Project : High Speed Rail Thailand on Bangkok to Nakhonratchasima
Contract No.3-4 Si Khio Section
Contractor : ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY
Duration Contract : 1,080 Days (36 Months)
Start Project : February 2021
Finish Project : January 2024
Progress as of October 2021
Accumulative Plan : 5.10%
Accumulative Actual : 8.74%
Ahead : +3.64% 👍👍