Situation based questions for PMP® Exam |Episode 8| Risk Management practice question for PMP® Exam

  Рет қаралды 3,417

Edzest Education Services

Edzest Education Services

Күн бұрын

Пікірлер: 33
@VimalKumarVV
@VimalKumarVV 2 ай бұрын
Excellent videos Amit.
@edzest
@edzest 2 ай бұрын
Thank you so much Vimal. :)
@fariaaisrar5476
@fariaaisrar5476 Жыл бұрын
Hi Amit! I passed 3AT today. I randomly found your videos 5 days before my exam and I sat and watched ALL of them. I hope to spread the word about your channel. I loved the way you explain things especially things like "observing" is an action, it's not something passive or the whole idea of parking each answer and seeing if your answer is justified with the information in the question. What really helped me was listening to your explanations of the wrong choices. They really try to trick you with the language.
@scumpuppies
@scumpuppies Жыл бұрын
What else did you do to study, aside from watching these videos?
@edzest
@edzest Жыл бұрын
Congrats Fariaa, this is so good to know. And thank you so much for taking out time to let me know about your result. Hope you are celebrating well. 🎉🎊 -Amit.
@rashedhassan2065
@rashedhassan2065 Жыл бұрын
SO HELPFUL, AWAITING YOUR NEXT VIDEO!
@edzest
@edzest Жыл бұрын
Thank you! Coming up tomorrow. 😊
@rizwanshahab8720
@rizwanshahab8720 Жыл бұрын
For questione no 5. Why not C, in the question it mentioned potential budget overrun due to increase in price. This means the price is not increased. Also, they have taken historical data that means it can also help to determine the potential increase in price.
@edzest
@edzest Жыл бұрын
Hi, option C suggests keeping a contingency reserve. And question suggests we don't know exact increase. In this case, team will not come to know how much contingency reserve to keep. A better choice is to discuss with supplier and fix a price - with this the team will eliminate the risk.
@vikasmehta3568
@vikasmehta3568 Жыл бұрын
Thanks for given clarification .. .contingency reserve is alwyas for low risk ..one of the important clarification got.
@edzest
@edzest Жыл бұрын
That's correct. 👍
@Latesh140
@Latesh140 Жыл бұрын
Hi Amit, I did watch your videos before appearing for PMP today and I cleared my exam with AT in all sections. I found your videos and explanations extremely helpful and strongly recommend your methodology for all the PMP aspirants. I emailed you last week for a question and you were kind enough to respond, even though I was not your student. Keep up the great work.
@edzest
@edzest Жыл бұрын
Congratulations on your success. Very happy for you. I hope you celebrate well. - Amit.
@edzest
@edzest Жыл бұрын
And thanks a lot for taking out time and commenting to let me know about your result as well. 🙏
@prafulladhavale9889
@prafulladhavale9889 Жыл бұрын
Thanks 🙏😇
@edzest
@edzest Жыл бұрын
You're welcome! 🙂
@AyushDubey205
@AyushDubey205 Жыл бұрын
In q3? Isnt the lesson learned review done in the beginning during initiation phase? Since we are at scheduling … we should go for insurance… Please help with your views
@edzest
@edzest Жыл бұрын
Hi, Insurance will only protect from any loss, and that too only monetary. The project's success depends on many other things as well not just cost. Hence, a better way to do it is to review the lessons learnt so that we understand the problems faced in previous projects. At the initiating level when you review the lessons learned from a previous project, you don't have a lot of information about this new project. Hence review of lessons learned from previous projects should happen at multiple levels.
@AyushDubey205
@AyushDubey205 Жыл бұрын
@@edzest thank you so much. That makes sense :)
@edzest
@edzest Жыл бұрын
@@AyushDubey205 you're welcome! Do let me know if there're any other doubts as well. Throughout your preparation.
@vibhor305
@vibhor305 Жыл бұрын
Question 2- how group discussion will ensure that team members won’t fall sick? Question says, how to ensure project continuity…I am bit unclear on the selected choice. Should n’t manager accept and use contingency reserve..do we select Accept only for low risks?
@edzest
@edzest Жыл бұрын
A group discussion will make people aware of changing weather conditions and they are expected to take better precautions after that. Contingency reserve is for low priority risks and those risks for which response cannot be planned. Which means you deal with the "effects" In all other cases it is always better to plan a response, which means dealing with the "causes"
@atuldhaundiyal_calgary
@atuldhaundiyal_calgary Жыл бұрын
If we ask another company ( client) to perform transportation. What kind of response is this?
@edzest
@edzest Жыл бұрын
It can also be considered a way to transfer risk.
@AnirudhaPavan
@AnirudhaPavan 26 күн бұрын
Bro Please clarify your 1st q&a As the equipment purchased from 3rd party it is their responsibility to reduce the probability of this risk occurring by seeing what could go wrong in the equipment after escalating from PM side. Instead the answer is mitigate How would a PM mitigate on himself if it’s a procured item? Request to clarify
@edzest
@edzest 21 күн бұрын
Hi, transferring the risk to supplier can not be called escalate. It will be called transfer but to be able to use transfer as a response, the supplier/vendor should also agree, which is not mentioned in the question. Hence, mitigate is better.
@vibhor305
@vibhor305 Жыл бұрын
At the completion of a small project, the risk manager performs a risk audit and finds that several identified risks had occurred, and the impact was significantly larger than expected. While the project remained on schedule, the project budget increased by 50%. The project met all risk response milestones and no additional, previously unidentified risks, occurred on the project. Based on this information, what risk management process improvement should the risk manager recommend for future similar projects? A. Increase frequency of risk management meetings with the project manager. B. Revise the level of accuracy of probability and impact scores. C. Document the risk audit report and capture it in the lessons learned database. D. Expand the use of risk identification techniques. --what is the right answer for this question. Please share your opinion. I believe it should be B because in current project risk impact was not analysed properly which caused addition of 50% budget
@edzest
@edzest Жыл бұрын
Hi Vibhor, B does sound better as the issue was with estimation of budget impact, that turned out to be 50% more ...
@vibhor305
@vibhor305 Жыл бұрын
@@edzest Thanks for taking time and responding back.
@stephenadjei7967
@stephenadjei7967 Ай бұрын
1C
@edzest
@edzest Ай бұрын
👍🏻
@stephenadjei7967
@stephenadjei7967 Ай бұрын
Mitigate
@edzest
@edzest Ай бұрын
👍🏻
She made herself an ear of corn from his marmalade candies🌽🌽🌽
00:38
Valja & Maxim Family
Рет қаралды 18 МЛН
UFC 310 : Рахмонов VS Мачадо Гэрри
05:00
Setanta Sports UFC
Рет қаралды 1,2 МЛН
So Cute 🥰 who is better?
00:15
dednahype
Рет қаралды 19 МЛН
Арыстанның айқасы, Тәуіржанның шайқасы!
25:51
QosLike / ҚосЛайк / Косылайық
Рет қаралды 700 М.
PMP JOURNEY| Where should I start
31:15
Edward Coke, Jr
Рет қаралды 5 М.
2025 PMP exam important Tips and Exam Study Guide
20:53
OPM RedPill - by Serkan Kaya
Рет қаралды 90
She made herself an ear of corn from his marmalade candies🌽🌽🌽
00:38
Valja & Maxim Family
Рет қаралды 18 МЛН