if in an Agile Project a customer makes a request for addition of a new feature in the last sprint of the release, that is nearing completion, then should the Scrum master ask the project manager to consider the request (considering Agile embraces changes) or should the scrum master assess the impact on sprints deadline along with the team members first?
@BABLOCKS
@BABLOCKS 2 жыл бұрын
If you're lucky enough to have a project manager and a scrum master on the same project then you should notify the PM right away and ask them for direction. The PM is accountable for cost/schedule and may not have the budget for any additional work. I hope that helps.
@olaomishore
@olaomishore 3 жыл бұрын
Hello, do you actually teach the BA class? How do we register if interested? Price and course curriculum and duration? Thanks
@BABLOCKS
@BABLOCKS 3 жыл бұрын
Hi, you can see a list of our courses here: bablocks.com/courses/ The course schedule is published inside our community. You can join here if you haven't already done so: bablocks.com/membership/
@siblingworldtv1946
@siblingworldtv1946 2 жыл бұрын
Isn't a change request simply a new User Story that can be added to the backlog and prioritised (just like another User Story)? The Story that was accepted must go ahead and delivered as per the normal way .. that's how I could address this situation
@BABLOCKS
@BABLOCKS 2 жыл бұрын
It can be. This video addresses the more extreme situation where the customer is demanding a change to a feature/function that is mid-build. It can be very common on some projects the receive these types of requests and the developers are the ones who should be making the yes/no decision.
@YamzyzStyle
@YamzyzStyle 4 жыл бұрын
This is very helpful. Thank you
@BABLOCKS
@BABLOCKS 3 жыл бұрын
You're very welcome.
@xldworld
@xldworld 3 жыл бұрын
very helpful
@SurajP16
@SurajP16 3 жыл бұрын
This video doesn't help, I am sorry.
@BABLOCKS
@BABLOCKS 3 жыл бұрын
Hi Suraj, Do you have any follow-up questions that you'd like answered to help you understand this more clearly?
@SurajP16
@SurajP16 3 жыл бұрын
@@BABLOCKS "how do you handle change requests in agile projects?" I had that question on my mind when I clicked on the video...
@BABLOCKS
@BABLOCKS 3 жыл бұрын
1. Check with the dev team to see if they can absorb the change request into their sprint for the next release. 2. If so, then let your customers know that the change can be accepted. 3. If not, tell your customers that the change cannot be accepted into the current release. Does that clear things up?
Business Analyst vs. Product Owner in Agile
12:49
BA BLOCKS
Рет қаралды 17 М.
Человек паук уже не тот
00:32
Miracle
Рет қаралды 4,2 МЛН
PRANK😂 rate Mark’s kick 1-10 🤕
00:14
Diana Belitskay
Рет қаралды 11 МЛН
СОБАКА ВЕРНУЛА ТАБАЛАПКИ😱#shorts
00:25
INNA SERG
Рет қаралды 3,8 МЛН
Requirements & Specification Essentials for Business Analysts
48:34
Agile planning techniques made simple
29:39
APMG International
Рет қаралды 441
Requirement Workshop Elicitation Technique: Everything You Need to Know
7:24
Business Analyst Academy - Komal Agarwal
Рет қаралды 374
Estimate Software Development Costs
14:02
AltexSoft
Рет қаралды 19 М.
Agile Portfolio Management
1:16:39
LeadingAgile
Рет қаралды 18 М.
Sprint Planning Meetings | 12 Tips To Run Them Like a Scrum Pro
9:12
The Digital Project Manager
Рет қаралды 6 М.
How to handle the urgent change request in Sprint? | Skill Transform
19:04