SSE Renewables’ first battery energy storage system (BESS) project has reached a significant milestone, with all 26 battery units successfully installed at the site in Salisbury, Wiltshire.
The 50MW project is being delivered in conjunction with Wartsila. The site is scheduled to be fully operational in early 2024.
Installation took place over a three-week period and was carried out by King Lifting. The battery units were carefully lowered down onto the concrete foundations in four modular sections via crane.
We caught up Project Manager Chris Lloyd as the works we're being conducted to discuss this specific project and the benefits of battery storage to the GB electricity system.