This is very well explained and in a way that most lessons miss
@roronoazoro-5183 жыл бұрын
I am subscribing to this channel!
@sameeralakmal77944 ай бұрын
Great 👍 very clearly explained.
@wflzoom62192 жыл бұрын
The interesting thing here, is, that in the "soup" example, process B was resolved by increasing equipment, as 1 person would still occupy process B, but in the toy example it would depend greatly on what is involved in that process , if it's a hand-on assembly process , then having three people doing that could lower the time to 2 min for that process, but if it's machinery that requires a dedicated operator, then we would need 3 machines and 3 operators. (a lot of cost) which may require some other creative solution.
@MINIAWARFR5 жыл бұрын
Thank you, its finally clear to me
@roronoazoro-5183 жыл бұрын
That was just amazing explanation, very comprehensively covered :)
@todoz98045 ай бұрын
Thank you so much!! Very good examples
@wowmix95224 жыл бұрын
Excellent explanation! Thank you! Keep making videos please.
@sixsigmaacademyamsterdam4 жыл бұрын
thank u
@HBazanDesign3 жыл бұрын
When calculating capacity of an inspection line, I account for reruns and Equipment downtime on top of the scheduled amount needed to be inspected which amounts to 11% more units and then on the inspection line there is a calculated capacity using the ideal cycle time however its a manned station and its not 100% efficient therefore my Actual throughput is 10% less. Can i show these numbers to show we need more overspeed or am i double dipping the downtime numbers?
@sixsigmamania3 жыл бұрын
Hi. If is still relevant. Yes return part must be calculated into the TT. If is rework, try to improve, because its a waste. Dowtimes must be subtracted from available time, so yes it is affecting final TT. I would suggest to focus on improving down times and rework to minimum. Focus on nonvalue added activities improvement. After I would recalculate and show to management. Does this helped?
@nobrainv6591 Жыл бұрын
at 14.7 can you explain why if cycle time is less than take time then it meet customer requirement? the total lead time of the total process still be 10+2+2+2+2 = 18 min if takt time is 2 it mean that suppose available time is 10 min, demand per day is 5 then take time is 2 min. but if you have cycle time 2 min. that mean you will complete the total process = 18 min. that is more than available time 10 min.? how can that be acceptable?
@SkillMusicSA6 жыл бұрын
Thanks, this really helped a lot.
@natnaelfasil91742 жыл бұрын
How is 2 instead 8 on product C????
@JaiisonBANKS3 жыл бұрын
Amazing champ
@นัฐยาจันทร์นอก5 жыл бұрын
Thank you.
@liyakatshaik40273 жыл бұрын
Thank you. Clearly understandable.
@jeremysun13484 жыл бұрын
Thanks for great video. In the Takt time section example is 40 hours, is it assuming there is only on person in the production line or during calcuation there is no need to consider the man power?
@sixsigmaacademyamsterdam4 жыл бұрын
Hi there, it assumes one person manning each station.
@jeremysun13484 жыл бұрын
@@sixsigmaacademyamsterdam thanks a lot!
@bhargavi54873 жыл бұрын
Nice but one doubt how come a week consists 40 hrs
@sixsigmamania3 жыл бұрын
Hi. If is still relevant. 1 work day = 8hours. 5days x 8=40. This is available time.
@bryansaenz90704 жыл бұрын
Very helpful! One question: A company has different types of products (let's say different toys, for instance), the takt time is refered to the complete demand of any kind of toys or you can apply that for each type? What is the common way to use it? Thank you a lot!
@sixsigmamania3 жыл бұрын
Hi. If is still relevant. TT in this case depends if all products pass the same line or there are different lines for each. If different lines TT is calculated separatelly. If one line TT is common for all products. It is key to have right scheduling method to induct every part every day. Does this helped?
@yamakozz3 жыл бұрын
very helpful , thx.
@sixsigmaacademyamsterdam3 жыл бұрын
tanx
@humphreychan63826 жыл бұрын
thank you/. I wish my professor explained the concept as clear as you did
@sixsigmaacademyamsterdam4 жыл бұрын
Welcome!
@rakeshlohana46576 жыл бұрын
Defects and its A, B, C types pe Hindi me video banaye
@HenryLopezmatos5 жыл бұрын
Hello profesor, thanks for your video. It is helpful for me to understand. Question: how can I calculate WIP in this example? I was watching Little's Law video kzbin.info/www/bejne/Zp2XoKaiat6MfNE and I understood WIP and Thruput concept. But how can I get WIP in this particular example. Attentive to your prompt response. Thanks in advance.
@sixsigmaacademyamsterdam4 жыл бұрын
Hi there, simply count the finished goods and count your inventory. The rest is WIP.