I am still confused about the relationship between the "Story points in Agile Story Estimate" and "point in Agile PI capacity estimate". SAFe workbook, it says 1 person is 8 point for a 2-week sprint. On the other hand, to estimate stories, we also try to use relative story points, and not to map to the hours or days.
@SatishKollaAgile Жыл бұрын
Your understanding is correct, and no confusion required WP H regarding this. SAFe mentions to start with an assumption of 8points for a 2 week Sprint, considering the time spent by team members for related Sprint events. No where the mention of mapping Story points to hours or days.