Question 55, Option D - RMP and SMP could be Resource Mangement Plan and Scope Management Plan respectively.
@massimokim15 күн бұрын
Thank you, David!
@raimom0829 күн бұрын
This set has really helped! Thx!
@michealoshos47692 ай бұрын
RMP - Risk Management Plan, SMP - Schedule management Plan
@monairan24294 ай бұрын
Are there procurement and quality process in the PMP exam?
@SwadeshiKitchen4 ай бұрын
The Risk Management Professional (PMI-RMP) and Schedule Management Plan (SMP) are both related to project management, but they serve different purposes
@41greene2 ай бұрын
On question 51, what is meant by “project process”?
@danielpion93444 ай бұрын
On question 56, since the question said that the item is "not complex and readily available", I thought we could jump right to an RFQ. The way I read it, the project team knows what they want, and where they can get it, which is what is required for an RFQ. Is that part of the question misleading, or am I misunderstanding it?
@BLOCKCHAINframework3 ай бұрын
I agree with your assessment. RFI is more appropriate when what the market has to offer is unclear. I picked answer D
@41greene2 ай бұрын
I think the key here is in the definition of what PMBoK 7 states as RFI is. It says “is used to gather more information from the market PRIOR TO SENDING OUT BID DOCUMENTS to a set of selected vendors.” I think that is the key difference here. But I was kind of on the fence and thinking it might have been D as wrll