from +92 m to +12 m. The Average height of 30 m is completed partially and still 90 meters is to be done. Now; excavation started at +92 meters and average of 6000 cubic meters per day work is being done. The front of 1 to 6 units is almost complete for a total of 12 units. All excavation work will be completed by March *7) Rehabilitation and Resettlement (R&R)* The construction of the Polavaram project has inundated 371 settlements of 222 villages in the East and West Godavari districts. Of these, a total of 1,05,601 displaced families are to be rehabilitated . In the last five years only 1846 houses have been completed in 15 rehabilitation centers. There is also a severe shortage of infrastructure in these rehabilitation centers then. Now; Construction of 11,500 houses in 47 R&R colonies is almost complete in the last 19 months. The government is taking steps to rehabilitate 17,860 displaced families by May, 2021. *8) Spill Channel*:Due to the unplanned construction of the Coffer dam, the entire spill channel was filled with flood water and mud due to the floods of 2019. The conditions were such that water and mud had to be removed to do the rest of the work. The spill channel is 2,920 meters long and 1,000 meters wide. This requires the completion of earthworks and the construction of 10 m long and 10 m wide concrete blocks with a thickness of 1 m. Not only works were started, but the major designs were not even approved. The soil on the left and right embankment slopes of the spill channel is slippery. Key designs for embankment slopes were not approved. Whereas Now, About 1 TMC of water had to be pumped from the spill channel to start work after the floods. It took from November to February to complete the pumping of water. Then work began but due to the Covid-19 lockdown work had to be done very sparingly from March to June. Again in July 2020, floodwaters receded from the spill channel, disrupting the work of the spill channel. Floodwaters have been pumping into the spill channel since October. It will be completed this week. The concrete block is being laid while removing the mud and silt. All these works will be completed by the end of April this year. Major designs are all approved and steps have been taken to complete it by the end of April. *9) Coffer Dam* In order to build the Earth cum Rockfill Dam uninterruptedly, upper and lower cofferdams must be constructed to prevent incoming floodwaters. If the upper and lower cofferdams are not built, it will be impossible build the main dam as water will reach to it. The upper Coffer Dam is 2,340 meters long and is to be built up to a level of 42.50 meters. Only 1200 m long, +28.00 m to + 33.00 m high in the middle of the Godavari has been partially completed in the last five years. The lower Coffer Dam is 1617 meters long and is to be built up to a level of 30.50 meters. It was partially built over a length of 950 meters. The important jet grouting, and linking of D wall, crucial permeation grouting works of Upper Cofferdam were not done and works of Upper Coffer Dam are stalled at various stages. Floodwaters and silt accumulated in the spill channel due to the diversion of flood water through the spillway and spill channel. This caused the project work to be delayed by two years. Whereas, Now; the upper and lower cofferdam works are in progress as planned and the work is scheduled to be completed by June, 2021 *10) Gap-III Concrete dam* The length of the concrete dam is 153.50 meters, the width above is 8.5 meters and the average height is 22.32 meters, and the entire Gap-III dam consists of 9 blocks. In the last five years, during the previous government, the dam designs were not submitted and not even a single task was started. However, in the current government, the designs were sent and were approved by the Central Water Energy Council and the work has also begun. So far, the foundation works in 12000 cubic meters were completed, while a total of 16000 cubic meters of concrete work is under process and estimated to be completed by April 2021. *11)Gap-I clay and stone construction* The length of Gap-I Earth-cum-Rockfill Dam is 564 meters, the width above is 12.5 meters and the average height is 29.32 meters. Similarly, the length of the diaphragm wall is 388 meters and has a total of 84 panels. The previous government had not submitted any designs of Gap-I Earth-cum-Rockfill Dam and work has not begun. In the current government, the designs have been approved by the Central Hydropower Board and the foundation works in two rigs are going at a fast pace. All other works are expected to be completed by June 2021. *12) Works on tunnel to supply water to right and left canals* During the previous government term work on left canal did not start. The twin tunnel lining work was not done on the right side. Whereas during the 19 months there was much progress. To provide water to the left canal 919 mtrs long tunnel with 18 mtr diameter should be built. About3.65 cubic mtrs stone should be dug of which 1.75 lkah cubic mtrs work is completed. The remaining work including lining is planned to be completed by December 2021. The right side twin tunnel should be dug, designs are done and the work is planned to be completed by December 2021.
@rakeshyalla3290
@rakeshyalla3290 3 жыл бұрын
@@eye2focus I think he didn't mean to provide Wikipedia information he means to provide some audio behind
@hammettchemistry2914
@hammettchemistry2914 3 жыл бұрын
Super jagan... Polavaram strt chesindi ysr.. Complete chesedi aayana bidda..
@konchadarakesh8134
@konchadarakesh8134 3 жыл бұрын
Ala anukodame
@sureshbabuvyas6224
@sureshbabuvyas6224 3 жыл бұрын
చంద్రబాబు కదా 🤔
@Krish-rm9sr
@Krish-rm9sr 3 жыл бұрын
History telusukondi ysr kadhu start chesindhi. cbn time lo ekuva work jargindhi kavalante google chesukondi.
@corneliuskaalla1744
@corneliuskaalla1744 3 жыл бұрын
Polavaram Project credit goes to Swargeeya Dr. YSR garu.
@naveenkumarswamireddy1441
@naveenkumarswamireddy1441 3 жыл бұрын
Yes absolutely.
@sureshbabuvyas6224
@sureshbabuvyas6224 3 жыл бұрын
🤔
@user-xm2qh3wg2u
@user-xm2qh3wg2u 3 жыл бұрын
ให้งบประมาณ​ไปทำลาย
@manjunathsg472
@manjunathsg472 3 жыл бұрын
Awesome 👏
@pradippurohit224
@pradippurohit224 3 жыл бұрын
Great🙏
@user-xm2qh3wg2u
@user-xm2qh3wg2u 3 жыл бұрын
สนิมจับแล้ว
@user-xm2qh3wg2u
@user-xm2qh3wg2u 3 жыл бұрын
ดาดฟ้า
@user-xm2qh3wg2u
@user-xm2qh3wg2u 3 жыл бұрын
เป็น10ปีแล้ว
@KLRaju-xc7gv
@KLRaju-xc7gv 3 жыл бұрын
Mention M.S.L at bottom of iron gate,for students
@balajiaalla2235
@balajiaalla2235 3 жыл бұрын
Super 👌
@sowmyakudupudi4639
@sowmyakudupudi4639 3 жыл бұрын
Great cm sir
@nagarajujetty7415
@nagarajujetty7415 3 жыл бұрын
Johar Ysr Jai Jagan Anna Long live jagan anna gournament
@jaykaklotar4453
@jaykaklotar4453 3 жыл бұрын
No audio that is why we don't know from where it is. You should mention state.
@prudhvirajdivi8350
@prudhvirajdivi8350 3 жыл бұрын
Andhra Pradesh
@rangarao27
@rangarao27 3 жыл бұрын
POLAVARAM YSR swapnam. complete chestadu JAGAN
@lpattabhiraman1041
@lpattabhiraman1041 3 жыл бұрын
But CBN fought with centre to get it off the ground
@spm2508
@spm2508 3 жыл бұрын
This is central govt project .....not CM....of Andra
@achyuthmadhavapeddi2703
@achyuthmadhavapeddi2703 3 жыл бұрын
Jai cbn jai devineni uma jai tdp jai lokesh
@user-xm2qh3wg2u
@user-xm2qh3wg2u 3 жыл бұрын
ลายขนำสะพาน2
@user-xm2qh3wg2u
@user-xm2qh3wg2u 3 жыл бұрын
ลึกกว่านั้น
@Nishtha1508
@Nishtha1508 3 жыл бұрын
(SANY)Chinese heavy vehicles are used for many of the constructions/ mega projects,can't our Indian vehicle manufacturers build this type of machines for infra projects.
@surajprakash3181
@surajprakash3181 3 жыл бұрын
Unfortunately, heavy machinery is not a child's play. It doesn't come as easily as words out of the keyboard. Plus, I think Sany, even though, Chinese company, has its own plant in India so probably these heavy machines are manufactured in India. Probably. Good for you, l&t, BEML and ACE are some Indian heavy machine manufacturers.
@Sammy58328
@Sammy58328 3 жыл бұрын
We have Tata-Hitachi (again Hitachi is not Indian but the JV formed in 60s)
@VELS436
@VELS436 3 жыл бұрын
Tata Hitachi can be used as alternative in upcoming projects..
@konchadarakesh8134
@konchadarakesh8134 3 жыл бұрын
CBN rocked..
@vijaykittu6017
@vijaykittu6017 3 жыл бұрын
ఎస్కో నా రాజా.. జయము జయము సెంద్రన్న
@KNKR1234
@KNKR1234 3 жыл бұрын
జయము జయము సెంద్రన్న, బొల్లిగాడు కమీషన్లు దొబ్బేయటం తప్ప, పనేమీ చెయ్యలేదు. వాడికి రాదు కూడా.
@user-xm2qh3wg2u
@user-xm2qh3wg2u 3 жыл бұрын
มีกล้องอยู่
@varaprasadg5571
@varaprasadg5571 3 жыл бұрын
చంద్రబాబు నాయుడు గారి కష్టం రాబందుల పాలు
@KLRaju-xc7gv
@KLRaju-xc7gv 3 жыл бұрын
Sir good video very beautiful,please mention m.s.l.of dam to understand,for engineering students.
@aakhilbeig6552
@aakhilbeig6552 3 жыл бұрын
M.s.l means ?
@KLRaju-xc7gv
@KLRaju-xc7gv 3 жыл бұрын
@@aakhilbeig6552 Mean Sea Level.
@aakhilbeig6552
@aakhilbeig6552 3 жыл бұрын
@@KLRaju-xc7gv thank you
@purnnachandraraokantamneni7591
@purnnachandraraokantamneni7591 3 жыл бұрын
ఇంతటి వర్క్ రాయపాటి చేయగలిగే వాడా. ఎన్ని ఏళ్ళు పట్టేది. జగన్ పోలవరం పూర్తి చేసి ఎన్నికలకు పోతే పక్క పార్టీల పరిస్థితి ఏమిటా ఆలోచిస్తే వారికి అభ్యర్థులు దొరకునా.
@angaraprasad4910
@angaraprasad4910 3 жыл бұрын
rod canatviti ditals plesesar
@sampathavvari5427
@sampathavvari5427 3 жыл бұрын
రాజమండ్రీ నుంచి పోలవరం ప్రాజెక్టు
@babiumno6646
@babiumno6646 3 жыл бұрын
Biggest threat to this project is corruptions! Good luck India.
@farhadkpk430
@farhadkpk430 3 жыл бұрын
Canstruction video channel Farhad kpk
@NguyenNguyen-eo5hx
@NguyenNguyen-eo5hx 3 жыл бұрын
Cantho vietnam
@user-xm2qh3wg2u
@user-xm2qh3wg2u 3 жыл бұрын
ติดกล้องไว้ทั่วป่า
@local2global
@local2global 3 жыл бұрын
Daily enni gates amarchutunnaru
@vijaykittu6017
@vijaykittu6017 3 жыл бұрын
3 days ki one gate fix chestunaru inka gates ki holes lekunda welding cheyadaniki neat ga undo ledho check cheyadaniki 8 to 10 days padutundi
@Saikumar-mh7dg
@Saikumar-mh7dg 3 жыл бұрын
Jai cbn great visionary leader
@SaifAli-ke8mb
@SaifAli-ke8mb 3 жыл бұрын
Block namber 21 22 23 24 25 26 27 28 29 30 kaam kiya the
@manohar910
@manohar910 3 жыл бұрын
ఎందరో కలలు కన్నా పోలవరం, ఎవ్వరి వల్ల కాలేదు one and only వైస్ జగన్మోహన్ రెడ్డి గారు గ్రేట్ సీఎం జై జగన్
@sureshbabuvyas6224
@sureshbabuvyas6224 3 жыл бұрын
గుడ్ జోక్
@manohar910
@manohar910 3 жыл бұрын
@@sureshbabuvyas6224 జోక్ హ??? ఇందులో జోక్ ఏముంది చెప్పు
@sureshbabuvyas6224
@sureshbabuvyas6224 3 жыл бұрын
@@manohar910 చేసింది ఒకరు చెప్పుకునేది ఒకరు, లోకం తీరే అంత ఏమి చేయలేం.
@manohar910
@manohar910 3 жыл бұрын
@@sureshbabuvyas6224 ఎవరు చేశారు??? ఎవరు చెప్పుకుంటున్నారు నాకు కొంచం క్లారిటీ ఇస్తారా??
@sureshbabuvyas6224
@sureshbabuvyas6224 3 жыл бұрын
@@manohar910 చంద్రబాబు 80% చేసాడు, మిగతా ఇప్పుడు చేస్తున్నారు. నిజాలు చెప్పండి బ్రో.
@SaifAli-ke8mb
@SaifAli-ke8mb 3 жыл бұрын
Bhai is me kaam kiya the
@saibabumoka2983
@saibabumoka2983 3 жыл бұрын
M
@hanumantharaomanukonda9048
@hanumantharaomanukonda9048 3 жыл бұрын
Jai cbn polavaram ku oka shape thisukochhina okka magadu
@trendsetter8725
@trendsetter8725 3 жыл бұрын
Ongoniii moggaleyyiii ra pakodii... vaadu undi unte inko 5 yrs ayyina avvakapoyenuuu...endhuju ra bathukutharu... patcha buffons
@KNKR1234
@KNKR1234 3 жыл бұрын
వాడి బొంద, బొల్లిగాడు పది జన్మలెత్తినా 3D సినిమాలు చూపించాల్సిందే గానీ, వాడికి కమీషన్లు తప్ప ఇంకేం రాదు.
@CHannel-ip5ry
@CHannel-ip5ry 3 жыл бұрын
ไท่ถึง10ปีแตก
@SaifAli-ke8mb
@SaifAli-ke8mb 3 жыл бұрын
Megha campany hai
@hariprasad8261
@hariprasad8261 3 жыл бұрын
Kikikikikikikikikikikiki
@Mrsubramanyamtube
@Mrsubramanyamtube 3 жыл бұрын
We want KRMB in Kurnool
@boyamoulali9554
@boyamoulali9554 3 жыл бұрын
AP.. CM💪💪🐆🐆👈
@spm2508
@spm2508 3 жыл бұрын
This is central govt project .....not CM....of Andra
@aaalanurpatel5263
@aaalanurpatel5263 3 жыл бұрын
कहां कहां का है
@balwantyadav1238
@balwantyadav1238 3 жыл бұрын
Andhra
@prasadtommandru1107
@prasadtommandru1107 3 жыл бұрын
Polavaram Andhra ki varam Jagan Mohan matrame dheenini complete cheyagalaru jai Jagan johar YSR🙏🙏🙏
@sureshbabuvyas6224
@sureshbabuvyas6224 3 жыл бұрын
అవునా నిజంగా 🤔
@balajigauribalajigauri8341
@balajigauribalajigauri8341 3 жыл бұрын
అవును చూడు
@sureshbabuvyas6224
@sureshbabuvyas6224 3 жыл бұрын
@@balajigauribalajigauri8341 ఎవరు దానికి కారణం చెబుతారా.
@balajigauribalajigauri8341
@balajigauribalajigauri8341 3 жыл бұрын
@@sureshbabuvyas6224 మీరు చెప్పండి సోదరా నాకు తెలీదు
@sureshbabuvyas6224
@sureshbabuvyas6224 3 жыл бұрын
@@balajigauribalajigauri8341 చంద్రబాబు బ్రో
@venkatasiddaiah3836
@venkatasiddaiah3836 3 жыл бұрын
Jai.jagan
@maradanajnaidu647
@maradanajnaidu647 3 жыл бұрын
Chandrababu strategy, vision.
@vijaykittu6017
@vijaykittu6017 3 жыл бұрын
ఎస్కో నా రాజా.. జయము జయము సెంద్రన్న when cbn leave the project in 2019 porject height is just 20mts now the height is 52mts and completed bridge work and gate fitting is also under process complete credit goes to ysr family and megha company though i am a fan of cbn we must know the truth bro . even PM said polavaram is just like ATM TO CBN .so ,cbn just only managed with media not done anything
@KNKR1234
@KNKR1234 3 жыл бұрын
వాడి బొంద.
@sureshbabuvyas6224
@sureshbabuvyas6224 3 жыл бұрын
చంద్రబాబు పూర్తి చేసాడు దానికి గేట్స్ అమరుస్తున్నారు అంతే, జగన్ చేసేదేమిలేదు
@vijaykittu6017
@vijaykittu6017 3 жыл бұрын
kzbin.info/www/bejne/nn-QpWtrhtBqhc2cttps://kzbin.info/www/bejne/nn-QpWtrhtBqhc0
@sureshbabuvyas6224
@sureshbabuvyas6224 3 жыл бұрын
@@vijaykittu6017 ఫేక్ సంవత్సరం,2018 లో వీడియో అది
@balajibabu5671
@balajibabu5671 3 жыл бұрын
polavaram 72% complete chesindi okadu.. last lo gates petti credits dobeedi okadu..!! goreelu vacha gun gun ani bhajana
@kumarchowdary2106
@kumarchowdary2106 3 жыл бұрын
2019 end lo entha work cmplt aiyindo chusukora yellow 🐕......bolli babu unte inko 5 years aina cmplt avadhu....
@balajibabu5671
@balajibabu5671 3 жыл бұрын
@@kumarchowdary2106 me vallu official ga report echaru polavaram 68% complete ayindi ani.. nuv chuskora paytm 🐕. migilina 32% ki 2 years ayina complete avvala.. enka sagam gates kuda fit cheyaledu... oo bhajana
@mudapakalakshmiviswanadhac6805
@mudapakalakshmiviswanadhac6805 3 жыл бұрын
@@balajibabu5671 basement to the project is very very critical and it's engineering wonder that has been completed since five years ago. Upper portion of the spill way are errection of gates are so easy. Easy work also not completed these long period. Even though constructed completely until completion of R&R the water may not be stored completely. Then the purpose of construction of the project will not surve
@iamlion6673
@iamlion6673 3 жыл бұрын
Jai jagan
@madhusudhan719
@madhusudhan719 3 жыл бұрын
Jai Jagan Mohan Reddy
@pampanaedukondalu2743
@pampanaedukondalu2743 3 жыл бұрын
Cbn ku nedhrapattadhu
@afrozaffu5835
@afrozaffu5835 3 жыл бұрын
Rawali jagan kawali jagan
@hariprasad8261
@hariprasad8261 3 жыл бұрын
Jail jagan
@pampanaedukondalu2743
@pampanaedukondalu2743 3 жыл бұрын
Balisinnara neku.
@tangellavenkatesu7605
@tangellavenkatesu7605 3 жыл бұрын
జగన్ మోహన్ రెడ్డి గారి కష్టం తరతరాలకు మేలు.
Я обещал подарить ему самокат!
01:00
Vlad Samokatchik
Рет қаралды 9 МЛН
Spot The Fake Animal For $10,000
00:40
MrBeast
Рет қаралды 195 МЛН
Know about Polavaram in 3 minutes - Life Line of Andhra Pradesh
2:56
Megha Engineering and Infrastructures Ltd
Рет қаралды 327 М.
Polavaram Spillway Gates Discharge flood Water
4:32
GOPI PRASAD POLAVARAM PROJECT
Рет қаралды 501 М.
Radial Gate Hydraulic Cylinder Installation
8:15
JRAIN
Рет қаралды 20 М.
పోల‌వ‌రం టు ధ‌వ‌ళేశ్వ‌రం | MEIL
5:29
Megha Engineering and Infrastructures Ltd
Рет қаралды 137 М.
Polavaram Dam Project Latest video Updates
2:27
Dovinte vlog
Рет қаралды 424 М.
Polavaram Design Explained II Thulasi Chandu Clips
14:25
TC Clips
Рет қаралды 330 М.
Polavaram  dam
13:51
Ramarao Ramarao
Рет қаралды 386 М.
Polavaram Project : ECRF Dam Ongoing Works | #shorts
0:31
Megha Engineering and Infrastructures Ltd
Рет қаралды 51 М.
ЖЕСТКИЙ ШАПАЛАК👋
0:33
RFC Fighting Championship
Рет қаралды 201 М.
ЖЕСТКИЙ ШАПАЛАК👋
0:33
RFC Fighting Championship
Рет қаралды 201 М.
这是王子儿子吗
0:27
落魄的王子
Рет қаралды 20 МЛН
Waka Waka 💦💃😁 #funnyshorts #rianashow
0:14
RianaShow
Рет қаралды 19 МЛН