Do we need to do UAT within sprint?If so i think stakeholders can tell that as an excuse to avoid sprint review as they will have done stories in UAT.. We do Sprint review on 8th day of every Sprint in staging before ut gets deployed to Prod.is this correct
@izenbridge6 ай бұрын
It depend on your Definition of Done, yes it is good if you can include all it takes to make story available to customer as DoD, but in some cases where client may want to review collection of work in one go, you create DoD without UAT and than run special duration for doing this pending work, doing it later has risk since it can generate rework. so we need to find what is needed in our project.