Thanks for sharing... Love it... I am a BIM engineer.. Right now i trying to integrate BIM model, speckle, and power BI for project measures system in my project.. It would be great if you can share about it.. I am struggling to make a system of it.. 😢😢
@TheBIMCoordinator9 ай бұрын
What kind of information are you trying to show in powerbi?
@abdulkausar80739 ай бұрын
@@TheBIMCoordinator The information I want to display includes earned value KPIs such as SPI, CPI, and others, which I obtained from schedule tracking in Microsoft Project. I want to make it real-time is that possible?
@TheBIMCoordinator9 ай бұрын
Idk much about Microsoft Project but if the data is available it should be possible. I connect all sorts of data together across different systems. Sometimes they require different approaches. Like sometimes there isn't an api for direct data queries but there is a way to schedule downloads of Excel, which you can easily tie into PowerBI. It is hard to say though if what you want can actually be done. Good luck! Let me know how it goes for you!