PMP Exam Practice Question and Answer -176 : Vendor Avoiding Contractual Obligations

  Рет қаралды 284

iZenBridge Consultancy Pvt Ltd.

iZenBridge Consultancy Pvt Ltd.

Күн бұрын

Пікірлер: 2
@suhaspai118
@suhaspai118 3 ай бұрын
I understand Option B, but here Vendor having Business concern, in which case I believe going with option C is better?
@izenbridge
@izenbridge 3 ай бұрын
When we made this question we were expecting some conflicts will come in answer from participants because in general collaboration is good idea, in this case we are testing how clear PM is to protect his companies interest, if someone have problem why they stop giving low priority to your delivery why not to other work, and in this question the vendor is not coming and discussing with you just avoiding fulfilling responsibilities , in such cases manage procurement contract of PM task expects PM to ask for meeting contractual commitments. This is how we see this topic based on PMI's task and material interpretation , i understand some of you may not agree.
PMP Exam Practice Question and Answer -175:  Ensuring Knowledge Transfer
3:51
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 296
180 PMP Exam Practice Questions - Updated for 2024
3:02:43
Helena Liu
Рет қаралды 45 М.
coco在求救? #小丑 #天使 #shorts
00:29
好人小丑
Рет қаралды 18 МЛН
How To Choose Mac N Cheese Date Night.. 🧀
00:58
Jojo Sim
Рет қаралды 95 МЛН
200 Ultra Hard PMP Questions #1-10
24:04
Andrew Ramdayal
Рет қаралды 27 М.
Ricardo Vargas Explains the PMBOK® Guide 7th Edition Published by PMI
1:36:40
PMP Still Worth It In 2024?
3:24
David McLachlan
Рет қаралды 20 М.
200 Ultra Hard PMP Questions #31-40
21:17
Andrew Ramdayal
Рет қаралды 9 М.