For people taking the PMP exam and are looking for help with earned value, make these substitutions: BCWP is the same as EV. BCWS is the same as PV. ACWP is the same thing as AC. This video was great once I mentally made those changes.
@Engineer4Free6 жыл бұрын
Yes, thanks for the contribution!l
@beingaesthetic74023 жыл бұрын
Thank u
@s0steezy Жыл бұрын
You literally got me through my project management course this semester, I couldn't afford the book. thank you so much, you do an awesome job at explaining analysis processes and most importantly their significances
@Engineer4Free Жыл бұрын
Thanks for letting me know, I'm glad I could help 🙂🤗
@SoarLikeAnEagle6243 жыл бұрын
You explain it so well and make it easy to understand. I've watched this 4 times and gone from not knowing anything about Earned Value Management, to being able to teach it at a basic level. Came back to make sure I clicked like!
@FaridWY6 жыл бұрын
PMBOK 6th Edition: ACWP = AC BCWP = EV BCWS = PV
@denisdobrev33015 жыл бұрын
Very helpful, thanks!
@umarhanif13774 жыл бұрын
Thanks dude very helpful
@rajbpatil64044 жыл бұрын
Thanks Bro, great video, example and explanation. But this had me puzzled, was thinking to figure this out after watching the full video. Your quick tip helped.
@tanveerhussain92573 жыл бұрын
BCWS = PV is wrong. correct is pv =BCWS-ACWP
@tanveerhussain92573 жыл бұрын
pv =BCWS-EV
@oompaloompa90003 ай бұрын
Thank you for taking the time to make this video. My class textbook doesn't break down how it arrives at these numbers. It does a horrible job of explaining. I'm blessed that I found your video!
@TakeLife2TheExtreme7 жыл бұрын
As many of the other commenters has pointed out, you do a very good job explaining this and are very concise.
@motso65535 жыл бұрын
for BCWP of "Activity C" you could have said 33% of 1200= 396... I nearly got confused for a sec there but well done. It's my first time doing this and watching this video made me understand the concept so quickly. Thank you
@Engineer4Free5 жыл бұрын
Yeah sorry that's just rounding. really it's 33.3333333333333333333333333...%, but glad you got it figured out =) =).Make sure you check out engineer4free.com/project-management for all the tutorials if you haven't already!
@pietchavalala73512 жыл бұрын
You saved me there...i was expecting 396... so I was really confused as to why 400...but now it's clear that it was rounded
@a.r3725 жыл бұрын
am a student who studies on her own for CIPS advanced diploma, no teacher where I am actually.. and I have been proned to this chapter which I've found a little confusing to understand or to table it out. I just want to let u know, if a question on EVA comes out, I'll succeed because of this video! Am sure of it! Thanks again for the good job, may u be bless, this is soooo helpful!
@Engineer4Free5 жыл бұрын
Hey awesome I'm glad I can help you out! Make sure you check out all of my PM videos at engineer4free.com/project-management the EVA ones are numbers 33 - 38
@lamle-tu2tt4 жыл бұрын
I am from Vietnam and I thank you for your video, it was very helpful
@Engineer4Free4 жыл бұрын
Chúc mừng năm mới!! 🇻🇳
@janeswayne65244 жыл бұрын
I've never touched project management before. And I was confused looking at other videos and resources with formal lingo, until I found this GEM. I'm tempting to buy their hoodie right now after watching this video =))
@Engineer4Free4 жыл бұрын
Glad I can help!! You should check out the full PM playlist that I did here: engineer4free.com/project-management =) =)
@FzegeyeКүн бұрын
This is much more explanatory. Clear. Neat. Great work! So now EV is BCWP and Pv is BCWS. Right?
@201280964 жыл бұрын
Thank you for the simple yet effective explaination!
@Engineer4Free4 жыл бұрын
You're welcome, thanks for watching! You should check out the full playlist here: engineer4free.com/project-management 🤜🤛
@A.456-c8r9 жыл бұрын
Very clear and smooth explanation. This guy is a great instructor.
@Engineer4Free9 жыл бұрын
+A. Huckamee Thanks for the nice feedback! Glad to hear you found it helpful :)
@anishsule32835 жыл бұрын
Ur real jewel of a person..Spending your valuable time for mine kind of people who seeks engg mnmt knowldge is a great Cause..Thanx for uploading videos and they are very simple to interpret..Love from India 🇮🇳 and Nz🇳🇿loads of respect 🙏👍
@Engineer4Free5 жыл бұрын
Thanks Anish! Really appreciate your comment 🙂. Love back from 🇨🇦Canada where I'm from and 🇱🇦Laos where I am.
@alinapariyani46833 жыл бұрын
I have given up on trying to ask my professor for help. I am just watching these instead! Thank you.
@diyaz_mukhanov4 жыл бұрын
Thanks a lot. It became so easy after the explanation. The tables are beautiful!
@Engineer4Free4 жыл бұрын
Great!! Glad you liked it. Check out engineer4free.com/project management if you haven't already, for the rest of the PM videos that I did!
@AdiLNgay3 жыл бұрын
I just love the way you are able to clearly explain all these concepts! I do not know how much I have heard and read of Gant charts, yet I could never quite understand how it was put together!! and now I am just like: ddduuuhhh!! this was it? I am just in 2.45 min of the video and had to stop to make that comment! there are a few other concepts that I could not understand either but I am never disappointed when come here! you are a God sent!
@Engineer4Free3 жыл бұрын
=) thanks for letting me know!! And glad I can help. There are more videos here too: engineer4free.com/project-management The Earned Value Analysis ones are #33 - 38
@youngkim59094 жыл бұрын
2:27 you can't start activity E before completing D. D is a predecessor to E. If D is behind schedule, the whole project is behind schedule.
@Engineer4Free4 жыл бұрын
Yes. Note that on this diagram "7" represents both the end of day seven, and the beginning of day eight. If the project was on schedule, at this moment of reporting, we were expecting D to have been finished (at the end of day seven) and E to just be starting (at the beginning of day eight). The whole project will indeed finish late unless somehow a day is saved during activity E.
@aewcontrol29842 жыл бұрын
Perfect and to the point, very lean
@mohand0883 жыл бұрын
Thank you for the explanation. Just to clarify BCWP AKA Earned Value (EV) ; BCWS AKA Planned Value (PV)
@arihasan34238 жыл бұрын
You describe every detail, extremely good video! Thank you!
@rajatmishra15613 жыл бұрын
best video on EV
@Engineer4Free3 жыл бұрын
Thanks Rajat! ☺️
@Dimitrapet5 жыл бұрын
Thank you very much! All videos are well and simply explained. Greetings from Greece.
@Engineer4Free5 жыл бұрын
Thanks!!!
@jacqueshollands5630 Жыл бұрын
Excellent example
@tannkimhing91775 жыл бұрын
I hope this would help me with my Examination tomorrow
@Engineer4Free5 жыл бұрын
Hope so! How did it go?
@PhanCpants6 жыл бұрын
Thank You! This video actually made sense compared to my textbook!
@Engineer4Free6 жыл бұрын
hahaha glad I can help :p
@febeangulo48446 жыл бұрын
@@Engineer4Free Of course it made sense haha... This guy is the master of PM. I've learned more from him than from my whole Master's degree program in Project Management hahaha
@gsxrguru25 жыл бұрын
Very helpful video for a particular capstone! =)
@jms39425 жыл бұрын
I wonder why they wrote the textbook in such a nonsense format. Great job sir
@Engineer4Free5 жыл бұрын
ya me2 🤔
@RayOnRae959 жыл бұрын
Ooh now my exam doesn't seem so hopeless!
@eminabdullayev89597 жыл бұрын
Great video, it would be good to add here, ETC and EAC for full picture...
@theChrisCroft5 жыл бұрын
Does a SPI of 0.5 mean that you would predict that the whole project is going to take twice as long as planned? Can you use it to forecast finish date, at least approximately? Is that the point of SPI / what it is used for?
@Engineer4Free5 жыл бұрын
Yes, you are right in what you're thinking. Check out videos 33 - 38 here: engineer4free.com/project-management for a few more explainers on SPI etc, and some ways that you can use it to make predictions too.
@theChrisCroft5 жыл бұрын
@@Engineer4Free - this is great, at last I've found someone with a brain who really understands SPI! There is something that's been worrying me about SPI for a while and I really hope you can help. either I've missed something or the whole world of PM has missed something...! So, SPI is based on VALUE of work planned / performed, so the degree of lateness depends on the VALUE of what you should have done but haven't. so if the part you haven't done is something expensive (e.g, painting with gold paint) then SPI makes you looked later than if the part you haven't done is something cheap (e.g. painting with ordinary paint). That's right isn't it? But this is clearly crazy - because it shouldn't matter whether the painting I should have done but haven't is with gold or other paint, it's still the same degree of lateness. The forecast finish date should still be the same. Why should COST, or value, affect the forecast finish date? Does this question make sense? If not I can send you an example? I'd love to get to the bottom of this, I'm not a fool, I've thought about it a lot, and I think there is a flaw in the whole SPI methodology. Help me to change the world of PM thinking on this!!
@chakradharvangara32853 жыл бұрын
Very nicely explained !!
@Engineer4Free3 жыл бұрын
Glad you liked it!! =)
@ahmedzayed63013 жыл бұрын
Thank you so much , that was so tough for me to understand before watching these videos
@Engineer4Free3 жыл бұрын
Glad to hear it Ahmed 😊
@kwameadjei3964 Жыл бұрын
Well explained. Thank you
@YusufKhan-sp6ii5 жыл бұрын
Bcwp of activity C would be 33% of 800 or 1200? I think it should be 33% of 800 because we are calculating the performance of 7 days not 8 days,,, am I correct ? Please answer me.
@Engineer4Free5 жыл бұрын
Mmmm it should be 33% of 1,200. The reason is in the wording. The budgeted cost of work performed. One third of the work for a three day project was performed at the time when the report was taken. Ignore the cost that was actually incurred, because we are concerned with the budgeted cost. The budgeted cost of this activity is 1200 in total, or 400 for each day. The digested cost of the work that was actually performed is 1200/3=400. The budgeted cost of work performed is not the same as the actual cost of work performed, that would be 500 for activity C.
@aswanichittilla87455 жыл бұрын
Really liked the example
@Engineer4Free5 жыл бұрын
Thanks Aswani!!! 🙂
@Engineer4Free5 жыл бұрын
Thanks Aswani!!! 🙂
@khalidmuhammad27984 жыл бұрын
I have a quick question. On the reporting date if you are behind on some of the tasks but you have completed some of the tasks which were planned to be completed after the reporting date. Can you take credit of that work to compensate for the poor SPI or CPI on reporting date?
@Engineer4Free4 жыл бұрын
Yeah it would skew it in the positive direction, where as being behind skews it in the negative direction
@SoNuz144 жыл бұрын
BCWS of activity D will be 200 instead of 400
@Engineer4Free4 жыл бұрын
Mmmm BCWS stands for “budgeted cost of work scheduled.” By the time of the report, D was scheduled to be completed. And at $200 per day, $400 of work on activity D was scheduled to be complete. So the BCWS is $400. The BCWP is $200 (which is the budgeted cost of work performed), as only $200 of budgeted work was completed by the report date.
@tsp88552 жыл бұрын
excellent, very well explained!
@Engineer4Free2 жыл бұрын
Many thanks!
@nadeemasif2406 Жыл бұрын
Sir what is difference earned value approach, earned value analysis, and earned value Management
@El.mosquito.4 жыл бұрын
Good video. Question: why did you record BCWP for Activity B as 1200 if the incurred cost was 1400? Who pays that 200?
@Engineer4Free4 жыл бұрын
Thanks! Assume our project is to build a house, and that activity B is painting the walls. The painters told us that it would cost $1200 before they got started. But on day 7, we get a report back that for some reason $1200 wasn't enough, and it actually cost $1400. Like for example if the painters are our actual employees, and we pay them $100 per hour, and they thought it would take 12 hours, but it actually took them 14 hours, then we really have to pay them $1400, because that's what employers do. So we (the project owner, or manager) have to pay the extra $200. Thats just one example of why the cost of work scheduled may be different from the actual price paid for that work. Hope it clears it up!
@davidh2667 жыл бұрын
what would you do if a question says for example Activity budget % complete actual cost F 600 0 200 so that even though the activity hasn't started 200 is spent
@gnitri9 жыл бұрын
Great Tutorial by the way Activity C BCWP = .33 * 1200 = 396
@karlkerr73486 жыл бұрын
1/3 x 1200 = 400
@AndresTorres-jv6dh6 жыл бұрын
the 4 lacking units, are hidden in the aproximation of 0.3333333.......
@sergnextdoor52135 жыл бұрын
Agreed, i can see his perspective because he uses the # of days to conclude his EV. To be exact, its 396 because only 33% of the activity has been completed thus earning $396 USD. not 400.
@RicoThomas-vj4rb6 ай бұрын
Hi I just wanted to ask if activity C was 80% done, would it’s BCWP be the same as the BCWS because by the time the report date has been reached the same amount of work has been done as the BCWS?
@OO-lh7nt2 жыл бұрын
First of all thank you for your describing. Is it different by using 50-50 rule of calculation the BCWP (ev)?
@rohangeorge35533 жыл бұрын
Thank you, great help
@Engineer4Free3 жыл бұрын
You're welcome! Glad it helped =)
@katlarabi-tchalaia22643 жыл бұрын
Thank you, that was very useful
@babitapitta Жыл бұрын
I am working on as assessment for EVA, we were given an excel sheet with calculations. Total plan for 6 months with dollar values for BCWS are given, ACWP and BCWP till September are given. In the sheet given to us rolling status is provided and calculations for SC, SPI, CV, CPI are done based on the rolling status. In your example you have not taken that rolling status, now I am confused if I should do rolling status or not. and If i should consider the calculations for BCWS till October or till only September. Please help. Please let me know if you have not understood my concern.
@rizukiichirou42724 жыл бұрын
thanks sir, very helpful
@Engineer4Free4 жыл бұрын
You're welcome!! 🙏
@malsalihi1938 Жыл бұрын
Given a total quantity of 12000 CY of concrete to be placed, at a cost of $400/CY. At the 40% schedule point, the contractor placed $2,160,000.00 worth of concrete. What is the CV? Can you help solve this problem. Thanks
@shakesrear78503 жыл бұрын
What pen are you using kind sir? How are you able to write so accurately!?
@ashleymaddox55118 жыл бұрын
This is a GREAT video. Is there anyway for me to save this?
@Engineer4Free8 жыл бұрын
+Ashley Maddox Thanks for the compliment! I currently don't have any options for downloading, you'll just need to favorite it on KZbin or bookmark the website: www.engineer4free.com/project-management
@lilaresearch31622 жыл бұрын
Thanks for this video! Really helped me alot. I have one question: Why do activity C and D are expected to end on day 6?
@anthoniocassim6748 Жыл бұрын
Very helpful, thx a lot
@alfredmarx7438 Жыл бұрын
Well exlained
@jboone37459 жыл бұрын
Great example, and thank you for this.
@Engineer4Free9 жыл бұрын
+Joe Cooper Thanks for the feedback! Glad to hear its making sense!
@jboone37459 жыл бұрын
You're so welcome, I can't understand why so many people who I know have seen this, but refused to show application for your work.
@rpacook3 жыл бұрын
If the activity is 100% completed with a BCWS of 4, an ACWP of 6 and a planned duration of 2 days what would the BCWP be?
@elaniece3 жыл бұрын
why didnt you fill out the rest of the chart? that was the main information i needed
@Engineer4Free3 жыл бұрын
See videos 34 and 35 here: engineer4free.com/project-management
@mohanparthasarathy17774 жыл бұрын
Great Video
@Engineer4Free4 жыл бұрын
Thanks Mohan 😊
@LawDude-hb2vt4 жыл бұрын
THANK YOU SO MUCH.
@Engineer4Free4 жыл бұрын
YOU'RE WELCOME.
@fluturaperdja87193 ай бұрын
why does activity B have Incurred cost of 1400 and not 1200?
@dark_bull678 ай бұрын
How did bcws of activity d come 400, shouldn't it be 200 if bcws of activity c is 800, you calculated c to be 2/3. So shouldn't d be 1/2 of 400
@juancarlosotero56207 жыл бұрын
Really great video Thanks for your contribution. Brilliant
@Engineer4Free7 жыл бұрын
Thanks for writing! Make sure you check out engineer4free.com/PM for the rest of the tutorials :)
@eireneestellia8615 Жыл бұрын
Hey, this is really helpful! But, can I ask you a question? For the BCWP in the activity C, why can't we just calculate it as 33% multiply by actual cost? I'm genuinely curious and maybe miss some of details. Thank you in advance!
@thepriestofvaranasi Жыл бұрын
Yes you can do that too!
@miazuo50954 жыл бұрын
hi~I am wondering how to know the report day is 7?
@Engineer4Free4 жыл бұрын
That would be given to you in a problem, as well as the level of completion of certain activities, and from there you can assess the situation.
@arunraj_r5 жыл бұрын
Thank you so much
@Engineer4Free5 жыл бұрын
You’re welcome =)
@Daniela-xc7ds3 жыл бұрын
Hi, can I considere Deliverables or Objectives instead “activities”? Or different projects instead activities? I mean, if I am working with a portfolio. Or should I do the maths with weighted average?
@chris-125009 жыл бұрын
Great video and well explained. Thanks
@Engineer4Free9 жыл бұрын
chris long Thanks for the feedback!
@chriso79566 жыл бұрын
Very Helpful! Thank you
@Engineer4Free6 жыл бұрын
You're welcome Chris! Thanks for the comment =)
@junedshaikh29643 жыл бұрын
For activity C, how did we determine that only 33% of work is completed..is there a tool or calculation?
@Engineer4Free3 жыл бұрын
We are the off-site Project Manager, and the person in the field has delivered the report in the bottom left corner to us. Because we are at the end of day 7, we expect 66% of activity C to be completed based on the original Gantt chart, but they are telling us that in reality things are moving slower, and it is only 33% done.
@junedshaikh29643 жыл бұрын
@@Engineer4Free Yes. It is says on the chart 33% complete. Also, the expected work to be completed was 66%. if the work is not completed to 66% as estimated... how do we conclude it is 33%, 40% or 10%. How did the field report or any report can calculate % of work completion unless not assumed.
@rajivdahal92602 жыл бұрын
Thanks
@carsnation58604 жыл бұрын
Thanks that helped alot ❤️
@Engineer4Free4 жыл бұрын
Glad it helped!
@fcoatis7 жыл бұрын
Great video. One Question. How would I deal with the incurred cost of task C $500 in MS Project?
@Engineer4Free7 жыл бұрын
Hey thanks for watching and commenting. It's been too long since I used MS project so I can't remember the exact process. Sorry, good luck!
@Florenstiya8 жыл бұрын
thank you! i think i will pass my exam now
@Engineer4Free8 жыл бұрын
I hope so!!
@TheManubarcafan8 жыл бұрын
so... did you make it?
@karlkerr73486 жыл бұрын
With this example it doesnt explain where the % completes come from. What determined the task D to be 50% for example? Whats the basis of measurement of this task performance?
@Engineer4Free6 жыл бұрын
At 0:08 I mention that it is from a field report. IRL, a schedule for a project is made, then people attempt to carry it out, and sometimes it goes faster or slower or costs more or less than originally planned. Most of my PM videos revolve around planning before execution, but this video is an example of how to interpret the field results that are not determined by us, but by the actual performance of other people/circumstances. So the a person in the field reported to us that Task D was half done, and they would have their own criteria, for example, it could be as easy as they are building a wall and have half of it up, or for a more complicated task it might not be so easy, but that would entirely depend on the context. This video is just about how to take someone else's field report and interpret the status of our active project. Hope that helps clear it up.
@sanaahmed84645 жыл бұрын
Thanks alot
@Engineer4Free5 жыл бұрын
You're welcome Sana!
@rasmank9 жыл бұрын
Thanks for sharing. really helpful
@Engineer4Free9 жыл бұрын
Martin Karuiru Glad you found it helpful!!
@amiyo977 жыл бұрын
thank you sir.. you really help me so much :) thumbs up for you sir
@Engineer4Free7 жыл бұрын
Thanks for the comment :) glad the videos are helping!
@amiyo977 жыл бұрын
I've been going through hours of reading lecture notes to understand earned value management.. But it took me just 10 minutes to understand this just by watching your video.. Thanks again :)
@Engineer4Free7 жыл бұрын
No worries! If you haven't already, make sure you check out engineer4free.com/project-management for the rest of the videos :)
@odelalo84922 жыл бұрын
Hi, suppose if Activity B is only 66.6% complete, is it 3 days behind schedule from the reporting date, or do I consider it as 1 day (the unshaded part)?
@darkbroseph8 жыл бұрын
Thanks a lot!... God bless!
@yayatoure34618 жыл бұрын
Question though. How do you deal with earn value and fixed costs and cost resource?
@trevorrabey7366 жыл бұрын
The video does not properly define what "actual % complete" is. What is the numerator and denominator? It is apparent (maybe) that "actual % complete" = actual duration/baseline duration, or actual duration/total duration, where total duration = actual duration/(actual duration + remaining duration). What happens if Task A took 3 days actual instead of 2 days? It is still finished, but is the "actual % complete" 100% (ie 3 days/3 days) or 150% complete (ie 3 days/2 days)? Well, it can't be 150%, has to be 100%.
@Engineer4Free6 жыл бұрын
This is a pretty simple model that is designed to compare anticipated results with actual results. You can check out a few other videos that I did on the topic, they are videos 33-38 here: engineer4free.com/project-management . They are all at an introductory level.
@Daniela-xc7ds3 жыл бұрын
In the real life, What are the possible reasons for C had incurred Cost of $500? Instead of 400.
@Engineer4Free3 жыл бұрын
Ummm, could be absolutely anything, because this is a generic activity with no information whatsoever. If Activity C was "building a fence", but a tree fell on the fence during construction and smashed some pieces, and they had to buy more. For example.
@dice8568 жыл бұрын
Thank you
@salmagadal341710 ай бұрын
i need help my table contains optimistic most likely and pessimistic days + my exam is soon please help
@Engineer4Free10 ай бұрын
See the PERT section (the last section) at engineer4free.com/project-management
@7usinmansour9086 жыл бұрын
thank you ,,, great work
@Engineer4Free6 жыл бұрын
Thanks, you're welcome ☺️
@priyankathakur52236 жыл бұрын
Gr8 video...it helped me a lot😍😘
@Engineer4Free6 жыл бұрын
Glad to hear it! 😘
@pranaychauli23310 ай бұрын
How BCWS for Activity D is 400 when 50% work is completed. Total budget 400. 50% work completed so ACWP is 200.
@saeedtalib83588 жыл бұрын
taking BCWS of activivity c is 800.. why not its completion percentage is 66%... Same case for activity D... having confusion just in thses two activities,,,,,,
@karlkerr73486 жыл бұрын
% completes are physical % complete not duration % complete.
@andujarjj6 жыл бұрын
PLEASE MAKE MORE VIDEOS!
@Engineer4Free6 жыл бұрын
Hey Jei thanks for the comment. More are in the works
@angelikaa55006 жыл бұрын
Hi, which theory literature peer review you used or is it OK to share ,if you know? Need for my writting module. Thanks
@Engineer4Free6 жыл бұрын
The method used in this video was taught to me by a professor teaching project management at the undergraduate level in a Canadian university several years ago.
@sergnextdoor52135 жыл бұрын
so I have my CAPM from PMI and looking for an internship in project management. Any help in landing one? anybody want to give me a chance?
@Engineer4Free4 жыл бұрын
Good luck!!!
@xsauce38586 жыл бұрын
over budget or under budget ?
@Engineer4Free6 жыл бұрын
10:26 this project is over budget and behind schedule
@Satyammishra-bf4ty9 жыл бұрын
thankyou...:) great work
@pbrpb47358 жыл бұрын
Hi Engineer4free, may I know what is the whiteboard tool you are using. Is it something to WizIQ. Thanks in advance.
@Engineer4Free8 жыл бұрын
Hey, you can find a full list of the software/hardware that I use at www.engineer4free.com/tools
@pbrpb47358 жыл бұрын
Thanks but actually wanted to know the tool for recording video screen
@pbrpb47358 жыл бұрын
Got it! Camatasia. Thanks.
@pbrpb47358 жыл бұрын
hi, how did you get the table up the screen. I dont find options. Or is it available only in subscription version.
@Engineer4Free8 жыл бұрын
I didn't use any subscription software to make this video. Sketchbook Express came free with the tablet, and Camtasia for Mac was a one time purchase. I just made the tables in Google Docs, took screenshots and pasted them into the drawing program.
@taherbakry41745 жыл бұрын
Where is the (Earned Value) Value?
@gummymansg5 жыл бұрын
Earned Value (EV) is the Budgeted Cost of Work Performed (BCWP)
@Engineer4Free5 жыл бұрын
Thanks Matthew!
@gummymansg5 жыл бұрын
@@Engineer4Free You are most welcome. I have shared your video with my project management students after my class as additional materials. Thanks for making EVM simple to understand.
@renzy4079 жыл бұрын
helpful. well explained. :)
@sunnywoo22685 жыл бұрын
EAC=BAC/CPI so what is BAC ,and how to calculate it ????? BAC BAC``````
@Engineer4Free5 жыл бұрын
Estimate at completion (EAC) = Budget at completion (BAC) / Cost performance index (CPI). These are used for forecasting, not reporting. Very similar thought process though. Just rather than knowing the actual money spent at the end, you are using knowledge from past performance to estimate how much money will actually be spent at the end. If you google EAC=BAC/CPI a few decent resources pop up.
@belayyimenutube13306 жыл бұрын
exellent
@Engineer4Free6 жыл бұрын
Thanks
@CecilDSouza7 жыл бұрын
This was explained well but the pace of speaking was a bit too fast. Also, you have failed to use the terms PV and EV apart from BCWS and BCWP which is important as not everybody uses the latter.