Poetry in motion! Our first major milestone pour for the turbine hall pedestal foundation at Contact Energy Ltd's Tauhara Power Station went very smoothly.
That's 750 cubic metres or 1,800 tonnes of concrete pumped and placed, involving 126 truck movements, 126 concrete slump tests, and about 700 hours of work - phew!