Got 12 correct out of 15. Thank you for sharing the knowledge
@saumya3202 жыл бұрын
I got 13 correct out of 15, Hope I could clear at my 1st attempt. Have scheduled my test on 27 Aug 22. Good luck for me
@rakeshbali52522 жыл бұрын
Have you passed PMP brother
@adnanalmalki2 жыл бұрын
Did u pass 🎉
@mchllmnrd2 жыл бұрын
Hope you passed ! If not don't give up, try again...
@raphrryzzy64462 жыл бұрын
Thanks for the insightful work, I have passed my PMP
@lpaone012 жыл бұрын
Hi Ralph, any advice on not what to study?
@nirvab.166711 ай бұрын
LOVE THIS CONTENT!
@omonukpoma78922 жыл бұрын
Excellent content to aid preparation of my PMP next month. Thanks a lot. Yes indeed #!15 was quite tricky but I believe I understood the "Trick" in the question aka related knowledge area......
@careersprints96812 жыл бұрын
Thanks a lot Omon. Glad to know you found the video useful :)
@nareshsem333 Жыл бұрын
Nice stuff,great explanation.answered 14/15,
@kshitijrathod3969 Жыл бұрын
Very well explained. Please come up with many more..
@careersprints96812 жыл бұрын
Please note in question #15 there the correct answer is A since the Project Manager would not meet with individual team members but rather consult or talk to stakeholders before suggesting or making changes to the project variables. Option D says individual team members and not stakeholders. A PM must perform an impact assessment/analysis of all changes before incorporating them. Also, changes must always be analyzed for impact on various project variables before a decision is taken on them (this a key PMI mindset or a proper PM mindset). Sincerely, Rohit from CareerSprints.com
@TheBabyget2 жыл бұрын
For question 15, the answer should be D as per the explanation.
@prathameshsatankar64172 жыл бұрын
Hi. But how project team members can decide which aspects of scope are not of value to the customer?
@TheBabyget2 жыл бұрын
@@prathameshsatankar6417 In my opinion, the answer is A. But, if you see his explanation at last, the answer goes to D.
@djro20022 жыл бұрын
@@prathameshsatankar6417 the correct answer is A, please see the 'pinned' explanation above.
@saumya3202 жыл бұрын
Answer A will be the correct answer as it will be the first step to evaluation of the impact and the scope for change, after that he will come to an conclusion whether he will remove any scope from the project post consultation with Project Sponsor.
@jimnelson24802 жыл бұрын
Hi, thanks for the PMP preparation exercises. NOTE: I suggest that you listen to your provided answer for question 10. You suggest C. is answer, although you indicate C to be correct Answer. in you statement you say C is Wrong. You kind of, miss match answer to statement made.
@careersprints96812 жыл бұрын
Hi Jim, Good observation; glad that you caught it; sorry for the confusion. :) I meant Option C is correct whereas the other options are wrong. Option C is the correct answer. That would be the most logical answer choice for the question. Sincerely, Rohit
@sargamkapoor18992 жыл бұрын
Good quality questions - different from the others. And I like the way you are presenting - quick & fast
@careersprints9681 Жыл бұрын
Glad you liked it!
@mdg7258411 ай бұрын
I have been studying, but I still get some questions that I think should be easy wrong. I will come across a similar question, apply the logic given to the other question, and get blindsided when it’s wrong. Example, changes to scope. There are a number of questions where the answer involves issuing change request and the reasoning provided is that a change to scope MUST go through a change request. Then you see questions like the one in the video about the senior company executive who comes by occasionally to give instruction about urgent feature work. One answer is require issuing of change request. The correct answer is meet with the executive and product owner to agree on a workflow. With the executive occasionally coming by, wouldn’t this only fix it this time vs requiring change request for new items fixing it all the time? Also, how do you differentiate when a question is looking through a lens that wants can you pick change request vs other answers?
@asignul20092 жыл бұрын
One really needs to take time, think and evaluate the questions and their implications
@sumitmitra73362 жыл бұрын
For Question 15, the option selected and the answer provided are a mismatch. Also for the " stem " or the ending line of questions how is the following different . For instance what is the difference between the 2 questions : How should the project manager RESPOND or what should the project manager DO NEXT ? are both questions same or different as depending on that the mechanism adopted for option selection could vary..
@careersprints96812 жыл бұрын
Hi Sumit, Please see the 'Pinned' response by CareerSprints and my response to 'Jagan Tarigoppula'. You will find the explanation to question #15. Sincerely, Rohit from CareerSprints.com
@mathewadekunle79912 жыл бұрын
The answer for question 15 did not match the explanation in any way. However, in accordance to the explanation, the correct answer should be option B. Please revisit question 15 for clarity. Thank you for your time.
@lpaone012 жыл бұрын
Great Job, thank you so much.
@asignul20092 жыл бұрын
Thank you. The PO delegation question i definitely got wrong lol
@mustaphalogbi19652 жыл бұрын
Thank you
@tesfayeyalew5563 Жыл бұрын
Q4. A) The fact that end users did not complete their training is no more a risk. It is an issue. Updating the risk register could not, therefore, be the best choice.
@careersprints9681 Жыл бұрын
The correct answer for the question is A, you will not wait until the next project status meeting to raise a risk, by then it might be too late which makes B wrong. The risk if raised can be mitigated so that it doesn't become an issue later on. Unresolved risks can turn into issues.
@faresar Жыл бұрын
I got all correct. Is the exam really that easy?
@careersprints9681 Жыл бұрын
Hello Congratulations on getting all answers correct. Please practice more questions to get more practice prior to the exam.
@faresar Жыл бұрын
@@careersprints9681 i just passed yesterday. Used your video to practice. Thanks man
@tasha9650 Жыл бұрын
Was the exam easy? I hear it's hard...
@faresar Жыл бұрын
@@tasha9650 wasnt easy. Just too many questions and little time
@gopalashetty35922 жыл бұрын
Differemnce between Agile Aliance and PMI?
@careersprints96812 жыл бұрын
Hi Gopal, PMI is the project management institute, the body that governs PMP certifications and the Agile alliance is another company which promotes agile values, principles and practices globally. The Agile practice guide, one of the recommended books for the PMP exam is written collaboratively by the Agile Alliance and PMI.
@lpaone012 жыл бұрын
I would strongly disagree with this answer. This impacts so many people who are also stakeholders (other Teams), perhaps they already have the requested time and resources scheduled for something else. A PM should instinctively, have already completed an impact statement. He should work with stakeholders and project teams to discuss whether this is a viable option, and also get buy-in from all who are involved. Hey, I will give them what they want in order to get certified.
@coutourplusconfidence83022 жыл бұрын
I did well. I only missed 1.
@careersprints96812 жыл бұрын
Great job!!
@bmooremoore44602 жыл бұрын
Girl congrats !!! I'm nervous ! Were you able to find a job soon after with great pay?
@jagantarigoppula77902 жыл бұрын
Very interesting scenarios built for these questions. The explanation presented on the slide for question 15 did not go in line with the choice selected. Also for evaluating any change request, it should be submitted to change control board, not a senior person.
@careersprints96812 жыл бұрын
Hi Jagan. Thanks for your comment. For question #15, the primary thing to factor in for the explanation is that since the sponsor is requesting the project length to be shortened this is a change request and the PM will need to check with stakeholders if there is a possibility to reduce the scope of the project to deliver within the timelines (reducing project scope does help with delivering the project faster). The correct answer is A because the PM would need to analyze the impact of this schedule change before incorporating the change. Changes must always be analyzed for impact on various project variables before a decision is taken on them. Also, a change control board is a role that can be taken on by anyone who has the authority to approve or reject a change. This could also be a senior person in an organization, think of small organizations where one person might wear many hats. This means a change control board can be one person too, also called a change authority in some organizations. The term doesn't matter as much as having a person or a committee to take decisions on changes. Hope this clarifies your question.
@saumya3202 жыл бұрын
@@careersprints9681 Is it D ? But in my view Answer "A" will be the correct answer as it will be the first step to evaluate the impact and the scope for change, after that he will come to an conclusion whether he will remove any scope from the project post consultation with Project Sponsor.
@sumitmitra73362 жыл бұрын
For Question 13 , the most suitable appears to be Option C . Instead of D. The items from the Prioritized backlog are SELECTED OR PICKED by the TEAM. They are NOT prioritizing the items , they are just "selecting "the items from the prioritized list basis their own bandwidth and team capacity/ resources at that point of time. The Product owner autonomously could be do product grooming/ Refinement / prioritization as per the business needs , but POST THAT selection of the items from that prioritized list ( which technically is called the SPRINT BACKLOG )is at the sole discretion of the development team . Or the product owner decides which items will be picked and which will BE LEFT in the upcoming iteration? Request you to shed some light on this nuance.
@careersprints96812 жыл бұрын
Hi Sumit, The reason why 'C' is wrong is because the option says 'Select prioritized items from the Sprint backlog'. The team would select items from the Product backlog to include in the sprint backlog. Had it been 'Select items from the product backlog' instead of 'sprint backlog', C would be the correct answer. Hence, the correct answer is 'D' because the team can always add items to the product backlog for the product owner to prioritize. Sincerely, Rohit from CareerSprints.com
@sumitmitra73362 жыл бұрын
@@careersprints9681 Thanks Rohit... Clear Oversight from my end & consequently i did not see that it was Sprint Backlog & not a product backlog..
@stayreal91402 жыл бұрын
I still disagree with Q13. I don’t believe a team member can add to product backlog. Only the product owner can. Option C still seems correct. Since it talks about selecting ‘for’ the sprint backlog
@careersprints96812 жыл бұрын
@@stayreal9140 A Product Backlog is a wish list of what stakeholders want to see in a product/service. It isn't necessary that the Product Owner would choose everything that's put in the backlog to be built. For option C on why it's wrong, kindly read the explanation given at the top and you'll understand why it's wrong. --Rohit from CareerSprints.com
@Relaxingsounds6472 жыл бұрын
The reason C is wrong is because Product owner does not work on the sprint backlog that's reserved only for the developers. Developers generate the sprint backlog from the already priorized project backlog
@tesfayeyalew5563 Жыл бұрын
For the final Q, the explanation does not match the answer.
@careersprints9681 Жыл бұрын
Read the comments please. it has been pointed out which is the correct answer. -- Rohit from CareerSprints.com
@sumitmitra73362 жыл бұрын
Shouldnt be the answer for Question 2 be : Performing instead of Norming... Since they are working " COHESIVELY " ... ( Key Word in Performing stage)
@careersprints96812 жыл бұрын
Hi Sumit, For question 2, it is stated in the scenario that the team has just moved from arguments and contradictions to healthier and better ways of communication. Also, the team has recently developed team norms and procedures for working cohesively. They've not been consistently cohesive which is a characteristic of 'performing'. Hence, the answer is 'norming'. Sincerely, Rohit from CareerSprints.com
@sumitmitra73362 жыл бұрын
@@careersprints9681 Thank you for providing conceptual clarity on this one