SAFe - Capacity vs Velocity Calculations

  Рет қаралды 1,147

Satish Kolla

Satish Kolla

Күн бұрын

Пікірлер: 2
@summersummer1232
@summersummer1232 Жыл бұрын
I am still confused about the relationship between the "Story points in Agile Story Estimate" and "point in Agile PI capacity estimate". SAFe workbook, it says 1 person is 8 point for a 2-week sprint. On the other hand, to estimate stories, we also try to use relative story points, and not to map to the hours or days.
@SatishKollaAgile
@SatishKollaAgile Жыл бұрын
Your understanding is correct, and no confusion required WP H regarding this. SAFe mentions to start with an assumption of 8points for a 2 week Sprint, considering the time spent by team members for related Sprint events. No where the mention of mapping Story points to hours or days.
Velocity - An Agile Metrics
13:44
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 3,6 М.
Agile   Velocity and Capacity Planning Relationship
6:18
StandoutBrains
Рет қаралды 184 М.
Мясо вегана? 🧐 @Whatthefshow
01:01
История одного вокалиста
Рет қаралды 7 МЛН
黑天使只对C罗有感觉#short #angel #clown
00:39
Super Beauty team
Рет қаралды 36 МЛН
Inspect and Adapt
4:31
Louis Giboin
Рет қаралды 2,6 М.
The Ultimate Scrum Masterclass Full Series on Agile & Scrum
28:39
Suhaib Ajlouni
Рет қаралды 9 М.
Capacity Planning in Agile - Scrum
8:22
Pramod Hanumappa
Рет қаралды 11 М.
Simon Sinek's Advice Will Leave You SPEECHLESS 2.0 (MUST WATCH)
20:43
Alpha Leaders
Рет қаралды 1,5 МЛН
If you're ambitious but lazy, please watch this video...
12:57
Mark Tilbury
Рет қаралды 67 М.
Agile Estimating and Planning: Planning Poker ®
5:32
Mountain Goat Software
Рет қаралды 116 М.
Sudden Strengthening of Ukraine / Massive Offensive
12:01
NEXTA Live
Рет қаралды 667 М.