Was rebar required and placed in the footer ? About how many inches of the form are exposed and need to be flashed on the exterior ?
@JimSperanza7 күн бұрын
Rebar was placed into the footer. I typically use a 6 inch steel flashing then backfill to keep about 4 inches exposed which gives a nice clean look.
@qualitybydesign51197 күн бұрын
Thanks for the quick response ! Are you a general contractor/builder ? Your quite knowledgeable about all facets of your build .
@JimSperanza7 күн бұрын
@qualitybydesign5119 yes Speranza Development LLC. I offer designs and consulting services for residential builds.
@joebardo12255 ай бұрын
DID YOU INSTALL FOOTER DRAINS? AND WHAT ARE YOU DOING WITH RAIN SPOUTS?
@JimSperanza5 ай бұрын
No footer drains and the foundation and footer are raised up about 2 feet from the surrounding grade. Rain spouts will be ran into 4 inch piping and into the nearby drainage ditch.
@cdee24567 ай бұрын
I would build a castle on a well tamped bed of crusher
@JimSperanza7 ай бұрын
About 8 inches of CR1 and rake out 2 inches of washed 1 inch and she's perfecto!
@steventhury83667 ай бұрын
I'm a lone worker myself. For me, other people around disrupts my concentration. Of course, no one knows everything, so I get my human input from KZbin. I can start, take breaks, quit, at my own convenience which I like the most. Having things like skidloaders and laser levels make it possible.