Hi , I have a resource cost loaded p6 plan , when I update the schedule, in this case percent complete type is duration, all relevant field like duration , unit , activity percent complete reflacte the amount , but performance percent complete is still zero. Would you please advise how to resolve this issue. I've checked all setting I thought might affected the result. Regards and thank you.
@SoftEdemy8 ай бұрын
Baseline assigned and not cost loaded. Check on top is their any planned value cost and earned value cost.
@mahansor82958 ай бұрын
Thanks. I've slready created a baseline from the current project which is resource loaded .
@mahansor82958 ай бұрын
Planned value cost has value , but earned value cost is zero
@SoftEdemy8 ай бұрын
@@mahansor8295 check why their is no earned value.
@SoftEdemy8 ай бұрын
@mahansor8295 check when you update your activity does your resource changes.