Resource Loading in Primavera P6 - 5 Tips to make it EASIER

  Рет қаралды 34,718

Plan Academy Inc.

Plan Academy Inc.

Күн бұрын

Пікірлер: 29
@PlanAcademy
@PlanAcademy Жыл бұрын
Want to learn more about resource loading? Check out our on-demand courses and free preview videos here: www.planacademy.com/
@haroldheckel1656
@haroldheckel1656 Жыл бұрын
¹+
@jeferrysimyy8818
@jeferrysimyy8818 12 күн бұрын
Very good. Tq for knowledge sharing.
@davidalfonsokrobothpalmer4604
@davidalfonsokrobothpalmer4604 Жыл бұрын
Thank you Michael!
@doddabelerangaswamybalakri7756
@doddabelerangaswamybalakri7756 Жыл бұрын
Thanks Michael ! you give simple , effective tips. Hat's off to you. Appreciate it.
@PlanAcademy
@PlanAcademy Жыл бұрын
Thanks very much. Glad we could help!
@rubenaugustine8666
@rubenaugustine8666 Жыл бұрын
Thank you for this interesting video. I continue using individual resources and I would like to learn what it is the big difference you get using crews instead.
@rolanhdc
@rolanhdc Жыл бұрын
Superb
@PlanAcademy
@PlanAcademy Жыл бұрын
Thanks! Glad you liked it!
@mahsatabesh1055
@mahsatabesh1055 Жыл бұрын
Hello Michael, thank you for the great contents you share! I have a question: Is there any code to be used commonly in both activity and wbs level?
@paulinefonseca1007
@paulinefonseca1007 2 ай бұрын
So good and trustworthy material on this channel. Well done! I do have one question, my default units / time on resource only shows as 1.00d/d and not the h/d. I have tried everything to fix this and nothing seems to work. I would love some help on this. 🙏
@PlanAcademy
@PlanAcademy 2 ай бұрын
Go to Edit -> User Preferences -> Time Units -> Change Unit of Time to Hour, once you do that, refresh P6, and you will be able to see the default units in Hrs/d
@mohandoss3581
@mohandoss3581 Жыл бұрын
Thank you for your valid information :)
@PlanAcademy
@PlanAcademy Жыл бұрын
You're welcome, Mohan. Thank you.
@amiebatchelor1594
@amiebatchelor1594 8 ай бұрын
Thanks this was a great video..always find buttons Ive not used with your videos
@PlanAcademy
@PlanAcademy 7 ай бұрын
Glad to help
@SRRepublican
@SRRepublican Ай бұрын
Thank you for your efforts in this regard, but i have can i copy global calendar
@AhmedAli-dj9jo
@AhmedAli-dj9jo Жыл бұрын
Thank you
@PlanAcademy
@PlanAcademy Жыл бұрын
You're welcome, Ahmed. Glad you found it helpful.
@tinaenowenow9537
@tinaenowenow9537 Жыл бұрын
Nice one!
@MrLivekp
@MrLivekp Жыл бұрын
Thanks
@jasonfuqua4284
@jasonfuqua4284 Жыл бұрын
When I open assign resources and click display all, I have no resources to choose from. Can I download them into P6?
@HassanAhmed-nc7kc
@HassanAhmed-nc7kc 3 ай бұрын
❤️🌹👍 thank you
@omarhebatalla8626
@omarhebatalla8626 5 ай бұрын
coul you provide a safe link to download primavera 6 . and let me please know if you have a video to how to setup primavera p6
@jousalek7507
@jousalek7507 Жыл бұрын
How about loading of indirect and Direct Manpower in Primavera? Is it necessary to add the indirect Manpower loading? If needed, how to handle our indirect overhead Manpower in resources loading and cost loading.? Please help me!
@PlanAcademy
@PlanAcademy Жыл бұрын
Indirect manpower hours can be captured on special activities - Level of Effort (www.planacademy.com/level-of-effort-faq/) or WBS Summaries. These activities are not work activities, but still span large sections of the project and you can assign your resources to them - explained here -> www.planacademy.com/high-level-resourcing/
@zanashtv5479
@zanashtv5479 Жыл бұрын
I am here to learn P6....everything I need to know
@PlanAcademy
@PlanAcademy Жыл бұрын
You've come to the right place. Check out our other videos on this channel for lots of tutorials, tips and info. And of course, you can find full professional courses on our website.
@FranzMacalua
@FranzMacalua Жыл бұрын
Thank you Michael !
Manpower Resource Loading including S-curve in Primavera P6
13:30
Are YOU Using this Primavera P6 Float Paths Feature?
10:06
Plan Academy Inc.
Рет қаралды 18 М.
The evil clown plays a prank on the angel
00:39
超人夫妇
Рет қаралды 50 МЛН
99.9% IMPOSSIBLE
00:24
STORROR
Рет қаралды 29 МЛН
If people acted like cats 🙀😹 LeoNata family #shorts
00:22
LeoNata Family
Рет қаралды 45 МЛН
黑天使被操控了#short #angel #clown
00:40
Super Beauty team
Рет қаралды 59 МЛН
Why Half-Step Progressing is so Important!
6:55
Plan Academy Inc.
Рет қаралды 3,5 М.
How to add B O Q Qty and unit rate separately in Primavera P6
2:57
Technical Trainings For Free
Рет қаралды 3,6 М.
How To Use Resources in Primavera P6
7:09
Ten Six
Рет қаралды 10 М.
15 | How to Do Resource Loading in Primavera P6
8:58
Planning Engineer FZE.
Рет қаралды 1,9 М.
Make This Awesome Gantt Chart in Excel (for Project Management)
17:13
Kenji Explains
Рет қаралды 453 М.
How to Cost Load a Schedule in Primavera P6
9:57
PJM Scheduling Services
Рет қаралды 22 М.
Primavera P6: How to make S Curves in Primavera P6
19:07
Zero Float
Рет қаралды 216 М.
What P6 Schedule Comparison Tool Should You Use?
26:52
Plan Academy Inc.
Рет қаралды 10 М.
How To Bulk Upload Resources Data to Primavera P6 Using Excel
6:53
The evil clown plays a prank on the angel
00:39
超人夫妇
Рет қаралды 50 МЛН