FIORENTINI ALIMENTARI
Italy
The partnership with System Logistics started in 2017 with the design of a new logistics hub in the province of Turin and continued in 2023 with the necessary expansion following the constant growth of the brand. With the new hub, the company has internalized the storage of raw materials and finished products ready for shipment, in order to maintain control over the entire storage process, optimizing its management and timing. The intervention has allowed for better logistical traceability in the various production areas up to shipment, with a consequent control over risks and a reduction in costs. With the ongoing expansion, the warehouse area is increasing from about 13,000 pallet positions to over 18,000, doubling the goods receiving capacity thanks to the new external entrance area.
2017 Plant: Existing Structure
Stacker cranes:
6 units (2 double-depth, 4 single-depth).
Racking:
Capacity of 12,936 pallet positions, equipped with an oxygen-reducing fire prevention system. The dimensions of the warehouse are approximately 34x92xh28 meters.
SVL Automatic Loop:
System with 8 shuttles, connecting the stacker crane warehouse to various production points, including:
Finished product entry area from production.
Raw material exit area towards production.
Four “goods-to-man” picking bays, equipped with hydraulic platforms to improve operator ergonomics.
Inbound goods reception area from outside.
Outbound shipment area.
AGV Vehicles:
4 AGV CP MINI, to serve the production lines.
2 AGV CP Medium, used for activities on internal compactable shelving, with pallet lifting capacity up to 10 meters.
2023 Plant: Expansion of the Existing
Stacker cranes:
Addition of 3 units (1 double-depth, 2 single-depth).
Racking:
Capacity of 5,175 pallet positions, with oxygen-reducing fire prevention system. The dimensions of the new warehouse are approximately 16x92xh28 meters, with the racking erected alongside the existing one.
SVL Automatic Loop:
Extension of the loop with the integration of 4 additional shuttles, to improve the overall performance of the system.
New inbound goods reception area from outside.
Strengthening of existing areas, including:
Finished product entry area from production.
Raw material exit area towards production.
AGV Vehicles:
Addition of 2 AGV CP MINI to support the new production line.