Pre-Commissioning vs Commissioning - What Takes Place During Each Stage?

  Рет қаралды 59,699

Industrial Commissioning Association

Industrial Commissioning Association

Күн бұрын

Enroll in my FREE 3-Day Mini-Course on Commissioning and Startup
Instant Access at commissioninga...

Пікірлер: 37
@Sandra__4x0j
@Sandra__4x0j Ай бұрын
Emotionally, we are thrilled to announce that the confirmation of your Sales Incentive payment has been processed.
@lotusworks1370
@lotusworks1370 11 ай бұрын
Excellent information, well done commissioning academy
@johnpeter8326
@johnpeter8326 3 жыл бұрын
Thank you Sir, for insightful information
@commissioning
@commissioning 3 жыл бұрын
Hi, John. It's our pleasure. If you have any questions, please don't hesitate to ask.
@johnpeter8326
@johnpeter8326 3 жыл бұрын
@@commissioning Thank you Sir,
@transporter880
@transporter880 2 жыл бұрын
Thanks really helpful
@CkDickson_M
@CkDickson_M Жыл бұрын
Brilliant explanation 👏
@vegvillage-kj9qs
@vegvillage-kj9qs 2 ай бұрын
Great information
@Ronald___621o
@Ronald___621o Ай бұрын
The poetic journey of refund details and expected actions
@sahatlumbantoruan4818
@sahatlumbantoruan4818 Жыл бұрын
Thank you very much Sir
@Jennifer___7r3
@Jennifer___7r3 Ай бұрын
Optimistically, it's official-the funds have made it safely from your bank to your Visa/Mastercard card.
@ITandAutomationAcademy
@ITandAutomationAcademy 3 жыл бұрын
Just simply best
@commissioning
@commissioning 3 жыл бұрын
Thanks for the feedback Noman!
@Sylvie_in_the_Sea
@Sylvie_in_the_Sea 4 ай бұрын
Thank you for this awesome video. If I understand well, hydrostatic tests are part of the pre-commissioning. Could it be that Mechanical Completion comes after pre-comm? How far does the commissioning go? Can it start-up the whole plant or could it be that the client makes the final steps of the commissioning to check that all the systems work well together and that the General Contractor stops after having checked big systems of the plant? Thank you.
@commissioning
@commissioning 4 ай бұрын
All very good questions, and the answers are all very project specific based on the contracts. Hydrostatic tests are part of pre-commissioning and are often done by the installer prior to MC. Further pre-comm then takes place after MC. There are lots more free resources your can check out on our site www.commissioningandstartup.com
@Sylvie_in_the_Sea
@Sylvie_in_the_Sea 4 ай бұрын
@@commissioning Thank you for your answer :) In the pharma industry there are commissioning > qualification > validation. Have you already worked on a pharma project?
@paulcarsonturner
@paulcarsonturner 4 ай бұрын
Yeah, pharma uses CQV. Different terminology, same concepts. Wouldn’t it be great if there was a standard set of terminology used across the commissioning industry? I haven’t worked on a pharma project.
@HappyLightLove909
@HappyLightLove909 5 ай бұрын
Thank you
@ratheshkavanamani6061
@ratheshkavanamani6061 8 ай бұрын
Very helpful 🙂
@bunnyman6321
@bunnyman6321 Жыл бұрын
Thanks
@yazidsalehuddin7633
@yazidsalehuddin7633 3 жыл бұрын
In term of project planning and schedule, do you recommend to further divide the Work Breakdown Structure (WBS) to Cosntruction, Pre-Commissioning and Commissioning or better to divided it into system and subsystem?
@commissioning
@commissioning 3 жыл бұрын
Better to divide into subsystem and system. Individual equipment of each subsystem will undergo pre-commissioning, then be tested as a system during commissioning.
@yazidsalehuddin7633
@yazidsalehuddin7633 3 жыл бұрын
@@commissioning Agree with you. As much as i had the same thinking like you but in reality most of the project plan and schedule nowadays still divided the WBS by Construction, Pre-Comm and Comm instead of by system and sub-system. I see that the main reason is because usually Construction phase and Commissioning phase usually will be excuted by different people/organization. Maybe in the video you can explain and maybe show one good example of how the project WBSby systemization
@commissioning
@commissioning 3 жыл бұрын
@@yazidsalehuddin7633 You're right, and this can be a cause for confusion as the project transitions from construction to commissioning. The construction team will focus on installation of each individual piece of equipment, as they should. But the thought process needs to change and focus on groups of equipment as a system. One piece of equipment is not very useful to the commissioning team on it's own - several pieces if equipment as well as cables, piping, etc are required to function as a system. The Commissioning Team can help with this transition by having very well defined Mechanical Completion documents.
@aboudamgh4831
@aboudamgh4831 2 жыл бұрын
many thanks is a good video for commissioning please speak slowly in case i can understand what you speak.
@faizthakur5832
@faizthakur5832 2 жыл бұрын
You can slow down video speed if you think u ain't able to understand.. Go to play back speed.
@user-yl8qd4hw1p
@user-yl8qd4hw1p 8 ай бұрын
Pre-commissioning is called mechanical completion, right?
@paulcarsonturner
@paulcarsonturner 8 ай бұрын
No. Mechanical completion (or static completion) is the milestone before pre-commissioning indicating that construction is complete (static installation is verified) and that pre-commissioning (functionality) testing can begin.
@instengineer815
@instengineer815 6 ай бұрын
Mechanical completion is where the Construction team gives the "key" to the Comm team and says "that everything is installed as per specs, it is tested and passed, and you can proceed now; that is your baby."
@dingintsibande7367
@dingintsibande7367 3 жыл бұрын
How long does it take to perform each test; pre-commissioning and Commissioning process?
@commissioning
@commissioning 3 жыл бұрын
That will depend. Each specific test will take time, depending what is being tested. Some tests will take days, some tests will take minutes. The overall pre-commissioning and commissioning process on a large project can take many months.
@dingintsibande7367
@dingintsibande7367 3 жыл бұрын
@@commissioning Thank you for the insight
@nadim606
@nadim606 Жыл бұрын
Seen
@ksimms82
@ksimms82 Жыл бұрын
Hi does one take the test ?
@user-yl8qd4hw1p
@user-yl8qd4hw1p 8 ай бұрын
I don't understand how FAT can confirm no damage during shipping. Anyone who can clarify this?😊
@paulcarsonturner
@paulcarsonturner 8 ай бұрын
It won’t, FAT results are compared to SAT results to confirm no damage during shipping or installation.
@William_j7
@William_j7 Ай бұрын
Get ready, brace yourself for important refund info
The Old Way to Learn Commissioning
14:22
Industrial Commissioning Association
Рет қаралды 1,9 М.
Do You Know The 9 Commissioning Critical Success Factors?
15:07
Industrial Commissioning Association
Рет қаралды 3,5 М.
What Is Commissioning In Construction?
14:50
Jason Schroeder
Рет қаралды 2,6 М.
What is Commissioning? (and related terms) - Commissioning Training
9:38
CommissioningCoach.com
Рет қаралды 102 М.
Fundamentals of Transformer Commissioning and Maintenance Testing
1:45:27
What is HVAC Commissioning & Why is it Important?
12:31
Fire & Ice Heating and Air Conditioning Inc
Рет қаралды 12 М.
Commissioning Certification: Everything You Need to Know
16:15
Industrial Commissioning Association
Рет қаралды 3,3 М.
Precommissioning activities
18:03
ALCHEMY ACADEMY
Рет қаралды 27 М.
Elements of a Contract
9:34
David Jaroszewski
Рет қаралды 295 М.
QC Inspections vs Commissioning Inspections - What is the Difference?
4:49
Industrial Commissioning Association
Рет қаралды 1,3 М.
Data Center Commissioning: What you need to know
1:00:28
Consulting-Specifying Engineer
Рет қаралды 9 М.
Commissioning and Startup 3-Day Mini Course - Module 1 - Prior to On-Site Commissioning
9:25
Industrial Commissioning Association
Рет қаралды 16 М.