Incredible video. Hands down the best and most educational piece of content on the matter. You rock, Edward!
@ProjectManagementVideos2 жыл бұрын
Wow, thanks!
@ProjectManagementVideos Жыл бұрын
Hi...I would like to invite you to watch my latest video training series on PMI Risk Management Professional at kzbin.info/www/bejne/aJvYmo2Mirppaas Thank you for watching!
@sixsixbell5 ай бұрын
Great and insightful risk management breakdown... thank you Edward, you hit this at it's core.
@ProjectManagementVideos5 ай бұрын
You're very welcome and THANK YOU for watching and commenting!
@clevelandtradingwww91642 жыл бұрын
Amazing walk through on the risk register - I've liked and subscribed, recently got a new role as a ITPM and learning new techniques from your channel.
@ProjectManagementVideos2 жыл бұрын
Glad to hear that! Let me know when I can be of help.
@ProjectManagementVideos Жыл бұрын
Hi...I would like to invite you to watch my latest video training series on PMI Risk Management Professional at kzbin.info/www/bejne/aJvYmo2Mirppaas Thank you for watching!
@andrewgeorge56722 жыл бұрын
A very impressive lecture. I have seen this channel before. Thank you very much.
@ProjectManagementVideos2 жыл бұрын
Glad you liked it. And thanks for watching!
@ProjectManagementVideos Жыл бұрын
Hi...I would like to invite you to watch my latest video training series on PMI Risk Management Professional at kzbin.info/www/bejne/aJvYmo2Mirppaas Thank you for watching!
@Urmy9982 жыл бұрын
Amazing Explanation.Many Thanks. Guilda.
@ProjectManagementVideos2 жыл бұрын
Most welcome Guilda! Happy to hear from you. I am wondering if anyone will actually make it to the end of the video without jumping out or skipping. What do you think?
@Urmy9982 жыл бұрын
@@ProjectManagementVideos I hope every one will including me.I'm following all your series video on PMP and I'm so sure I will pass the exam and I will certainly keep learning from your rich experience and knowledge that you are willing to share. All my Respect.
@ProjectManagementVideos Жыл бұрын
Hi...I would like to invite you to watch my latest video training series on PMI Risk Management Professional at kzbin.info/www/bejne/aJvYmo2Mirppaas Thank you for watching!
@nadhiraal-habsi21702 жыл бұрын
Thank you for the information Edward. I have a question regarding residual risk column, do we fill up that after mitigation being implemented or we put the expected residual post mitigation
@ProjectManagementVideos2 жыл бұрын
You put the expected residual risk post mitigation. This is done in planning before executing on the mitigation plans
@ProjectManagementVideos Жыл бұрын
Hi...I would like to invite you to watch my latest video training series on PMI Risk Management Professional at kzbin.info/www/bejne/aJvYmo2Mirppaas Thank you for watching!
@debbiebutcher87612 жыл бұрын
Hi Edward, do you have anything on using parent risks?
@ProjectManagementVideos2 жыл бұрын
Not sure what you mean?
@debbiebutcher87612 жыл бұрын
Hi Edward, I have just watched your video and liked and subscribed....well done. One thing I need to be sure of is the following: my employer uses the risk assessment of probability x impact, but do not reduce the overall risk marking as the mitigation’s for that risk are achieved. So the risk marking remains the same until the all of the mitigation’s are cleared. I think this is incorrect and the risk marking should reduce as we progress through the process. Grateful for your response, and hope this makes sense. Kindest, Steve
@ProjectManagementVideos2 жыл бұрын
Hi Debbie…your employer should include columns to record the expected probability and impact of risks post mitigation. If either the P or I is reduced, the risk score and priority should also reduce. Doing this allows us to assess the current level of risk after we have completed some mitigation steps.
@ProjectManagementVideos Жыл бұрын
Hi...I would like to invite you to watch my latest video training series on PMI Risk Management Professional at kzbin.info/www/bejne/aJvYmo2Mirppaas Thank you for watching!
@Urmy9982 жыл бұрын
Dear Mr. Shehab Could kindly consider talking in details about WBS? I watched your video on WBS and learned a lot on how to develop one , could you tell us how to distract all possible statistical Reports and Diagramms? could you also please share with us an example or template of Risk Report? is it different from the Risk Register? Kind regards , Guilda..
@ProjectManagementVideos2 жыл бұрын
I will see what I can do. Thanks for the suggestion. The risk report would be different from the register, but probably extracted from it.
@alaaqat465 Жыл бұрын
Hello... thanks for your efforts.. this is of very much help for our study. I am unable to watch the videos starting the 21st.. any help is highly appreciated...
@ProjectManagementVideos Жыл бұрын
Hi. The remaining videos are for the members only. These are paid members. Membership fees help support the work I am going 🤓
@alaaqat465 Жыл бұрын
@@ProjectManagementVideos ok... thanks i think we should be members to get the maximum benefits of these valuable education 😉😉