How to set WIP limit in kanban, I mean what all factors need to consider as a scrum master
@izenbridge3 жыл бұрын
Some factors need consideration are, team capacity , type of work (if work items are small or large) , % of people loaded , lead time expectations
@vaikadam Жыл бұрын
fantastic
@izenbridge Жыл бұрын
Thank you so much 😀
@ParminderSingh-ee3ps5 жыл бұрын
How Kanban Teams handle velocity in SAFe during PI Planning?
@izenbridge5 жыл бұрын
Thank you!! Parminder for exploring and liking our content. You can also explore the following video on SAFe Version 4: Introduction: kzbin.info/www/bejne/jWHIoqqLipZoe8k&lc=UgxsI7HxiGQxmHtOlS54AaABAg
@SaketBansal5 жыл бұрын
Hi, Thank you exploring our video. The Kanban team can use throughput information for forecasting the work they can do in given PI. I see kanban team is becoming more popular nowadays in ART.