@SirGanttalot : Thanks a million for the videos. I am appearing for the CAPM exam next month. The videos are extremely useful and it is free. WOW! If I were is UK I would have certainly signed up for a formal training with WestMurray.
@bidyut10114 жыл бұрын
@SirGanttalot : Thanks a million for the videos. I am appearing for the CAPM exam next month. The videos are extremely useful and it is free. WOW!
@tonytrinh83479 жыл бұрын
Just wanted to say THANK YOU! You've help a lot in my preparation for my PM exam. Very detailed and professional speaker.
@santoshkmhatre9 жыл бұрын
Undoubtedly the best PMP videos I have come across on KZbin. I was struggling with EVM, CPM and watching these videos made those concepts engraved in my mind now. Much appreciated !!
@Ashley1978ism11 жыл бұрын
Thanks a lot for the two part tutorial. My tutor spend weeks trying to get us to understand this using a much more complicated method. Less than 20 min with you and I now get it. Awsome stuff.
@guyrogers345615 жыл бұрын
Sir Gantalott, you are the BEST, Great job. Keep it up.
@SirGanttalot14 жыл бұрын
Yes that's right. You can look at it this way: 3 days of float is AVAILABLE to any activity in that sub-path. In other words EITHER activity B or activity D could slip by 3 days without delaying the project, but they cannot BOTH get delayed by 3 days EACH because that would add 6 days to that sub-path within the overall network. Thanks for the question, and I hope the answer helps.
@pullatstrings8 жыл бұрын
very valuable tips. Just saw this 1 hour before the exam start and the eyeballing technique is awesome to save time and not get lost in detail. Cheers
@SirGanttalot15 жыл бұрын
You are welcome. Glad it was useful to you.
@colinmaharaj14 жыл бұрын
@yesIdoLikeDogs Did this in a PM class a few months ago. These videos are a great help for revision. exactly what was required.
@SirGanttalot15 жыл бұрын
Float and slack mean exactly the same thing. You can use either word with no problem. "Lag" is different though. Lag is a delay you build in between tasks (like waiting for paint to dry, or something similar).
@SirGanttalot14 жыл бұрын
Thanks for the comments and good luck with your exam. We are US-based rather than UK. However, we will shortly be starting on-line web-based seminar PMP and CAPM preparation courses, as well as other on-line and on-site courses. Please stay connected for more information. Regards.
@SirGanttalot15 жыл бұрын
I am really glad to be of help. Best of luck with your other studies. Are there any additional PM topics you think would make good items I could cover in a video?
@SirGanttalot13 жыл бұрын
Thanks for the feedback, I am very pleased that the video was helpful for you. It is still important to know that Float/Slack is LS minus ES, or LF minus EF, even though you most likely won't have to calculate values for ES and LS. You might, for example, get a question where you are told that an activity has an ES of 15th March and a LS of 15th March. The question will ask if the task is critical, and of course it is, because slack is zero in this case. (Beware the Ides of March!)
@SirGanttalot16 жыл бұрын
That's right. First, work out the Critical Path duration. Then, for the activity you want to know the float of, work out the duration of the longest path that goes through that activity, and subtract it from the duration of the critical path. This even works when an activity itself is on the critical path, bacause then the longest path through it will actually be the critical path, and the subtraction will give you the answer of zero, which is what you would expect.
@nuriasanzgarcia51195 жыл бұрын
Thank you! I have been racking my brains about slack for a bit.
@SirGanttalot15 жыл бұрын
Because it has 3 days of float. If you look at the possible paths, there are three: ABDI is one path, it's duration is 12, ACEGI is another path, duration is 11, and the last path is ACFHI. The last path duration is 15, so that is the longest and therefore critical path. The path that contains D is only 12 days in duration so that path is not critical. It is 3 days shorter than the critical path, so B and D both have 3 days of float. Hope this helps.
@SirGanttalot15 жыл бұрын
Thanks for the question. In that case there would be 2 critical paths. This is perfectly possible. In fact there can be as many critical paths as there are paths altogether. If Task G was 6 days, and Task B was also 6 days, there would be 3 critical paths. Sometimes you hear people say there can only be one critical path. That is incorrect. Bear in mind that any critical path is the most risky path, so having more than one critical path means the project has extra risk. Hope this helps.
@doralynch63509 жыл бұрын
For the critical path you need to include start and finish ... So in the example provided, the critical path is Start, A, C, F, H, I, Finish. Thanks for the videos, they are indeed very useful for reviewing!
@tranzoditty13 жыл бұрын
Really great representation. Your voice and explanation is unambiguous. Big ups mate :)
@batmandarknite397214 жыл бұрын
very clear!!! thank u so so so much. Now, i'm off to the second clip.
@TheBreze15 жыл бұрын
Thanks. It helps me to better understand the concept!
@SirGanttalot14 жыл бұрын
Yes that's right. Take a look at my Part 2 Video, which covers the Forward Pass/Backward Pass technique (the "Critical Path Method"). The purpose of CPM is basically to calculate the float (schedule flexibility or leeway) of every activity in the network. Typically, the Critical Path activities are then the ones that have ZERO float. In fact, most scheduling software does the CPM technique as the way to determine the critical path. Hope this helps......
@SirGanttalot14 жыл бұрын
Do you mean how do you identify the paths? If so, "paths" means all the different routes you can take from start to finish, or from A to I. In this network there are three paths in total: A-B-D-I; A-C-E-G-I; and A-C-F-H-I. Of these, the last is the longest duration, and is therefore the critical path. Hope this helps.
@howardschechter97689 жыл бұрын
OK! Good, short, well illustrated explanation of Critical Path.
@lewissteve716 жыл бұрын
You are the man! Thanks for this, very helpful indeed
@guitarist300112 жыл бұрын
THANK YOU VERY MUCH THIS WAS VERY HELPFUL AND SIMPLE PLEASE CAN WE HAVE LONGER ONES WITH MORE EXAMPLES THANK YOU. I AM WILLING TO PAY!!! THANKS AGAIN!
@SirGanttalot15 жыл бұрын
PART 2 reply: Just go one activity at a time, draw a box, and draw links to any predecessors. For example, in my own network diagram the description of Task G says it can start after activity E is finished. This means that E is a predecessor to G. Some activities, like Task I, can have more than one predecessor. Hope this helps.
@rajus016 жыл бұрын
i am doing it at A level in college i got my exam next week so this has been helpful
@เกียรติศักดิ์สุขยา-พ8จ5 жыл бұрын
Thank you teacher , Thank you very much.
@vishal18agarwal15 жыл бұрын
Thanks for sharing the video, it was good.
@SirGanttalot14 жыл бұрын
Did you look at the Part 2 Video? That covers Early Start and Finish, Late Start and Finish. If you still need clarification, ask again on the Part 2 video if you would. Thanks.....
@6myearsoldcoming14 жыл бұрын
Thank you for the best coach.
@drawohr14 жыл бұрын
@SirGanttalot Do you have any proposed dates for the online web based seminar fro PMP? Thanks
@SirGanttalot15 жыл бұрын
Well, you are right to be puzzled by a question like that because you need additional information. You need to know the sequence of activities. In the PMBOK itself, "Sequence Activities" is the process immediately after "Identify Activities", so any question about a network has to give you information that allows you to sequence the tasks, or it is an invalid question. Sometimes the questions are asked against an actual diagram of course, with the sequence shown. Feel free to send an example.
@rajus016 жыл бұрын
to work out the float you take away the next longest path to work out slack time?
@SirGanttalot14 жыл бұрын
There are several different ways to set out the diagrams. In fact, there is more than one type of diagram altogether, the "Activity on Arrow" diagram. I'm sure the way you learned is just fine. The key thing is to understand what the REASONS are for the steps you take. So, learn an approach that you like, and stick with that. Good luck.
@metallica92914 жыл бұрын
Hello, I have one question for you if you don't mind answering: if there are two paths with same duration i.e. longest duration = 10 days and 2 paths have a duration of 10 days how do you determine which one is the critical path?
@ahmednasr3248 жыл бұрын
Hello, we select the one which has the widest variance
@1chabot113 жыл бұрын
Very good, sir. Thank you so much!
@vash84713 жыл бұрын
yeah, this video is very helpful, and easily to understand..
@jigneshngadhia13 жыл бұрын
that was great.... I do not have to do any early start, late start calculations any more!!
@goodcraze15 жыл бұрын
Question. Activity D, has 5 days duration. Why it is not the in critial path?
@jonathandelapaz64362 жыл бұрын
Love this video so much. *HIHIT rocks
@wasilamjad15 жыл бұрын
What if task B would be of 6 days duration. That would make ABDI a second critical path of 15 days duration. What will be the critical path in this case? Why?
@romashka048711 жыл бұрын
This was very helpful, thank you soooo much!!! :)
@doust14 жыл бұрын
thank u very much. if u say node mode, wot dos that actually mean
@todaladentro15 жыл бұрын
Really nice Sir
@wasilamjad15 жыл бұрын
Thanks alot sir!!
@SirGanttalot13 жыл бұрын
It is possible. You need to have, and be able to list, experience managing projects or leading activities within projects. How much experience you need depends on if you have a Bachelors degree. If you do, you need to show 4500 hours experience over at least 3 years. If not, then 7500 hours over at least 5 years. You also need to have 35 hours of project management training. Go to the PMI web site and search for and download the "PMP Credential Handbook" for more details. Good luck.....
@SirGanttalot15 жыл бұрын
PART 1 reply: I'm not familiar with the way the questions are structured for the A level. Feel free to email me an example. Generally, however, when constructing the diagram all you are doing at that point is "sequencing" the activities. So the only info you care about at that point is each activity's ID plus its predecessor(s).
@nickknowles840211 жыл бұрын
THANK YOU FOR MAKING THIS EASY LOl
@Bari_Khan_CEng_CMarEng10 жыл бұрын
Sir Ganttalot... make more videos sir!
@Zico2015 жыл бұрын
i should pay u the tuition fees not the f'ing college.. thanks a lot for the helpful tutorial..
@hythamtikka12 жыл бұрын
nice
@85thday14 жыл бұрын
What country do you come from, you sound short of British and Ausie.